TBM S115 Records Final Breakthrough at Agra College station of Agra Metro 

0
393
TBM Breakthrough at Agra college station of Agra metro

Agra ( Metro Rail News): Afcon-Sam India Consortium’s TBM S-115 recorded the final breakthrough at Agra College station of Line 1 spanning 14.25 km from Sikandra to Taj East Gate for package AGCC-02 of Agra Metro Phase 1. 

1732209338704
Image Credit: Gaurav Chauhan
1732209334228 1
Image Credit: Gaurav Chauhan

TBM S-115 Journey 

1732209341669 1 1
Image Credit: Gaurav Chauhan

S115 is a refurbished Terratec Earth Pressure Balance (EPB) machine and Afcons’ fourth TBM. This was TBM S-115’s third and final breakthrough for the Package AGCC-02. Under Package AGCC-02 TBM S-115 was first commissioned in December 2023 to construct a total of 2.2 km underground tunnel for the up-line, extending from RBS College Ramp to Agra College Interchange Station.

Current Assignment Raja Ki Mandi Station -Agra College Station534mNovember 2024 
First Assignment RBS Ramp -RBS College Station720mApril 2024 
Second Assignment RBS College Station – Raja Ki Mandi Station684m August 2024 

Package AGCC-02 

Afcon-Sam India Consortium bagged underground Package AGCC-02 at an estimated cost Rs.1819.79 Crore in March 2022 with a 48-month deadline. 

The scope of work under this 7.93 km underground package includes the construction of twin tunnels and 7 stations at Agra Metro Line 1. 

Stations: 

  • Taj Mahal 
  • Agra Fort
  •  Jama Masjid
  • SN Medical College
  •  Agra College
  •  Raja ki Mandi 
  • RBS College