CHENNAI (Metro Rail News): Chennai Metro Rail Limited (CMRL) has completed casting all precast elements for the Corridor 5 Package between Ullagaram-Sholinganallur, including its final U-girder. The milestone shifted the focus to installing the remaining girders and completing station entry and exit structures on this elevated stretch of Chennai Metro Phase 2.
The ECV-03 package is being executed by the HCC-KEC Consortium, with design and construction oversight from General Consultant AEON Consortium.
U-Girder production reaches 892 units
The package has produced 3,126 elements, covering the major structural components required for the Chennai Metro Phase 2 elevated corridor. The detailed inventory includes:
- 1,041 I-Girder
- 892 U-Girder
- 871 Pier Arm Segment
- 303 Pier Cap
- 19 Portal Shell
CMRL said the 892 U-Girder represents the highest quantity used in this project as compared to other projects under Phase-2. U-Girders from the main elevated deck structure that carries metro tracks, making their production a key part of preparing the viaduct for installation.
Get the Daily Metro & Rail Brief
Join 125,000+ metro and rail professionals. Project updates, new tenders and contract awards from across India, in your inbox every day.
Concrete and steel use reflects construction scale
The precast programme involves substantial material consumption across the casting operations. The reported quantities includes:
| Material | Quantity Used |
| Concrete | 98,052 Cubic Meters |
| Reinforcement steel | 18,550 MT |
| High-Tensile (HT) Strands | 3,010 MT |
The milestone was marked by the officials from CMRL, AEON Consortium and the HCC-KEC Consortium. Those presents included CMRL Director (Projects) Thiru. T. Archunan, Additional General Manager, R. Srinivasan, AEON Resident Engineer M.P. Muthaiya, Thiru. Jaideep Rajeshwarkar, Senior VP & BU Head, HCC-KEC Consortium; Thiru. Lalichan Antony, Project Manager; Thiru. Hari Krishna, Casting Yard In-charge; along with other project personnel.
Driven by strategic vision and leadership
Following the successful casting of the final U-Girder, the project shifted towards the erection of remaining U-Girders and construction of entry/exit structures. These critical works are actively progressing towards the compilation of Chennai Metro phase-2 project.
A collaborative effort behind these achievements are the team who have a strategic vision and leadership quality to make this milestone with 100% successful compilation of all Precast Element and U-Girder casting.