The Ahmedabad Metro Phase 2 project, which comprises two corridors covering a total distance of 28.254 km, was approved by the Indian Central Government's Cabinet on February 19, 2019. The estimated cost of the project is Rs. 5384.17 crores. Prime Minister Narendra Modi laid the foundation stone for the project on March 4, 2019. Phase 2 involves extending Line-2 from Motera Station to Mahatma Mandir in Gandhinagar.A notice inviting bids for civil construction was published in January 2020, technical bids were opened in June 2020, and construction work started in February 2021. Route map
The Ahmedabad Metro Phase 2 includes key figures such as 20.02 km under construction, 7.41 km approved, and 0 km proposed. While the GMRC's Phase 2 deadline has not been revealed, my estimate for completion is 2026.Phase 2 includes two routes: Line-2 (North-South/Red Line) and Line-3 (Eastern Spur). Line-2 is an elevated type route with a length of 22.838 km and a depot located in Indroda. It includes 20 stations with the following names: Koteshwar Road, Vishwakarma College, Tapovan Circle, Narmada Canal, Koba Circle, Juna Koba, Koba Gam, GNLU, Raysan, Randesan, Dholakuva Circle, Infocity, Sector-1, Sector-10A, Sachivalaya, Akshardham, Juna Sachivalaya, Sector-16, Sector-24, and Mahatma Mandir.Line-3 is also an elevated type route with a length of 5.416 km and includes three stations: Gujarat National Law University (GNLU), Pandit Deendayal Petroleum University (PDPU), and Gujarat International Finance Tec-City (GIFT City).The following is a list of major contractors involved in the construction of the Line-2 extension from Motera Stadium to Mahatma Mandir as part of the Ahmedabad Metro Phase 2 project:
The Ahmedabad Metro Phase 2 includes key figures such as 20.02 km under construction, 7.41 km approved, and 0 km proposed. While the GMRC's Phase 2 deadline has not been revealed, my estimate for completion is 2026.Phase 2 includes two routes: Line-2 (North-South/Red Line) and Line-3 (Eastern Spur). Line-2 is an elevated type route with a length of 22.838 km and a depot located in Indroda. It includes 20 stations with the following names: Koteshwar Road, Vishwakarma College, Tapovan Circle, Narmada Canal, Koba Circle, Juna