BENGALURU (Metro Rail News): Bangalore Metro Rail Corporation Limited (BMRCL) has started trial runs on the Blue Line’s Outer Ring Road (ORR) corridor, running a test train over about 6 km of the mainline viaduct between the Baiyappanahalli depot and Doddanekundi station on 10 November 2026. The route passes through KR Puram.

Bengaluru Development Minister Krishna Byre Gowda said the 58.19-km Blue Line, which will connect Central Silk Board with Kempegowda International Airport via KR Puram and Hebbal, has moved a step closer to mainline testing.

“Our government is committed to completing all pending works and ensuring the Blue Line is opened to the public at the earliest, strengthening Bengaluru’s connectivity and transforming urban mobility,” Gowda said in a post on X.

Blue Line trial run on the mainline viaduct, 10 November 2026. Video: Ashok Siva via BLR Metro Tracker.

Marathahalli Target and Pending Work

BMRCL aims to extend the trial runs from the depot via KR Puram to Marathahalli by 15 November. The 33 kV cables and third rail between the depot and Marathahalli have been charged in stages since 30 October.

Get the Daily Metro & Rail Brief

Join 125,000+ metro and rail professionals. Project updates, new tenders and contract awards from across India, in your inbox every day.

Free · One email a day · Unsubscribe anytime · We never share your address

Signalling integration is the main item left before full testing can begin. About 2 km of track installation and some station work also remain on the corridor, according to reports. In August, the Railway Board gave in-principle approval for CBTC signalling on the Blue and Pink lines.

BMRCL officials with a Bengaluru Metro Blue Line train during the trial run
BMRCL officials with a Blue Line train during the trial run on 10 November 2026.

Opening Timeline

Reports put the opening of the 19.75-km Phase 2A section between Central Silk Board and KR Puram in mid-2027. In August, Gowda moved the target for the full Blue Line to the airport to March 2028, from December 2027, citing pending work at Marathahalli, Silk Board and Hebbal.

The trials come days before Prime Minister Narendra Modi inaugurates the Pink Line’s elevated Kalena Agrahara-Tavarekere stretch on 13 November, which will take Bengaluru’s operational metro network to 103.6 km.

Also Read: Bengaluru Metro Blue Line Opening Pushed to March 2028, Airport Link Faces Further Delay

Untitled design 29Read nextBengaluru Metro Blue Line Opening Pushed to March 2028, Airport Link Faces Further Delay24 Aug 2026

Add Metro Rail News as a preferred source on Google

Join the Discussion

Have a correction, an on-the-ground update, or a question about this project? Engineers, operators and consultants across the metro, rail and RRTS sector read these threads.

Every comment is read by our editorial team before it appears.

Please enter your comment!
Please enter your name here