Mumbai Monorail Unlikely to Restart This Year as MMRDA Reviews IIT Bombay Safety Advice on Guideway Gaps

0
9
Mumbai Monorail Unlikely to Restart This Year as MMRDA Reviews IIT Bombay Safety Advice on Guideway Gaps
Representative image: a Mumbai Monorail train runs above road traffic in Chembur, before services were suspended. Photo: Arjun Mohan / Wikimedia Commons (CC BY-SA 2.0)
Listen to this story
0:00

MUMBAI (Metro Rail News): Mumbai Monorail services are unlikely to resume before the end of 2026, as the Mumbai Metropolitan Region Development Authority (MMRDA) first wants to act on safety recommendations from IIT Bombay.

The main concern is the gap between the two elevated guideways, which officials want addressed so that passengers can be rescued safely if a train gets stuck between stations, The Free Press Journal reported on 19 November.

Why the Mumbai Monorail restart is on hold

MMRDA is studying what covering the gaps would do to the structure. The guideways were designed for the light monorail system, and officials worry that adding metal mesh or covers could increase the load on them. A senior MMRDA official said that, unlike a conventional metro, the monorail draws its power through the guideways, so sending a standby train on the other guideway may not be a safe rescue option in every emergency.

Twin guideways of the Mumbai Monorail in Chembur
The twin concrete guideways of the Mumbai Monorail in Chembur, photographed during construction. The gap between them is the issue now under review. Photo: Karthik Nadar / Wikimedia Commons (CC BY-SA 3.0)
InformationDetails
LineMumbai Monorail, Chembur to Sant Gadge Maharaj Chowk
OperatorMumbai Metropolitan Region Development Authority (MMRDA)
Services suspended since20 September 2025
Upgrade workNew Made-in-India trains, CBTC signalling upgrade, refurbishment of the old fleet
Pending issueCovering the gap between the twin guideways for safe rescue
Expected restartNot before the end of 2026
Annual operating lossAbout ₹180 crore, expected to fall to ₹120 crore after the upgrade

Trains kept ready

Asked whether the new trains would age while they wait, the official said they are being maintained. The official pointed to Navi Mumbai Metro, where trains were reportedly put into service after almost eight years in storage, and said MMRDA wants every precaution taken before the Mumbai Monorail carries passengers again.

Get the Daily Metro & Rail Brief

Join 125,000+ metro and rail professionals. Project updates, new tenders and contract awards from across India, in your inbox every day.

Free · One email a day · Unsubscribe anytime · We never share your address

Mumbai Monorail guideway beam over a road junction
A Mumbai Monorail guideway beam over a road junction. Photo: Karthik Nadar / Wikimedia Commons (CC BY-SA 3.0)

Why it matters

The monorail has been shut since September 2025 for a modernisation that includes new trains and a new signalling system. MMRDA expects the upgrade to cut the line’s annual operating loss from about ₹180 crore to about ₹120 crore, but an official said the monorail is unlikely to break even soon because of its limited passenger capacity.

Also Read: Mumbai Metro 2B: MMRDA Races to Install Final Three Girders at Juhu Circle for Andheri West-Saraswat Nagar Stretch

EvEug2kUUAAe3Tj e1614422558442Read nextMaha Metro floats Rs 3.54 cr tender for Navi Mumbai Metro Line 1 maintenance28 Jul 2026

Add to Preferred Sources

Join the Discussion

Have a correction, an on-the-ground update, or a question about this project? Engineers, operators and consultants across the metro, rail and RRTS sector read these threads.

Every comment is read by our editorial team before it appears.

Please enter your comment!
Please enter your name here