Koba, Koba Gam, GNLU, Raysan, Randesan, Dholakuva Circle, Infocity, Sector-1, Sector-10A, Sachivalaya, Akshardham, Juna Sachivalaya, Sector-16, Sector-24, and Mahatma Mandir.Line-3 is also an elevated type route with a length of 5.416 km and includes three stations: Gujarat National Law University (GNLU), Pandit Deendayal Petroleum University (PDPU), and Gujarat International Finance Tec-City (GIFT City).The following is a list of major contractors involved in the construction of the Line-2 extension from Motera Stadium to Mahatma Mandir as part of the Ahmedabad Metro Phase 2 project:- ଲାଇନ-2 ସମ୍ପ୍ରସାରଣ ଏବଂ ଭାୟାଡକ୍ଟର ବିସ୍ତୃତ ଡିଜାଇନ୍ ପରାମର୍ଶଦାତା (ଡି. ଡି. ସି.) ଙ୍କ ପାଇଁ, 22ଟି ଷ୍ଟେସନ ଏବଂ ଡିପୋ ଭୂ-ବୈଷୟିକ ଅନୁସନ୍ଧାନ, ଏସ୍. ଆଇ. ଏସ୍. ଟି. ଆର୍. ଏ.-ଏସ୍. ଆଇ. ଏସ୍. ଟି. ଆର୍. ଏ. ଏମ୍. ଭି. ଏ. କନସଲ୍ଟିଙ୍ଗ୍ (ଇଣ୍ଡିଆ) ପ୍ରାଇଭେଟ୍ ଲିମିଟେଡ୍। ଜେ. ଭି. ଏବଂ ଏମ୍. କେ. ମୃତ୍ତିକା ପରୀକ୍ଷଣ ପରୀକ୍ଷାଗାରକୁ ଯଥାକ୍ରମେ ଚୟନ କରାଯାଇଥିଲା।
- ବିଦ୍ୟୁତ୍ ଯୋଗାଣ ଏବଂ ବିତରଣ ବ୍ୟବସ୍ଥା, 750 ଭି. ଡି. ସି. ତୃତୀୟ ରେଳ କର୍ଷଣ ବିଦ୍ୟୁତକରଣ, ଏବଂ ଏସ. ସି. ଏ. ଡି. ଏ. ବ୍ୟବସ୍ଥା ପାଇଁ ଡି. ଡି. ସି. ଭାବେ ଆର୍ଡାନୁଇ ଇଞ୍ଜେନିଏରିଆ ଏସ. ଏ. କୁ ଚୟନ କରାଯାଇଥିଲା।
- ସିଭିଲ୍ ପ୍ୟାକେଜ୍ ସି1, ଯେଉଁଥିରେ ମୋଟେରାରୁ ଜି. ଏନ୍. ଏଲ୍. ୟୁ. (8.124 କି. ମି.) ପର୍ଯ୍ୟନ୍ତ ଭାୟାଡକ୍ଟ ଏବଂ ଜି. ଏନ୍. ଏଲ୍. ୟୁ. ରୁ ଜି. ଆଇ. ଏଫ୍. ଟି. ସିଟି (5.420 କି. ମି.) ପର୍ଯ୍ୟନ୍ତ 10ଟି ଷ୍ଟେସନ ରହିଛି, ତାହା ଏଫ୍କନ୍ସ ଇନଫ୍ରାଷ୍ଟ୍ରକ୍ଚରକୁ ପ୍ରଦାନ କରାଯାଇଥିଲା।
- ସିଭିଲ୍ ପ୍ୟାକେଜ୍ ସି2, ଯାହା ଜି. ଏନ୍. ଏଲ୍. ୟୁ. ରୁ ଗାନ୍ଧୀନଗର ସେକ୍ଟର-1 (6.478 କି. ମି.) ପର୍ଯ୍ୟନ୍ତ 5ଟି ଷ୍ଟେସନ ସହିତ ଭାୟାଡକ୍ଟକୁ ଅନ୍ତର୍ଭୁକ୍ତ କରେ, ରଣଜିତ ବିଲ୍ଡକନଙ୍କୁ ପ୍ରଦାନ କରାଯାଇଥିଲା।
- ସିଭିଲ୍ ପ୍ୟାକେଜ୍ ସି3, ଯେଉଁଥିରେ 7ଟି ଷ୍ଟେସନ ସହିତ ସେକ୍ଟର-1ରୁ ମହାତ୍ମା ମନ୍ଦିର ପର୍ଯ୍ୟନ୍ତ ଭାୟାଡକ୍ଟ ରହିଛି, ଦିଲୀପ ବିଲ୍ଡକନଙ୍କୁ ପ୍ରଦାନ କରାଯାଇଥିଲା, ଯିଏ ସର୍ବନିମ୍ନ ନିଲାମ ଦାଖଲ କରିଥିଲେ।
- 30ଟି କୋଚ୍ ପାଇଁ ରୋଲିଂ ଷ୍ଟକ୍ ପ୍ୟାକେଜ୍ ଆର୍. ଏସ୍. 3 ପାଇଁ ଏପ୍ରିଲ୍ 2022ରେ ଟେଣ୍ଡର ଆହ୍ୱାନ କରାଯାଇଥିଲା।
- ବିଦ୍ୟୁତକରଣ ପ୍ୟାକେଜ ଇ. ପି. 2 ପାଇଁ ସିମେନ୍ସ ସର୍ବନିମ୍ନ ନିବେଶକ ଥିଲା, ଯେଉଁଥିରେ 750 ଭି. ଡି. ସି. ତୃତୀୟ ରେଳ ଅନ୍ତର୍ଭୁକ୍ତ।
- ଭି. ଏନ୍. ସି.-କେ. ଇ. ସି.-ଏମ୍ରେଲ୍ ଜେ. ଭି. କୁ ଟ୍ରାକ୍-ୱାର୍କ ପ୍ୟାକେଜ୍ ପାଇଁ ସର୍ବନିମ୍ନ ନିବେଶକ ଭାବରେ ଚୟନ କରାଯାଇଥିଲା, ଯେଉଁଥିରେ ବାଲାଷ୍ଟଲେସ୍ ଟ୍ରାକ୍ର ଡିଜାଇନ୍, ଯୋଗାଣ, ସ୍ଥାପନ, ପରୀକ୍ଷା ଏବଂ କାର୍ଯ୍ୟକ୍ଷମ କରିବା ଅନ୍ତର୍ଭୁକ୍ତ | ଏହି ଠିକାଦାରମାନେ ଲାଇନ-2 ସମ୍ପ୍ରସାରଣ ନିର୍ମାଣରେ ଏକ ଗୁରୁତ୍ୱପୂର୍ଣ୍ଣ ଭୂମିକା ଗ୍ରହଣ କରନ୍ତି, ଏବଂ ସେମାନଙ୍କର ପ୍ରୟାସ ଆଶା କରାଯାଉଥିବା ସମୟ ସୀମା ମଧ୍ୟରେ ପ୍ରକଳ୍ପକୁ ସମ୍ପୂର୍ଣ୍ଣ କରିବାରେ ସହାୟକ ହେବ।