ETA Engineering to Install Systems at 4 Subterranean Stops of Delhi Metro Silver line

Date:

Share post:

NEW DELHI (Metro Rail News): ETA Engineering Pvt. Ltd. was selected as the most cost-effective company to install the electrical and mechanical system, environment control system and tunnel ventilation system at four underground stops of the 23.622 km Silver Line (Line-10) of Delhi Metro.

Delhi Metro’s Phase 4 project in South Delhi, situated mainly beneath the surface, will join Aerocity to Tughalakabad via 16 stations, 12 of which will be built through civil packages DC-07 (Afcons Infrastructure), DC-08 (J Kumar Infraprojects) and DC-09 (Larsen & Toubro) below the ground.

In July 2022, DMRC called for tenders for contract DE-11, funded by Japan International Cooperation Agency (JICA). This contract had a 2.95-year deadline and an unknown estimate. When the technical bids were opened in October 2022, it was revealed that there were seven bidders.

Financial Bid Values

Firm Bid. (Rs. Crore)

ETA Engineering 183.61

Universal MEP Projects & Engineering Services 212.11

Efkon India 217.36

Sudhir Power 221.03

Blue Star 221.15

Larsen & Toubro (L&T). 240.07

Sterling And Wilson (SWPL). 259.18

DMRC’s Brief Scope includes Design verification, Detail engineering, SITC of Electrical and Mechanical system, DG set, Environment control system, Tunnel ventilation system and Building Management System for four underground stations of line-10 of Phase-IV of Delhi MRTS.

Since October 2022, an evaluation of the technical bid for a larger system package (DE-11) that includes seven underground and four elevated stations between Chhatarpur and Tughlakabad, similar to the existing line, has been underway.

LEAVE A REPLY

Please enter your comment!
Please enter your name here

This site uses Akismet to reduce spam. Learn how your comment data is processed.

spot_img

Related articles

Bullet Train Project Advances With Bridge Completion on Kaveri River

(Metro Rail News): Another milestone has been achieved in the Mumbai-Ahmedabad Bullet Train Project. On 25th August, NHSRCL...

Kolkata Metro Launches QR Ticketing System on a Trial Basis  

Stepping towards a more digitalised world, the Kolkata metro introduces a mobile-based QR ticketing system on trial Basis. On...

PM To Inaugurate Ahmedabad Metro’s 2nd Phase & Vande Metro On 16 September

(Metro Rail News): Gujarat residents are going to witness a significant development in the public transportation sector.  On 16 September,...

UPMRC Issues LOA to L&T for Agra Metro’s AGCC-07 Package 

Agra ( Metro Rail News): Recently, Larsen and Toubro (L&T) was awarded the package AGCC-07 for 15.09 km...