Patna (Metro Rail News): The Patna Metro Phase 1 project is advancing at a rapid pace. Recently,  Larsen & Toubro (L&T) deployed Tunnel Boring Machine (TBM-1) at Patna University Metro Station on Line 2 (Patna Junction Railway Station- New ISBT) for underground Package PC-03. This package spans 8 km and connects Rajendra Nagar to Patna Junction Railway Station.

GPyq0WiaUAA576I
Image Credit: Patna Metro

This achievement comes about three months after TBM DZ1090, also known as TBM-1, achieved its first breakthrough at Patna University’s east shaft in March 2024. Over a period of 11 months, the TBM-1 constructed a 1494-meter tunnel for the down-line, starting from Moin-ul-Haq Station.

GPyqvDXbIAABORB
Image Credit: Patna Metro

After its first breakthrough, TBM-1 was moved from Patna University’s east shaft into its west shaft. Now L&T has deployed TBM-1 for its next assignment which involves constructing a 2302 m downline tunnel toward PMCH Station.

GPyqtENaEAAAqqv
Image Credit: Patna Metro

Patna Metro Phase 1’s Package PC-03

In December 2021, Larsen & Toubro (L&T) secured Package PC-03 from the Delhi Metro Rail Corporation (DMRC) at a cost of Rs. 1989 crore. The contract has a completion deadline of 42 months.

The weekly brief metro & rail professionals read.

One email a week. We never share your address. Unsubscribe anytime.

Scope of work

Package PC-03 will link a ramp near Rajendra Nagar with Patna Junction Railway Station. To facilitate this work L&T will design and construct a Twin Tunnel and six underground metro stations: Rajendra Nagar, Moin Ul Haq Stadium, University, PMCH, Gandhi Maidan, and Akashvani (formerly Dak Bungalow).

Advancements in Package PC-03

Till now L&T has achieved 2 Tunnel breakthroughs in Package PC-03. Both were recorded at Patna University Metro Station: The first in March for the down-line by TBM-1, and the second in May for the up-line by DZ1091, also known as Buddha.

Guide

Patna Metro: the complete guide

All corridors, status, routes and the latest news in one place →

Join the Discussion

Have a correction, an on-the-ground update, or a question about this project? Engineers, operators and consultants across the metro, rail and RRTS sector read these threads.

Every comment is read by our editorial team before it appears.

Please enter your comment!
Please enter your name here