KOLKATA (Metro Rail News): West Bengal Chief Minister Suvendu Adhikari has asked Railway Minister Ashwini Vaishnaw to arrange the inauguration of the Kolkata Metro’s New Garia-Sector V line extension at the earliest, during a meeting at Rail Bhavan in New Delhi on 19 November. Chief Secretary Manoj Agarwal accompanied him.
Adhikari called the meeting fruitful and said the Railway Minister has always been positive towards West Bengal. The state wants Prime Minister Narendra Modi to inaugurate the metro stretch, on a date to be set by the Prime Minister’s Office.
Kolkata Metro Sector V stretch ready, awaits opening
The extension of the Orange Line from Beleghata to IT Centre in Sector V had been held up for years by a 700-metre stretch at Chingrighata. Adhikari said the bottleneck has been resolved, construction is complete and trial runs have been held.
According to the Railway Ministry, the West Bengal government allowed the temporary traffic diversion at the Chingrighata crossing, needed to launch the Kolkata Metro viaduct segments, in May 2026, about one and a half years after it was first sought, and the crossing work was completed the same month.
Get the Daily Metro & Rail Brief
Join 125,000+ metro and rail professionals. Project updates, new tenders and contract awards from across India, in your inbox every day.
The section is about 4.5 km long and adds three stations, Gour Kishore Ghosh (Chingrighata), Nalban and IT Centre, linking Salt Lake’s Sector V IT hub with New Garia on the southern side of the city. Metro Railway, Kolkata officials have said commercial services are expected by December, after the remaining safety approvals.

Other projects discussed
| Project | What was discussed |
| New Garia-Sector V Metro (Orange Line) | Early inauguration sought; construction and trials complete |
| Hili and Nandigram-Deshapran rail lines | Land issues resolved; services sought by March 2027 |
| Gangasagar rail link (Kapil Muni Ashram) | About ₹4,000 crore; survey and DPR to be expedited |
| Pending railway projects in Bengal | Budget allocation sought for projects already approved by the Railway Board |
| Freight | More goods rakes sought for industry and trade |
| Monitoring | A special officer appointed to oversee rail projects in the state |
Adhikari said steps would be taken to speed up the survey and detailed project report for a rail link to Gangasagar, the site of the annual Gangasagar Mela, with the aim of extending rail connectivity there within the next few years. ETV Bharat reported that the Railway Ministry has already prepared a preliminary plan and that the link may cost about ₹4,000 crore, while the Millennium Post said around ₹4,000 crore has been allocated.
On pending projects, the reports differ. The Millennium Post quoted Adhikari as saying 17 railway projects in Bengal have been approved, while ETV Bharat reported that he raised 19 state projects that already have Railway Board approval but remain stalled, and asked for enough funds for them in the coming Union Budget. Adhikari said the state has issued the required no-objection certificates, so land acquisition and surveys face no hurdles. The ministry has also named a special officer to monitor railway projects in West Bengal.

Bengal’s ₹83,433 crore rail pipeline
Beyond the Kolkata Metro, the meeting comes against a large backlog of sanctioned work. In a written reply in the Lok Sabha on 12 August 2026, Vaishnaw said that, as on 1 April 2026, 63 railway projects falling fully or partly in West Bengal were sanctioned, covering 5,148 km at a cost of ₹83,433 crore.
| Information | Details |
| Sanctioned projects (as on 1 April 2026) | 63: 14 new lines, 4 gauge conversions, 45 doublings |
| Length | 5,148 km |
| Cost | ₹83,433 crore |
| Rail budget for West Bengal, 2026-27 | ₹14,205 crore, more than 3 times the 2009-14 average of ₹4,380 crore a year |
| Road over and under bridges in progress | 363 works, about ₹8,060 crore |
| Project monitoring | State task force under the Chief Secretary |
Overview: at ₹14,205 crore a year, this year’s budget for the state is about 17% of the ₹83,433 crore cost of the sanctioned projects, which is why the state is pressing for bigger allocations in the coming Union Budget.
Why it matters
Once the Kolkata Metro reaches Sector V, office-goers from south and east Kolkata will get a direct metro link to the city’s biggest IT hub, with one report estimating that New Garia to Sector V could take about 30 minutes. In October, Adhikari had already urged Vaishnaw to secure an early date from the Prime Minister for the opening.
Earlier the same day, Adhikari met Union Home Minister Amit Shah in New Delhi.
Also Read: Kolkata Metro Orange Line to Become Driverless Once the Stretch Extends till Sector V
Read nextKolkata Metro Orange Line: Beleghata-IT Centre Stretch Cleared for Electrical Works After Track Inspection21 Sep 2026Get alerts for big metro and rail stories Openings, trials, fares and approvals. Two or three a day at most; turn them off any time.