NEW DELHI (Metro Rail News): In a major step towards progress in the execution of the Mumbai Ahmedabad High-Speed Rail (MAHSR) Project, NHSRCL has signed a contract agreement with M/s Sojitz & L&T Consortium for executing Electrical works under the EW-1 package in the presence of MD/NHSRCL, Directors, seniors officers of NHSRCL and representatives from MLIT Japan (Ministry of Land, Infrastructure, Transport and Tourism), JICA (Japan International Cooperation Agency), Japanese embassy and Japan HSR Electric Engineering Company.
The signing of the contract agreement sets a benchmark for enhanced collaboration for India’s first bullet train operation based on the Japanese Shinkansen technology.
EW-1 works include the Design, Manufacture, Supply, Construction, Installation, Testing and Commissioning of 2 x 25 kV Electrification Systems suitable for speeds up to 320 km/h, involving Japanese Shinkansen system-based traction power supply.
They include Traction Substations (TSS) -14 Nos., Sectioning Post (SP)- 11 Nos., Sub-Sectioning Post (SSP)- 19 Nos., and Auto Transformer Post (ATP)- 1 No., Overhead Equipment (OHE): Mainline: 508 route km, double line and three depots: Surat, Sabarmati & Thane, Elaborate Distribution System with an 11 kV backbone and more than 125 substations and Associated Civil Utility Buildings, Training Institute Equipment, etc. for the entire MAHSR corridor of around 508 kms.
Discover the endless possibilities of our city’s Metro at InnoMetro, our flagship Expo and Conference. Be an active participant in shaping its future towards a more sustainable tomorrow. Stay informed and join us to take a step towards a brighter future.
Project OverviewHigh-Speed Rail in India – Information, Route Map, Fares, Tenders & Updates
Read nextMumbai-Ahmedabad Bullet Train: All 14 Portal Beams Installed Over Rajdhani Route in Vadodara15 Oct 2026Get alerts for big metro and rail stories Openings, trials, fares and approvals. Two or three a day at most; turn them off any time.