CMRL Conducts Trial Run on Corridor 4 of Chennai Metro Phase 2

0
46
Chennai metro
Chennai metro

CHENNAI (Metro Rail News): Chennai Metro progressed as Chennai Metro Rail Limited (CMRL) conducted a trial run on Corridor 4 of Chennai Metro Phase 2 which spans 26.1 km from Light House to Poonamallee Bus Depot covering 28 stations. 

Advertisement1
InnoMetro_2026

CMRL conducted a trial run on the 5.5 km stretch of  Chennai Metro Phase 2’s Corridor 4. The trials were initiated from Porur Junction to Vadapalani. The train departed around 11.15 am from Porur and reached Vadapalani at 12.10 pm on 11 January 2026. 

Earlier in June 2025, CMRL also conducted trials on the 10 km Downline stretch of Line 4 which connects Porur Junction Metro Station to Poonamalle Bypass Metro Station through 10 stations. 

Phase 2 of the Chennai Metro spans 118.9 km and consists of three new metro corridors.

Line Route Elevated Length Underground Length Total Length 
Line 3 ( Purple Line) Madhavaram – SIPCOT 219.1 km 26.7 km 45.8 km 
Line 4 (Orange Line) Light House – Poonamallee Bus Depot16 km 10.1 km 26.1 km 
Line 5 (Red Line) Madhavaram – Sholinganallur41.2 km 5.8 km 47 km 

Explore how AI-integrated systems are improving comfort, connectivity, and accessibility for passengers across metro and rail networks at the 6th edition of InnoMetro, India’s leading expo for the Metro & Railway industry which is going to held on  21-22 May 2026 at  Bharat Mandapam, New Delhi

Register now: https://innometro.com/visitor-registration/

LEAVE A REPLY

Please enter your comment!
Please enter your name here

This site uses Akismet to reduce spam. Learn how your comment data is processed.