Home Latest News Siemens Receives LoA for Telecommunication System Contract Of Nagpur Metro Phase 2

Siemens Receives LoA for Telecommunication System Contract Of Nagpur Metro Phase 2

Siemens Receives LoA for Telecommunication System Contract Of Nagpur Metro Phase 2
Nagpur Metro
Listen to this story
0:00

Nagpur (Metro Rail News): Siemens Limited has received a Letter of Acceptance (LoA) from Maha-Metro for the telecommunication system contract for Nagpur Metro Phase 2. 

Screenshot 2025 05 30 104520

Bidding Process 

In 2024, Maha-Metro invited bids for this contract with a 994-day deadline. 

Technical bids were opened on 19 September 2024, revealing that 2 firms, Siemens Limited and L&T Technology Services Limited, have submitted bids for the contract. 

The technical evaluation of the submitted bids took place on 24 October 2024. 

Get the Daily Metro & Rail Brief

Join 125,000+ metro and rail professionals. Project updates, new tenders and contract awards from across India, in your inbox every day.

Free · One email a day · Unsubscribe anytime · We never share your address

On 25 October 2024, financial bids were opened, and the financial evaluation took place on 29  May 2025. During the financial evaluation, the L&T Technology Services Limited bid of ₹ 204.9 Cr got rejected. 

After the financial evaluation, Siemens Limited was declared the lowest bidder for the contract. On 29 May 2025, Siemens Limited received the Letter of Acceptance (LoA) for the telecommunication system contract for Nagpur Metro Phase 2. 

SponsoredInnoBus Conference & Expo 2026, 23 December 2026, Bharat Mandapam, New Delhi

Contract Details 

Siemen Bid Value: ₹ 197.9 Cr

Contract Duration: 994 Days

Scope of Work: Design, Supply, Installation, Testing & Commissioning of Telecommunication System For Nagpur Metro Rail Project Phase-2.

Project Overview

Nagpur Metro – Information, Route Map, Fares, Tenders & Updates

All corridors, status, routes and the latest news in one place →

Join the Discussion

Have a correction, an on-the-ground update, or a question about this project? Engineers, operators and consultants across the metro, rail and RRTS sector read these threads.

Every comment is read by our editorial team before it appears.

Please enter your comment!
Please enter your name here