Chennai Metro Phase 2: Ullagaram-Sholinganallur Package Completes Casting of 3,126 Precast Elements

Chennai Metro Phase 2: Ullagaram-Sholinganallur Package Completes Casting of 3,126 Precast Elements
Successful completion of precasting on Ullagaram-Sholinganallur Section

This article has not been translated yet, so the English original is shown below. Translate now (takes a few seconds).

CHENNAI (Metro Rail News): Chennai Metro Rail Limited (CMRL) has completed casting all precast elements for the Corridor 5 Package between Ullagaram-Sholinganallur, including its final U-girder. The milestone shifted the focus to installing the remaining girders and completing station entry and exit structures on this elevated stretch of Chennai Metro Phase 2. 

The ECV-03 package is being executed by the HCC-KEC Consortium, with design and construction oversight from General Consultant AEON Consortium.

U-Girder production reaches 892 units 

The package has produced 3,126 elements, covering the major structural components required for the Chennai Metro Phase 2 elevated corridor. The detailed inventory includes:

Get the Daily Metro & Rail Brief

Join 125,000+ metro and rail professionals. Project updates, new tenders and contract awards from across India, in your inbox every day.

Free · One email a day · Unsubscribe anytime · We never share your address

  • 1,041 I-Girder
  • 892 U-Girder
  • 871 Pier Arm Segment
  • 303 Pier Cap
  • 19 Portal Shell 

CMRL said the 892 U-Girder represents the highest quantity used in this project as compared to other projects under Phase-2. U-Girders from the main elevated deck structure that carries metro tracks, making their production a key part of preparing the viaduct for installation. 

Concrete and steel use reflects construction scale

The precast programme involves substantial material consumption across the casting operations. The reported quantities includes:

SponsoredInnoBus Conference & Expo 2026, 23 December 2026, Bharat Mandapam, New Delhi
Material Quantity Used 
Concrete98,052 Cubic Meters 
Reinforcement steel 18,550 MT
High-Tensile (HT) Strands3,010 MT

The milestone was marked by the officials from CMRL, AEON Consortium and the HCC-KEC Consortium. Those presents included CMRL Director (Projects) Thiru. T. Archunan, Additional General Manager, R. Srinivasan,  AEON Resident Engineer M.P. Muthaiya, Thiru. Jaideep Rajeshwarkar, Senior VP & BU Head, HCC-KEC Consortium; Thiru. Lalichan Antony, Project Manager; Thiru. Hari Krishna, Casting Yard In-charge; along with other project personnel. 

Driven by strategic vision and leadership 

Following the successful casting of the final U-Girder, the project shifted towards the erection of remaining U-Girders and construction of entry/exit structures. These critical works are actively progressing towards the compilation of Chennai Metro phase-2 project. 

A collaborative effort behind these achievements are the team who have a strategic vision and leadership quality to make this milestone with 100% successful compilation of all Precast Element and U-Girder casting.  

Also Read: Alstom powers Chennai Metro Phase II with its driverless Metropolis trainsets

Project Overview

Chennai Metro – Information, Route Map, Fares, Tenders & Updates

All corridors, status, routes and the latest news in one place →

Join the Discussion

Have a correction, an on-the-ground update, or a question about this project? Engineers, operators and consultants across the metro, rail and RRTS sector read these threads.

Every comment is read by our editorial team before it appears.

Please enter your comment!
Please enter your name here