South Eastern Railway has issued bids for upgrading the electric traction system for the Kharagpur-Tatanagar section of the Kharagpur Division of South Eastern Railway.  

Tender Details 

Opening Date1 Jul 2025
Closing Date20 Aug 2025
EMD₹ 91,06,500
Tender IdSEROHE-KGP-TATA-2X25KV-RT-SER HQ-ELECTRICAL/SOUTH EASTERN RLY
Tender NoSEROHE-KGP-TATA-2X25KV-RT
Pre-Bid Conference Date25/07/2025

Contract Amount: Rs. 179 Cr 

Contract Duration: 24 Months

Contracts Scope of Work: Design, Supply, Erection, Testing and Commissioning for upgradation of Electric traction system from 1 x 25 KV to 2 x 25 KV traction system for Kharagpur-Tatanagar section of Kharagpur division of South Eastern Railway to meet 3000 MT loading target. 

The weekly brief metro & rail professionals read.

One email a week. We never share your address. Unsubscribe anytime.

Additionally, South Eastern Railway also floated a tender for two major Kavach contracts. The total combined value of both contracts stands at 419.79 crores.

  • Contract 1 included the Supply, Installation, Testing & Commissioning Of Kavach On Hun Routes (1040 Rkm), Including Associated Works On Section Of Kharagpur, Adra, Ranchi & Chakradharpur Division Of South Eastern Railway. 
  • The Contract 2 included The contract 2 included the Design, Supply, Erection, Testing & Commissioning Of 132 Kv Traction Substation, Sectioning & Paralleling Post (sps), And Sub Sectioning & Paralleling Post (ssps) In 2x25kv System On Muri-ranchi-tori Section Of Ranchi Division Of South Eastern Railway To Meet 3000mt.  

To know about the full details of Contracts, Click Here.

Join the Discussion

Have a correction, an on-the-ground update, or a question about this project? Engineers, operators and consultants across the metro, rail and RRTS sector read these threads.

Every comment is read by our editorial team before it appears.

Please enter your comment!
Please enter your name here