TBM-1 Achieves Breakthrough at Chhatarpur Mandir Station of Delhi Metro’s Golden Line

Date:

Share post:

Delhi (Metro Rail News): On 21 August 2024, Delhi Metro Phase 4 reached another milestone as the TBM DZ1122 achieved a breakthrough at Chhatarpur Mandir Station of 23.622 km long Golden Line that will connect Aerocity-Tuglakabad through 15 stations.

1724227770897
TBM-1 Achieves Breakthrough at Chhatarpur Mandir Station of Delhi Metro’s Golden Line 3

This is TBM DZ1122’s second breakthrough and overall a 3rd breakthrough out of 10 breakthroughs planned in package DC-09 for the Delhi Metro Phase 4 project.

TBM DZ1122’s Journey in Delhi Metro Phase 4

  • For its second assignment, TBM DZ1122 (TBM-1) was deployed in January 2024 to start tunnelling from Chhatarpur station. The TBM reached Chhatarpur Mandir station covering a distance of 865 metres over the past roughly 7 months.
  • In its first assignment, TBM DZ 1122 constructed a 1267m tunnel from Chhatarpur station to Kishangarh station in 8 months which was completed in November 2023.  
  • TBM DZ1122 constructed 618 rings (1 ring = 1.4m) at an approximate depth of 15m. The machine streamed under the Yellow Line’s viaduct just south of the existing Chhatarpur Station particularly.
1724227771048
TBM-1 Achieves Breakthrough at Chhatarpur Mandir Station of Delhi Metro’s Golden Line 4

Package DC-09

As part of Golden Line, Package DC-09 connects Kishangarh and Saket G Block covering a total distance of 6.51km.

Larsen & Toubro secured the package DC-09 at Rs. within the Delhi Metro Phase 4 project in March 2022 with 42-month deadline. 

The final contract value: Rs. 1737 crores.

Scope of work

Under package DC-09,  Larsen & Toubro will be responsible for the construction of twin tunnels in the middle of Golden Line and will link Kishangarh station’s east end with a ramp west of Saket G Block station through 4 stations at Chhatarpur (interchange with Yellow Line), Chhatarpur Mandir, IGNOU and Neb Sarai. 

Ongoing Development 

L&T’s other 2 TBMs (DZ1124 and DZ1125) are constructing tunnel from Chhatarpur Mandir Station to IGNOU Station at present.

LEAVE A REPLY

Please enter your comment!
Please enter your name here

This site uses Akismet to reduce spam. Learn how your comment data is processed.

spot_img

Related articles

CLC Bridge Installed for Mumbai- Ahmedabad Bullet Train Project 

Surat ( Metro Rail News): This week, MG Contractors Pvt. Ltd. (MGCPL) achieved a milestone in the Mumbai...

KPIL – Gulermak JV Lowers Their 1st TBM At Rawatpur For Kanpur Metro Line 2

Kanpur (Metro Rail News): Another development has been waiting for the Kanpur Metro Project as Kalpataru Projects International...

PM Modi Shows Green Light To Mumbai Metro Line 3 (Aarey Colony-BKC) 

Mumbai (Metro Rail News): Prime Minister Narendra Modi has finally inaugurated the long-awaited Mumbai Metro Line 3 between Aarey...

NCRTC Initiates Train Trial Runs between Sahibabad & New Ashok Nagar RRTS Station

Delhi (Metro Rail News): The long-awaited Delhi Section of the Delhi Meerut RRTS corridor has finally advanced as...