
New Delhi (Metro Rail News): On 9 February 2025, National Capital Regional Transportation Corporation (NCRTC) conducted trial run on an additional 6 km stretch spanning from Meerut South to Shatabdi Nagar in Meerut.

This 6 km stretch between Meerut South and Shatabdi Nagar features 3 stations in total. The Shatabdi Nagar Station is part of the Delhi-Ghaziabad-Meerut RRTS Project. The remaining 2 stations Partapur and Rithani are a part of Meerut Metro.

Shatabdi Nagar station in Meerut is the second RRTS station on which both Namo Bharat and the Meerut Metro will operate.


NCRTC’s Objective Behind the Trial
As the testing phase progresses, NCRTC will undertake thorough evaluations to assess the integrated performance of the train and its coordination with critical subsystems, including track infrastructure, signaling systems, Platform Screen Doors (PSDs), and overhead power supply systems.
Get the Daily Metro & Rail Brief
Join 125,000+ metro and rail professionals. Project updates, new tenders and contract awards from across India, in your inbox every day.
About Delhi – Ghaziabad- Meerut RRTS Corridor
Currently, the Delhi – Ghaziabad RRTS Corridor is operational between New Ashok Nagar and Meerut South spanning 55 km through 11 stations.
Stations
- New Ashok Nagar
- Anand Vihar
- Sahibabad
- Ghaziabad
- Guldhar
- Duhai
- Duhai Depot
- Muradnagar
- Modi Nagar South
- Modi Nagar North
- Meerut South
Once this section becomes operational, the Delhi- Ghaziabad-Meerut RRTS corridor section will extend up to 61 km featuring 12 stations.
Further Updates
The Meerut Metro project is also progressing rapidly on the other hand. Currently, NCRTC is also conducting trial runs between the Meerut South and Meerut Central. The entry and exit structures are nearly complete while the finishing touches are underway At Partapur and Rithani stations. Furthermore, Platform Screen Doors have been installed till Shatabdi Nagar Station.
.
Read nextKochi Metro to Make JLN Stadium Key Interchange for Pink Line from August 202724 Nov 2026Get alerts for big metro and rail stories Openings, trials, fares and approvals. Two or three a day at most; turn them off any time.




