Delhi Metro Phase 4: All Three Priority Corridors likely to be Operational by 2026

Date:

Share post:

New Delhi (Metro Rail News): The Delhi Metro Rail Corporation (DMRC) is progressing rapidly with its Phase 4 expansion work with the target of opening all three priority corridors comprising 65 kilometres of new lines by 2026. Though work on the fourth phase of expansion started in December 2019, immediately after the finalization of tenders, progress of work was significantly impacted from 2020 to 2022 for almost three years due to the Covid pandemic and delays in getting tree-cutting permissions.

GRTQ3fxakAAb1t2
Image Credit: DMRC

DMRC has been working continuously on the Phase 4 project practically since the last one and a half – two years only, which gives the organisation just about four years’ time to complete the entire work by the year 2026. 

Progress in Delhi Metro’s Phase IV

At present, over 50 percent progress has already been achieved on all three corridors. On the Majlis Park – Maujpur section, about 80 percent of civil work has already been completed. Tunneling works are in progress on various stretches on the Aerocity – Tughlakabad (Golden Line) and the Janakpuri West – RK Ashram Marg (Magenta Line) corridors.

GRTQ3fcW4AAPMDH
Image Credit: DMRC

Despite the adverse situation of COVID-19 and the delay in various permissions, the Phase 4 section from Janakpuri West to Krishna Park Extension is now almost complete and is likely to be opened by August 2024. The Majlis Park – Maujpur corridor is also likely to be opened during the next year. The rest of the sections of the priority corridors are expected to be opened in a phased manner by 2026.  However, certain permissions for tree cutting and the acquisition of land pockets at isolated locations are still awaiting approval.

GRTQ3fUWcAAlZhY
Image Credit: DMRC

The project is being monitored at various levels on a day-to-day basis. Site visits are also taken up at the highest level to expedite the work. Tree-cutting permissions are being pursued at appropriate levels.

The Addition of 2 New Corridors

Two more corridors under Phase 4, Inderlok – Indraprastha and Saket G Block – Lajpat Nagar have also received approval recently. DMRC at present is processing for statutory clearances including land acquisition from the concerned authorities. Forest clearances and tree-cutting permissions are also being taken up at the appropriate levels. Further processes regarding the planning and tendering for civil works are in progress.

LEAVE A REPLY

Please enter your comment!
Please enter your name here

This site uses Akismet to reduce spam. Learn how your comment data is processed.

spot_img

Related articles

Kolkata Metro: L&T Begins Construction of D-Wall for Launching Shaft on Mominpur-Esplanade Section

Kolkata (Metro Rail News): Construction work on the Purple Line beyond Majerhat station has got a major boost...

Kanpur Metro: Ceigall Initiates Pilling on Line 2 Under Package KNPCC-12

On July 1, Ceigall India successfully completed drilling and concreting the first pile on Kanpur Metro’s 8.38 km...

Delhi Metro’s Golden Line & Violet Line to have an Interchange at Tughlakabad Station

New Delhi (Metro Rail News): On July 1, the Delhi Metro Rail Corporation (DMRC) announced that as part...

Shri Shalabh Goel Appointed as the Managing Director of NCRTC

New Delhi (Metro Rail News): On 2nd July 2024, Shri Shalabh Goel (IRSEE) assumed the role of Managing...