NEW DELHI (Metro Rail News): Delhi Metro Rail Corporation (DMRC) has floated a tender for consultancy of electrical work across multiple corridors in Delhi and Jaipur. The tender includes Lajpat Nagar station to Saket G Block station (Upcoming Golden Line) and Rithala-Narela-Kundli Corridor (Red Line) under Delhi Metro Phase IV and Prahladpura-Todi Mod Corridor under Jaipur Metro Phase II.
Tender Information
| Information | Details |
| Tender No. | D2EDD-02 |
| Approximate Cost of Work | ₹8.71 Cr. |
| Completion Period | 36 Months |
| Pre-Bid Meeting | July 31, 2026 (11:00 Hrs) |
| Bid Submission Start Date | August 07, 2026 (09:00 Hrs) |
| Bid Submission Deadline | August 13, 2026 (15:00 Hrs) |
Scope of Work
The selected contractor will have to Detailed Design Consultancy for Design of 25 kV Overhead Equipment (OHE) system for the elevated lines, Power Supply & SCADA for both Underground and Elevated lines including checking of Design of Receiving Substations and Design Validation of 2 corridors of DMRC Phase-IV Project and Jaipur Metro Phase-2 Project.
The weekly brief metro & rail professionals read.
| S.No | Corridor Details | Length of Corridors (km) | Underground Stations | ROCS (km) | Elevated Stations | FOCS (km) | At-Grade Stations | FOCS (km) |
| Jaipur Metro Rail Project | ||||||||
| 1 | Prahladpura-Todi Mod Corridor | 42.8 | 2 | 3.18 | 34 | 39.62 | 0 | 0 |
| DMRC Phase-IV Project | ||||||||
| 2 | Lajpat Nagar to Saket G Block | 8.38 | 0 | 0 | 8 | 8.38 | 0 | 0 |
| 3 | Rithala-Narela-Kundli Corridor | 26.46 | 0 | 0 | 18 | 25.48 | 1 | 0.98 |
| TOTAL | 77.64 | 2 | 3.18 | 60 | 73.49 | 1 | 0.98 | |
About Delhi Metro Phase IV
Delhi Metro Phase IV is projected to improve the connectivity across the city with inclusion of around 88.375-km of metro line and 69 metro stations. The project will expand the magenta line and the red line. Moreover, it will introduce the Golden Line to improve connectivity in Southern Delhi.
About Jaipur Metro Phase II
Jaipur Metro Phase II includes a 41-km long Corridor connecting Prahaladpura to Todi Mod. The cost of the project is ₹13,037.66 Cr. The project is expected to improve connectivity between the North and South region of the city.