Surat Metro- TBM Narmada Completes Its Third Drive 

0
301
TBM Narmada final breakthrough Surat metro

Surat (Metro Rail News):Surat Metro project advances as TBM Narmada accomplishes Its last Breakthrough.

On 30 August 2024, Surat Metro witnessed another milestone on Line 1 when Gulermak – Sam India Builtwell JV’s TBM Narmada achieved its third and final breakthrough at Surat Railway Station for the Surat Metro Phase 1 Project.

TBM Narmada established the overall fifth and second-last breakthrough for Package CS2 / UG1. 

Binod Kumar
Image Credit: Binod Kumar

TBM Narmada’s Journey In Surat Metro Phase 1

First assignment Kapodra – Labheshwar Chowk.1.5km January 2024
Second assignment Labheshwar Chowk Station – Central Warehouse Station600m March 2024 
Current assignment Central Warehouse- Surat Railway Station.338m August 2024 

Note: The first breakthrough was still hidden as soil excavation is still in progress.

Antima
Image Credit: Antima

Package CS2 / UG1

In March 2021, Gulermak – Sam India JV grabbed underground Package CS2 / UG1’s construction contract, which spans 3.46 km connecting Kapodra station and Surat Railway Station. 

The scope of work under this package incorporates the construction of three twin tunnels and the 3 stations at ;

  • Kapodra
  •  Labheshwar Chowk
  •  Central Warehouse 

Surat Metro Phase 1 Project

Surat metro is an under construction Mass Rapid Transit System (MRTS) which spans 41.93 km, consisting of  2 corridors and 37 stations. 

Line 1 Sarthana station – Dream City station 22.77 km Total no. of stations: 20 

Line 2 
Bhesan station – Saroli station 19.26 km.Total  no. of stations:  18 