TBM T61 provides a rapid pace to tunnelling work of Mumbai Metro Line-3

1
575
TBM T61 provides a rapid pace to tunnelling work of  Mumbai Metro Line-3
MMRC

MUMBAI (Metro Rail News): Tunnel Boring Machine (TBM) T61 nicknamed Tapi-1 operated by the J Kumar Infraprojects – China Railway Tunnel Group JV made a breakthrough at Chhatrapati Shivaji Maharaj International Airport’s Domestic Terminal-1 Station’s northern-end on Mumbai Metro’s 33.5 km Aqua-Line (Line-3).
This was T61’s second (and final) breakthrough, J Kumar – CRTG’s fifth (and penultimate) breakthrough for the 4.45km Santa Cruz Mid Ventilation Shaft – CSIA Terminal 2 Package UGC-06, and overall Mumbai Metro Line-3’s 31st TBM breakthrough.
This Ø6.68m dual-mode Terratec TBM had passed factory acceptance tests in September 2017 and arrived in the city in November 2017.

For its first assignment, it was commissioned as TBM Godavari-1 from Package UGC-05’s Vidyanagari Station to the Santa Cruz Mid Ventilation Shaft (dead-end of UGC-05/06) and onwards to CSIA’s Terminal-1 Station for building the 2895 meter up-line tunnel, and recorded a joint breakthrough for UGC-05 and UGC-06 in April 2019.
For its last assignment that ended today – the machine was commissioned from Sahar Road Station towards Terminal 1 in September 2019 to build the 1512 meter down-line tunnel.

Guide

Mumbai Metro: the complete guide

All corridors, status, routes and the latest news in one place →

1 COMMENT

Join the Discussion

Have a correction, an on-the-ground update, or a question about this project? Engineers, operators and consultants across the metro, rail and RRTS sector read these threads.

Every comment is read by our editorial team before it appears.

Please enter your comment!
Please enter your name here