Noida Metro: Information, Route Maps & Project Updates

AN OVERVIEW

Noida Metro is a Mass Rapid Transit System (MRTS) with a single line including 21 stations made and operated by the Noida Metro Rail Co. to serve Delhi’s suburbs between Noida & Greater Noida. The completion cost of the project is Rs. 5,503 cr.

Noida Metro Line-1 construction of 29.7 km elevated, began in May 2015 and started its commercial operations on 25 Jan 2019.

Line-1 extension from Sector 52-Knowledge Park V with a distance of 14.95 km with an expected cost of Rs. 2,682 cr, approved by Uttar Pradesh govt in December 2019.

Noida Metro (Operational)

• Aqua Line – Sector 51 to Greater Noida Depot (Line-1)
• Total Distance
– 29.7 km
• Expected Cost – Rs. 5,503 crore
• Station Type – Elevated
• Station Names – Noida Sector-51, Sector-50, Sector-76, Sector-101, Sector-81, NSEZ, Sector-83, Sector-137, Sector-142, Sector-143, Sector-144, Sector-146, Sector-147, Sector-148 in Noida and Knowledge Park II, Pari Chowk, Alpha-1, Delta-1, GNIDA Office and Depot stations in Greater Noida.

• Phase 1 – Sector 51 – Greater Noida Sector-2
• Total Distance – 9.605 km
• Stations Name – Noida Sector 122, Noida Sector 123, Greater Noida Sector 4, Ecotech 12 and Greater Noida Sector 2
• Phase 2 – Greater Noida Sector-2 to Knowledge Park V
• Total Distance – 5.8 km
• Stations Name – Greater Noida Sector 3, Sector 10, Sector 12 and Knowledge Park V

Proposed Line of Noida Metro

• Extension of Line-1 – From Depot Station to Chamrawali Bodaki
• Total Distance – 3.5 km
New Line – From Sector 142 to Botanical Garden
• Total Distance – 11.504 km
• Station Type – Elevated
• New Line – From Greater Noida Knowledge Park II to Jewar Airport
• Total Distance – 53.95 km
• Station Type – Elevated

Contractors of Noida Metro

• Siemens – OHE & SCADA System
• AYESA – Detailed Design Consultant
• DMRC – Project Executor
• CRRC – (Rolling Stock) 76 Coaches
• CEC-SAM India – Construction of viaduct and eight stations from Sector 71 to 137, Construction of viaduct and seven stations from Sector 142 to 149, Construction of viaduct and six stations from Knowledge Park II-Depot
• Ansaldo STS – ZTE Corporation – ZTE Telecom – CBTC Signalling and Telecommunication Systems
• Anupam Constructions – Construction of Depot & Workshop Buildings
• Jindal Buildsys – Design, Fabrication & Erection of Pre-engineered Steel Buildings at Depot

Total Length:             29.7 km (18.5 mi).
Aqua-Line -Noida City Centre- Depot Station – 29.7 km (22 Stations)

Estimated Project Cost:       INR 5,064 crore.

Major Contract Awarded

  • Contract NCDD-01: Ayesa India Pvt. Ltd. appointed as Detailed Design Consultant for 21 elevated stations.
  • Contract NRS1: Chinese firm CRRC Nanjing Puzhen awarded contract for supply of standard gauge 76 coaches (Rolling Stock).
  • Contract NE-01/02: Siemens for providing Overhead Electrification & SCADA system.
  • Contract NS01: A Joint Venture (JV) consortium of Ansaldo STS – ZTE Corporation – ZTE Telecom for providing CBTC Signalling and Telecommunication Systems
  • Contract NC-01: A Joint Venture (JV) consortium of CEC – SAM India Build Well for construction of viaduct & 8 stations from Noida Sector 71 to Sector 137.
  • Contract NC-02: A Joint Venture (JV) consortium of CEC – SAM India Build Well for construction of viaduct & 7 stations from Noida Sector 142 to Sector 149.
  • Contract NC-03: A Joint Venture (JV) consortium of CEC – SAM India Build Well for construction of viaduct & 6 stations from Knowledge Park-II to Delta Depot.
  • Contract NC-04: Anupam Construction Company for construction of Depot & Workshop Buildings.
  • Contract NC-05: Jindal Buildsys Limited for design, fabrication & erection of Pre-engineered Steel Buildings at Depot.

Important Dates:

  • Oct 2014: UP Government approves the metro project.
  • Nov 2015: 700 piles (pillar foundation) out of total 5000 has been made.