Mumbai Metro Line 7 (Red Line)

Operational Operator: Maha Mumbai Metro Operation Corporation Ltd (MMMOCL), the MMRDA-formed company that runs MMRDA's metro lines; MMRDA owns and built the line Length: 16.5 km Since: 02/04/2022 Updated: Official site ↗

As of 19 Oct 2026, Mumbai Metro Line 7 (Red Line) is operational (since 2 Apr 2022). Latest news: 14 Oct 2026.

Mumbai Metro Line 7, the Red Line, is a 16.5 km elevated metro along the Western Express Highway from Dahisar (East) to Gundavali in Andheri East, with 14 stations including the shared Dahisar (East) terminal. MMRDA built it and MMMOCL operates it. It has been fully open since January 2023. Distance-based fares run from ₹10, with ₹30 for the full length.

Why it matters

Line 7 runs parallel to the Western Express Highway, one of Mumbai's most congested roads, and gives the eastern side of the western suburbs, from Dahisar through Borivali East, Kandivali East, Malad East and Goregaon East, a rail option that the Western Railway suburban line does not provide. It links with Line 2A at Dahisar (East) and Line 1 at Gundavali, and is the spine of a longer corridor: Line 9 north to Mira-Bhayandar and Line 7A south to the airport.

Key facts

  • Operator: Maha Mumbai Metro Operation Corporation Ltd (MMMOCL), the MMRDA-formed company that runs MMRDA's metro lines; MMRDA owns and built the line
  • Length: 16.5 km, 14 stations
  • Status (October 2026): Fully operational (October 2026). Dahisar East to Aarey opened on 2 April 2022 and Goregaon East to Gundavali on 19 January 2023, completing the line. Its northern extension, Line 9, has been open from Dahisar East to Kashigaon since April 2026; the southern extension, Line 7A to the airport, is under construction.
  • Cost: About ₹6,208 crore (estimated project cost)
  • Trains: BEML 6-car trainsets, driverless-capable, shared with Line 2A
  • Ridership: No Line 7-only figure is published. Lines 2A and 7 together carried more than 2.5 lakh passengers a day (January 2025); the wider MMMOCL network of Lines 2A, 7, 9 and 2B averaged about 2.8 lakh journeys a day in 2026, with a record 3,58,115 on 23 June 2026.

Mumbai Metro Line 7 (Red Line) stations

The 14 stations below run from Dahisar (East) to Gundavali. Interchanges are listed where a station connects with another line or a railway station.

#StationTypeConnects to
1Dahisar (East)ElevatedLine 2A (Yellow) / Line 9 (Red, northern extension)
2OvaripadaElevated
3Rashtriya UdyanElevated
4DevipadaElevated
5MagathaneElevated
6PoisarElevated
7AkurliElevated
8KurarElevated
9DindoshiElevated
10AareyElevated
11Goregaon (East)Elevated
12Jogeshwari (East)ElevatedLine 6 (Pink, under construction)
13MograElevated
14GundavaliElevatedLine 1 (Blue) / Line 7A (under construction)

Sections and opening dates

SectionStationskmStatusOpened or expected
Dahisar (East) to Aarey10Operational2022-04-02
Aarey to Gundavali4Operational (Goregaon East, Jogeshwari East, Mogra, Gundavali)2023-01-19

Explore more

Official source: www.mmmocl.co.in

Latest updates

56 tenders tracked →

See all news & updates →

Phases

PhaseLinesStationsLength (km)Status
Dahisar (East) to AareyDahisar (East) to Aarey10Operational
Aarey to GundavaliAarey to Gundavali4Operational (Goregaon East, Jogeshwari East, Mogra, Gundavali)

Latest ridership: No Line 7-only figure is published. Lines 2A and 7 together carried more than 2.5 lakh passengers a day (January 2025); the wider MMMOCL network of Lines 2A, 7, 9 and 2B averaged about 2.8 lakh journeys a day in 2026, with a record 3,58,115 on 23 June 2026.

Milestones

  • MMRDA approves the detailed project report for an elevated Dahisar East to Andheri East line
  • Prime Minister Narendra Modi lays the foundation stone
  • Construction work begins
  • MMRDA cancels a ₹348 crore civil contract held by Simplex Infrastructure over slow progress
  • Trial runs flagged off on Lines 2A and 7
  • Dahisar (East) to Aarey opens to passengers, together with the first section of Line 2A
  • Prime Minister Narendra Modi dedicates the full Lines 2A and 7; Goregaon (East) to Gundavali opens, completing Line 7
  • Rail safety commissioner clears Lines 2A and 7 for full design speed of 80 km/h
  • Line 9 Phase 1, the northern extension from Dahisar East to Kashigaon, is inaugurated; passenger service from 8 April
  • Ten-day morning block (to 25 September) on Lines 2A, 7 and 9 for Line 9 Phase 2 signalling integration; first trains moved to 06:30

Fares

Mumbai Metro Line 7 (Red Line) fares range from ₹10 (up to 3 km) to ₹10 (up to 3 km), set by Maha Mumbai Metro Operation Corporation Ltd (MMMOCL), the MMRDA-formed company that runs MMRDA's metro lines; MMRDA owns and built the line.

Distance / zoneFare
Minimum fare₹10 (up to 3 km)

Frequently asked questions

What is the route of Mumbai Metro Line 7?

It runs about 16.5 km along the Western Express Highway from Dahisar (East) to Gundavali in Andheri East. The whole line is elevated.

How many stations are on Line 7?

14 stations including Dahisar (East), which it shares with Line 2A; MMMOCL counts 13 stations as its own.

When did Line 7 open?

Dahisar (East) to Aarey opened on 2 April 2022. The rest, Goregaon (East) to Gundavali, opened on 19 January 2023.

Who operates Mumbai Metro Line 7?

Maha Mumbai Metro Operation Corporation Ltd (MMMOCL) runs it. MMRDA planned and built the line and owns it.

Where can I change lines on Line 7?

At Dahisar (East) for Line 2A and Line 9, and at Gundavali for Line 1 (Versova to Ghatkopar). Jogeshwari (East) will connect to Line 6 once that line opens.

Does Line 7 go to the airport?

Not yet. Line 7A, a 3.42 km extension from Gundavali to Terminal 2 of Chhatrapati Shivaji Maharaj International Airport, is under construction and has no announced opening date.

What is the fare on Line 7?

Fares are distance based: ₹10 up to 3 km, ₹20 for 3 to 12 km and ₹30 for 12 to 18 km, so a full end-to-end trip costs ₹30.

Journey Planner & Route Map

Awarded tenders & contracts

No awarded tenders or contracts recorded yet.

Ongoing tenders

TenderAgencyValueBid dueStatus
MahaMetro invites maintenance tender for Navi Mumbai Metro Line-1 Maha MetroOpen
MRVC invites bids for electrification work in Borivali-Virar Section of Western RailwaysMRVCSubscribersUnder evaluation
Maha Metro floats Rs 3.54 cr tender for Navi Mumbai Metro Line 1 maintenanceMaha MetroSubscribersSubscribersUnder evaluation

Upcoming tenders

No upcoming tenders announced yet.