M/S Sterling Wilson Receives LoA for Electrification Contract of Nagpur Metro Phase 2 

M/S Sterling Wilson Receives LoA for Electrification Contract of Nagpur Metro Phase 2 

Nagpur (Metro Rail News): M/S Sterling Wilson Pvt Ltd has received a Letter of Acceptance (LoA) from Maha-Metro for the electrification contract of Nagpur Metro Phase 2. 

Screenshot 2025 05 30 113134

Bidding Process 

In 2024, Maha-Metro invited bids for this contract with a 1260-day deadline.

Technical bids were opened on 9 August 2024, revealing that 6 firms have submitted bids for the contract. 

The technical evaluation of the submitted bids took place on 30 September 2024. 

The weekly brief metro & rail professionals read.

One email a week. We never share your address. Unsubscribe anytime.

On 1 October 2024, financial bids were opened, and the financial evaluation took place on 29  May 2025. 5 firms out of 6 got rejected during the financial evaluation. 

After the financial evaluation, M/S Sterling Wilson Pvt Ltd was declared the lowest bidder for the contract. 

On 29 May 2025, M/S Sterling Wilson Pvt Ltd received the LoA for the contract. 

Financial Bid Values 

Firms Bid Value 
M/S Sterling Wilson Pvt Ltd₹ 389.9 Cr 
BNC Power Projects Limited₹ 388.9 Cr 
Ircon International Limited₹ 508 Cr 
KEC International Limited₹ 397.8 Cr 
Larsen and Toubro Limited₹ 508 Cr 
Siemens Ltd₹ 413.5 Cr 

Contract Details 

M/S Sterling Wilson Bid Value: ₹ 389.9 Cr

Contract Duration:1260 Days

Scope of Work: Design, Supply, Installation, Testing & Commissioning of Receiving Cum Auxiliary Main Cum Traction Sub Stations Including EHV Connection From Grid Substation, 33 kV Cable Network, ASS & SCADA System For Nagpur Metro Rail Phase-2 Project.

Guide

Nagpur Metro: the complete guide

All corridors, status, routes and the latest news in one place →

Join the Discussion

Have a correction, an on-the-ground update, or a question about this project? Engineers, operators and consultants across the metro, rail and RRTS sector read these threads.

Every comment is read by our editorial team before it appears.

Please enter your comment!
Please enter your name here