Bengaluru Metro Pink Line: BMRCL Seeks CMRS Nod to Start Underground Trials up to Shivajinagar

3 min read
0
1
Bengaluru Metro Pink Line: BMRCL Seeks CMRS Nod to Start Underground Trials up to Shivajinagar
Dairy Circle, the first underground station on the Bengaluru Metro Pink Line after the elevated section, in April 2026. Photo: Sameer2905 / Wikimedia Commons (CC BY-SA 4.0)
Listen to this story
0:00

BENGALURU (Metro Rail News): Bengaluru Metro Pink Line trial runs on the 13.76 km underground section can begin as soon as the Commissioner of Metro Railway Safety (CMRS) grants a minor sanction, Bangalore Metro Rail Corporation Limited (BMRCL) has said, a week after the line’s elevated section opened.

“We have applied for minor sanction from CMRS to remove the buffer barrier at the end of the elevated section (SG Palya). Once it is received, trials can start. We are ready to start any time up to Shivajinagar station,” BMRCL Managing Director PC Jaffer told Moneycontrol.

Bengaluru Metro Pink Line underground section: where work stands

The Bengaluru Metro Pink Line underground section runs from Dairy Circle to Nagawara with 12 stations, including MG Road, Shivajinagar and Cantonment. The first trials would run from SG Palya, the end of the elevated stretch, into the tunnel towards Shivajinagar.

  • Platform screen doors: Materials for 10 of the 12 underground stations have been shipped.
  • Three stations nearly done: Only the glass panels of the screen doors remain to be fitted.
  • Target: BMRCL is aiming to open the underground section in May 2027.
Bengaluru Metro Pink Line elevated section at Kalena Agrahara station
Kalena Agrahara, the southern end of the Pink Line’s elevated section. Photo: Sameer2905 / Wikimedia Commons (CC BY-SA 4.0)

Elevated section ridership and late-night advisory

Prime Minister Narendra Modi inaugurated the 7.5 km elevated section from Kalena Agrahara to SG Palya on 13 November. It now carries about 33,000 passengers a day, after 33,409 commuters on its first day.

Get the Daily Metro & Rail Brief

Join 125,000+ metro and rail professionals. Project updates, new tenders and contract awards from across India, in your inbox every day.

Free · One email a day · Unsubscribe anytime · We never share your address

BMRCL has asked commuters not to book QR tickets that need a transfer to the Bengaluru Metro Pink Line after 10.45 pm, as no connecting trains are available at the Jayadeva interchange after that time. The last trains leave Kalena Agrahara at 10.50 pm and SG Palya at 10.54 pm.

Blue Line and Green Line updates

LineLatest status
Blue Line (ORR)Trials running from Baiyappanahalli depot to Doddanekundi; BMRCL wants to take them at least up to HSR Layout once electrical and third-rail work is done. The 13-station ORR stretch is also targeted for May 2027.
Green Line10 of 21 CRRC-Titagarh trains received and 3 inducted; 4 more by the second week of December and 3 in the first week of January 2027.
SignallingRailway Board has given in-principle approval for CBTC on the Pink Line and the whole Blue Line up to the airport.
Hulimavu station on the Bengaluru Metro Pink Line
Hulimavu station on the Pink Line, seen during construction in August 2025. Photo: Sameer2905 / Wikimedia Commons (CC BY-SA 4.0)

Why it matters

The underground section is what turns the Bengaluru Metro Pink Line from a Bannerghatta Road shuttle into a cross-city line. It will link MG Road and Shivajinagar in the city centre with Cantonment railway station and Nagawara, where it will meet the Blue Line. Track the full timeline on our Bengaluru Metro Pink Line project page.

Also Read: Alstom CBTC Signalling Runs Bengaluru Metro Pink Line’s 7.5 km Section With Automatic Train Operation From Day One

pm modi flags off bengaluru metro pink line sg palyaRead nextPM Modi Inaugurates Bengaluru Metro Pink Line’s 7.5 km Kalena Agrahara-SG Palya Stretch, Rides With CM Shivakumar13 Nov 2026

Add to Preferred Sources

Join the Discussion

Have a correction, an on-the-ground update, or a question about this project? Engineers, operators and consultants across the metro, rail and RRTS sector read these threads.

Every comment is read by our editorial team before it appears.

Please enter your comment!
Please enter your name here