TBM-1 Achieves Breakthrough at Chhatarpur Mandir Station of Delhi Metro’s Golden Line

Date:

Share post:

Delhi (Metro Rail News): On 21 August 2024, Delhi Metro Phase 4 reached another milestone as the TBM DZ1122 achieved a breakthrough at Chhatarpur Mandir Station of 23.622 km long Golden Line that will connect Aerocity-Tuglakabad through 15 stations.

1724227770897
TBM-1 Achieves Breakthrough at Chhatarpur Mandir Station of Delhi Metro’s Golden Line 3

This is TBM DZ1122’s second breakthrough and overall a 3rd breakthrough out of 10 breakthroughs planned in package DC-09 for the Delhi Metro Phase 4 project.

TBM DZ1122’s Journey in Delhi Metro Phase 4

  • For its second assignment, TBM DZ1122 (TBM-1) was deployed in January 2024 to start tunnelling from Chhatarpur station. The TBM reached Chhatarpur Mandir station covering a distance of 865 metres over the past roughly 7 months.
  • In its first assignment, TBM DZ 1122 constructed a 1267m tunnel from Chhatarpur station to Kishangarh station in 8 months which was completed in November 2023.  
  • TBM DZ1122 constructed 618 rings (1 ring = 1.4m) at an approximate depth of 15m. The machine streamed under the Yellow Line’s viaduct just south of the existing Chhatarpur Station particularly.
1724227771048
TBM-1 Achieves Breakthrough at Chhatarpur Mandir Station of Delhi Metro’s Golden Line 4

Package DC-09

As part of Golden Line, Package DC-09 connects Kishangarh and Saket G Block covering a total distance of 6.51km.

Larsen & Toubro secured the package DC-09 at Rs. within the Delhi Metro Phase 4 project in March 2022 with 42-month deadline. 

The final contract value: Rs. 1737 crores.

Scope of work

Under package DC-09,  Larsen & Toubro will be responsible for the construction of twin tunnels in the middle of Golden Line and will link Kishangarh station’s east end with a ramp west of Saket G Block station through 4 stations at Chhatarpur (interchange with Yellow Line), Chhatarpur Mandir, IGNOU and Neb Sarai. 

Ongoing Development 

L&T’s other 2 TBMs (DZ1124 and DZ1125) are constructing tunnel from Chhatarpur Mandir Station to IGNOU Station at present.

LEAVE A REPLY

Please enter your comment!
Please enter your name here

This site uses Akismet to reduce spam. Learn how your comment data is processed.

spot_img

Related articles

PM Modi Launches Vande Bharat Trains On 6 New Routes

Gujarat (Metro Rail News): On 15 September, Prime Minister Narendra Modi showed green light (virtually) to six new...

A Deep Dive Into Hyderabad-Vijayawada RRTS, PSD’s ,Train Depots And Railway Platforms

Project Approval and CostFacilities provided by train depot areasKey Components and Facilities:Specialised Workshops:Challenges Faced by Train Depots in...

Varanasi Metrolite Project: A Boost To The Economy

A Quick Tour to VaranasiNeed for Varanasi MetrolitePopulation GrowthRoad CongestionVaranasi Metrolite ProjectDPR ApprovedInfrastructure DetailsPartnership DetailsMetrolite OperationsLines of Varanasi...

Indore Metro Advances With Completion Of Pier Foundation On Super Corridor

Indore(Metro Rail News): Indore Metro project advanced as URC has finished casting all 142 open foundations and 235...