Chennai Metro Phase II: PM Modi, CM Joseph Vijay Inaugurate 15-km Corridor 4 Stretch 

Chennai Metro Phase II: PM Modi, CM Joseph Vijay Inaugurate 15-km Corridor 4 Stretch 
Prime Minister Narendra Modi inaugurates the first operational stretch of Chennai Metro Phase II between Poonamallee Bypass and Vadapalani.
Listen to this story
0:00

CHENNAI (Metro Rail News): Prime Minister Narendra Modi and Tamil Nadu Chief Minister Joseph Vijay inaugurated the first operational stretch of Chennai Metro Phase II, opening around 15 km of Corridor 4 between Poonamallee Bypass and Vadapalani. The ₹4,900 crore section adds 11 elevated stations and a double-decker viaduct, but six more stations and permanent entry and exit facilities at Vadapalani remain unfinished.

PM Modi and CM Vijay also travelled on the Metro between Poonamallee Bypass and Porur as officials briefed them on the project. The opening gives western Chennai a new rail connection, though passengers will initially have to use a temporary link to transfer between the new section and the existing Metro network at Vadapalani.

Chennai Metro Phase II Corridor 4 opens with 11 stations 

The newly inaugurated section forms part of Corridor 4 under Chennai Metro Phase II. It runs from Poonamallee Bypass to Vadapalani and includes 11 elevated stations:

  • Poonamallee Bypass
  • Poonamallee Bus Stand
  • Poonamallee Government Hospital
  • Karayanchavadi
  • Kumananchavadi
  • Kattupakkam
  • Iyappanthangal
  • Thelliyaragaram
  • Porur Bypass
  • Porur Junction
  • Vadapalani

The corridor is expected to improve connectivity between western suburbs and central Chennai, offering commuters an alternative to congested roads.

Get the Daily Metro & Rail Brief

Join 125,000+ metro and rail professionals. Project updates, new tenders and contract awards from across India, in your inbox every day.

Free · One email a day · Unsubscribe anytime · We never share your address

The elevated section also features a double-decker structure of around 3.7 km, where the Metro viaduct runs above road infrastructure. Advanced signalling has been designed to support driverless train operations.

The section also introduces platform screen doors on an elevated Metro stretch in Chennai, adding a safety feature previously associated with other parts of the network.

SponsoredInnoBus Conference & Expo 2026, 23 December 2026, Bharat Mandapam, New Delhi

Six stations and Vadapalani access works still pending

Despite the opening, construction continues on the remaining six stations between Porur and Vadapalani, along with permanent entry and exit facilities at Vadapalani.

Until those works are completed, passengers will use a link bridge connecting the new Phase II station facilities with the existing Phase I Vadapalani station.

The remaining stations and access works are expected to be ready by December, according to the New Indian Express report. Until then, the new corridor will operate with an incomplete set of planned station facilities.

Next focus: Koyambedu-Alandur connection

With the Poonamallee-Vadapalani stretch open, attention is turning to the wider Koyambedu-Alandur section, which is expected to cover nearly 29.6 km. The plan originally covered a 26-km stretch up to Chennai Trade Centre (CTC). Officials now aim to complete the additional 3.6-km link from CTC to Alandur, passing through the congested Butt Road area.

Track work up to CTC has been completed, and trial runs from Koyambedu to CTC are expected by the end of November. Extending trials to Alandur will take longer because track installation on that section is still pending. The extension of trials is expected to require around two additional months.

Chennai Metro Phase II Corridor 4: Key Project Details

InformationDetails
ProjectChennai Metro Phase II, Corridor 4
Inaugurated stretchPoonamallee Bypass-Vadapalani
LengthAround 15 km
Cost₹4,900 crore
Stations opened11 elevated stations
Double-decker structureAround 3.7 km

The opening brings Metro services deeper into western Chennai, but the corridor is not yet complete at all planned stations. The next milestones are finishing the pending Vadapalani access and six stations, followed by trial runs towards CTC and Alandur. The pace of those works will determine how quickly the wider Chennai Metro Phase II network can deliver its intended connectivity gains.

Also Read: Chennai Metro Phase II Records Three TBM Breakthroughs in 3 Days

Project Overview

Chennai Metro – Information, Route Map, Fares, Tenders & Updates

All corridors, status, routes and the latest news in one place →

Join the Discussion

Have a correction, an on-the-ground update, or a question about this project? Engineers, operators and consultants across the metro, rail and RRTS sector read these threads.

Every comment is read by our editorial team before it appears.

Please enter your comment!
Please enter your name here