Home Latest News Mumbai Metro 2B: MMRDA Races to Install Final Three Girders at Juhu Circle for Andheri West-Saraswat Nagar Stretch

Mumbai Metro 2B: MMRDA Races to Install Final Three Girders at Juhu Circle for Andheri West-Saraswat Nagar Stretch

0
3
Mumbai Metro 2B: MMRDA Races to Install Final Three Girders at Juhu Circle for Andheri West-Saraswat Nagar Stretch
Representative image: DN Nagar station in Andheri West, where Mumbai Metro 2B will begin. Photo: Rupturestriker / Wikimedia Commons (CC BY-SA 4.0)
Listen to this story
0:00

MUMBAI (Metro Rail News): Mumbai Metro 2B is moving closer to its next opening, with the Mumbai Metropolitan Region Development Authority (MMRDA) racing to install the last three girders at Juhu Circle on the Andheri West to Saraswat Nagar stretch.

The 7.53 km stretch is about 75% complete and has a March 2027 deadline, The Times of India reported. The Juhu Circle girders are among the last major civil works left on this section of the line.

Mumbai Metro 2B Andheri West-Saraswat Nagar stretch at a glance

InformationDetails
LineMumbai Metro Line 2B (Yellow Line), DN Nagar to Mandale
StretchAndheri West (DN Nagar) to Saraswat Nagar
Length7.53 km
ProgressAbout 75% complete
Pending workLast three girders at Juhu Circle
DeadlineMarch 2027
AgencyMumbai Metropolitan Region Development Authority (MMRDA)
DN Nagar metro station building in Mumbai
DN Nagar station, which will link Line 2B with Lines 1 and 2A. Photo: Superfast1111 / Wikimedia Commons (CC BY-SA 4.0)

Why Juhu Circle has been slow

Juhu Circle is one of the busiest junctions in Andheri West, and girders there can only be lifted when traffic is held back. In August 2026, a crane broke down at the junction after a night of girder work for Metro 2B, leaving commuters stuck in queues nearly 2 km long. Chief Minister Devendra Fadnavis later told officials to plan a 12-hour Sunday road block if needed to finish the girder work near Juhu Circle.

Why it matters for commuters

Once open, this Mumbai Metro 2B stretch will give Juhu, Vile Parle and Santacruz residents a metro link that connects at DN Nagar with Line 1 (Versova-Ghatkopar) and Line 2A (Dahisar-DN Nagar), so passengers from the western suburbs can reach the Bandra-Kurla Complex and the eastern suburbs without changing to road transport.

Get the Daily Metro & Rail Brief

Join 125,000+ metro and rail professionals. Project updates, new tenders and contract awards from across India, in your inbox every day.

Free · One email a day · Unsubscribe anytime · We never share your address

MMRDA metro trains at Gundavali station in Mumbai
Representative image: MMRDA metro trains at Gundavali station on Line 7. Photo: Mumbaimetro / Wikimedia Commons (CC BY-SA 4.0)

About Mumbai Metro 2B

According to MMRDA, Line 2B runs 23.643 km from DN Nagar to Mandale with 20 stations. Its first section, from Mandale to Diamond Garden in Chembur, opened to passengers on 7 April 2026. The line will be completed in stages:

  • Mandale to Diamond Garden (Chembur): open since April 2026
  • Andheri West (DN Nagar) to Saraswat Nagar: 7.53 km, March 2027 target
  • Saraswat Nagar to Diamond Garden via Bandra-Kurla Complex and Kurla: under construction

Each section of Mumbai Metro 2B needs clearance from the Commissioner of Metro Rail Safety (CMRS) before passenger services can start.

Also Read: Mumbai Metro: MMRDA Targets Year-End Opening of Four More Line 9 Stations and Next Line 2B Stretch

mumbai metro line 9 trainRead nextMumbai Metro: MMRDA Targets Year-End Opening of Four More Line 9 Stations and Next Line 2B Stretch8 Nov 2026

Add Metro Rail News as a preferred source on Google

Join the Discussion

Have a correction, an on-the-ground update, or a question about this project? Engineers, operators and consultants across the metro, rail and RRTS sector read these threads.

Every comment is read by our editorial team before it appears.

Please enter your comment!
Please enter your name here