Kolkata ( Metro Rail News ): Kolkata Metro progressed as successful trials were conducted on the under Construction Line 4 (Yellow Line ) spanning 16.876 km from Noapara to Barasat featuring 10 stations and Green Line .

GiEIlc9bcAAYkwR

About the Trials on Yellow Line 

1737455586355 21.01 1

On 24 January 2025, The trials were conducted on a 7.03  km stretch of Line 4 connecting Noapara and Jai Hind Biman Bandar (airport) metro stations through 4 stations. 

Station 

  • Noapara
  • Dum Dum Cantt
  • Jessore Road 
  • Biman Bandar
1737455573123 21.01 5

Metro Railway Kolkata General Manager P Uday Kumar Reddy was also present during the trials. During the trials,  P Uday Kumar Reddy also inspected the Dum Dum Cantonment station and  Jai Hind Biman Bandar Metro station. 

The weekly brief metro & rail professionals read.

One email a week. We never share your address. Unsubscribe anytime.

About the Trials on Green Line 

GhzhetnboAArRDJ

On 21 January 2025, The first trial run was conducted successfully o­n sealdah-esplanade stretch of green line spanning 2.63 km. 

Shri P. Uday Kumar Reddy, General Manager, Metro Railway and Chairman, Kolkata Metro Rail Corporation Limited (KMRCL), other senior officers of Metro Railway and KMRCL were present during the trials. 

GhzhekrbEAAr0Bu

Guide

Kolkata Metro: the complete guide

All corridors, status, routes and the latest news in one place →

Join the Discussion

Have a correction, an on-the-ground update, or a question about this project? Engineers, operators and consultants across the metro, rail and RRTS sector read these threads.

Every comment is read by our editorial team before it appears.

Please enter your comment!
Please enter your name here