Surat-Bilimora Bullet Train Section to Be Energised With 25 kV From 20 November, NHSRCL Issues Safety Alert

0
15
Surat-Bilimora Bullet Train Section to Be Energised With 25 kV From 20 November, NHSRCL Issues Safety Alert
The elevated bullet train viaduct with overhead equipment masts in place, ahead of energisation. Photo: X/@Infragati
Listen to this story
0:00

SURAT (Metro Rail News): The overhead wires on the Surat-Bilimora bullet train section will be energised with 25,000 volts on or after 20 November 2026, the National High Speed Rail Corporation Limited (NHSRCL) has said.

This will be the first time any part of the Mumbai-Ahmedabad bullet train corridor carries live traction power. In a public safety notice posted on X on 10 November, NHSRCL warned that, from that date, the wires must always be treated as live.

Surat-Bilimora bullet train safety notice

According to the notice, unauthorised persons must not approach, touch or work near the overhead wires on the elevated section in any way. Contact with the high-voltage wires could be fatal.

For the first time in India, an elevated railway stretch will take power through overhead equipment built to the 2×25 kV high-speed standard. The overhead system for the corridor uses about 22,000 steel masts and 25,700 overhead equipment assemblies, The Economic Times reported.

Get the Daily Metro & Rail Brief

Join 125,000+ metro and rail professionals. Project updates, new tenders and contract awards from across India, in your inbox every day.

Free · One email a day · Unsubscribe anytime · We never share your address

InformationDetails
SectionSurat (Antroli, Surat district) to Bilimora (Kesali, Navsari district), elevated, about 50 km
EnergisationOn or after 20 November 2026
Traction system2×25 kV AC autotransformer system, 25 kV, 50 Hz, single-phase
Overhead wire typeHeavy compound catenary
Public warningTreat all wires as live; do not approach, touch or work near them
Electrification contractorL&T-Sojitz consortium (package EW-1)
Issued byNational High Speed Rail Corporation Limited (NHSRCL), notice of 10 November 2026
Workers on the roof of Bilimora bullet train station
Workers fixing roof sheeting at Bilimora bullet train station. Photo: NHSRCL

Why it matters

Energising the wires is the step that lets trains run under their own power, so it moves the Surat-Bilimora bullet train section from construction towards trial runs. The Surat-Bilimora bullet train stretch, about 50 km long between Surat station at Antroli and Bilimora station at Kesali, is set to be the first operational section of the corridor. Electrification work on this stretch began in January 2025, and it is the first section to get India’s first 2×25 kV high-speed traction system, built by the Larsen & Toubro and Sojitz consortium.

Railway Minister Ashwini Vaishnaw has said the Surat-Bilimora bullet train section will open by 2027, Thane to Ahmedabad by 2028 and the full Mumbai-Ahmedabad corridor by 2029, according to Swarajya.

SponsoredInnoBus Conference & Expo 2026, 23 December 2026, Bharat Mandapam, New Delhi
  • Surat-Bilimora: by 2027
  • Thane-Ahmedabad: by 2028
  • Mumbai-Ahmedabad (full corridor): by 2029
Roof structure of Bilimora bullet train station
The roof structure of Bilimora bullet train station. Photo: NHSRCL

Surat bullet train station nears completion

Heavy civil work at Surat bullet train station is complete, and finishing and utility work is under way, Railway Minister Ashwini Vaishnaw said during an earlier inspection of the station. Its roof, facade and station name boards are now in place.

Surat bullet train station roof and name board
Surat bullet train station at Antroli, with its roof in place and the station name board up. Photo: X/@buildbharatnews

NHSRCL and the Railway Ministry have given 2027 as the target for opening the Surat-Bilimora bullet train section. Some social media updates mention 15 August 2027 as the opening date, but no official date has been announced.

Platform level of Surat bullet train station under finishing work
Finishing work on the platform level of Surat bullet train station. Photo: X/@buildbharatnews

About the Mumbai-Ahmedabad bullet train

The 508 km Mumbai-Ahmedabad High Speed Rail corridor is being built by NHSRCL with Japanese Shinkansen technology and is designed for speeds of up to 320 km/h. Once complete, it will cut the Mumbai-Ahmedabad journey to about two hours.

Also Read: Mumbai-Ahmedabad Bullet Train: All 14 Portal Beams Installed Over Rajdhani Route in Vadodara

Completion of bridge over Sabarmati River for Mumbai Ahmedabad Bullet Train Project 04Read nextMumbai-Ahmedabad Bullet Train: 480-metre Sabarmati River Bridge Completed in Ahmedabad8 Oct 2026

Add to Preferred Sources

Join the Discussion

Have a correction, an on-the-ground update, or a question about this project? Engineers, operators and consultants across the metro, rail and RRTS sector read these threads.

Every comment is read by our editorial team before it appears.

Please enter your comment!
Please enter your name here