TBM-1 Achieves Breakthrough at Chhatarpur Mandir Station of Delhi Metro’s Golden Line

TBM-1 Achieves Breakthrough at Chhatarpur Mandir Station of Delhi Metro’s Golden Line

Delhi (Metro Rail News): On 21 August 2024, Delhi Metro Phase 4 reached another milestone as the TBM DZ1122 achieved a breakthrough at Chhatarpur Mandir Station of 23.622 km long Golden Line that will connect Aerocity-Tuglakabad through 15 stations.

1724227770897

This is TBM DZ1122’s second breakthrough and overall a 3rd breakthrough out of 10 breakthroughs planned in package DC-09 for the Delhi Metro Phase 4 project.

TBM DZ1122’s Journey in Delhi Metro Phase 4

  • For its second assignment, TBM DZ1122 (TBM-1) was deployed in January 2024 to start tunnelling from Chhatarpur station. The TBM reached Chhatarpur Mandir station covering a distance of 865 metres over the past roughly 7 months.
  • In its first assignment, TBM DZ 1122 constructed a 1267m tunnel from Chhatarpur station to Kishangarh station in 8 months which was completed in November 2023.  
  • TBM DZ1122 constructed 618 rings (1 ring = 1.4m) at an approximate depth of 15m. The machine streamed under the Yellow Line’s viaduct just south of the existing Chhatarpur Station particularly.
1724227771048

Package DC-09

As part of Golden Line, Package DC-09 connects Kishangarh and Saket G Block covering a total distance of 6.51km.

Larsen & Toubro secured the package DC-09 at Rs. within the Delhi Metro Phase 4 project in March 2022 with 42-month deadline. 

The weekly brief metro & rail professionals read.

One email a week. We never share your address. Unsubscribe anytime.

The final contract value: Rs. 1737 crores.

Scope of work

Under package DC-09,  Larsen & Toubro will be responsible for the construction of twin tunnels in the middle of Golden Line and will link Kishangarh station’s east end with a ramp west of Saket G Block station through 4 stations at Chhatarpur (interchange with Yellow Line), Chhatarpur Mandir, IGNOU and Neb Sarai. 

Ongoing Development 

L&T’s other 2 TBMs (DZ1124 and DZ1125) are constructing tunnel from Chhatarpur Mandir Station to IGNOU Station at present.

Join the Discussion

Have a correction, an on-the-ground update, or a question about this project? Engineers, operators and consultants across the metro, rail and RRTS sector read these threads.

Every comment is read by our editorial team before it appears.

Please enter your comment!
Please enter your name here