DELHI (Metro Rail News): Delhi Metro Rail Corporation (DMRC) has invited bids for electrical tender for the Delhi Metro Phase IV extension of the Red Line from Rithala to Kundli (Nathupur). The approximate cost of the work is ₹18.97 Crore and the time period for the completion of work is 18 months.
Tender Information
| Information | Details |
| Tender No. | D2EUD-05 |
| Approximate Cost of Work | 18.97 Cr. |
| Completion Period | 18 Months |
| Pre-Bid Meeting | July 28, 2026 (11:00 hrs.) |
| Bid Submission Opening | August 11, 2026 (09:00 hrs.) |
| Bid Submission Deadline | August 17, 2026 (15:00 hrs.) |
Scope of Work
The scope of work of the contract includes the supply, installation, testing & commissioning for shifting / raising the height of 400KV D/C Transmission Lines of PGCIL (NR-1) & DTL infringing near MCD’s WtE Bawana Plant in Rithala – Kundli (Nathupur) Corridor of Delhi Metro Phase-IV Project.
The weekly brief metro & rail professionals read.
About Rithala – Kundli (Nathupur) Corridor

The Red Line (Line 1) extension from Rithala to Kundli (Nathupur) is a part of the Delhi Metro Phase IV project. The proposed extension has a length of 26.463 km, with 21 stations. The Red Line was the first operational line of the Delhi Metro and with the proposed extension, it will surpass the length of 60 kilometers.