MMRDA Invites Bid for Mumbai Metro Line 5’s Rolling Stock & Signaling Contract CA-241

0
1,124
MMRDA Invites Bid for Mumbai Metro Line 5’s Rolling Stock & Signaling Contract CA-241
MMRDA achieved historic milestone, passenger journey crosses 300 million in 179 days /Representational Image

MUMBAI (Metro Rail News): Following the recent re-invitation of bids for Line-4’s systems, the Mumbai Metropolitan Region Development Authority (MMRDA) has now initiated bids for supplying critical systems for Mumbai Metro’s 24.90 km Line-5 (Orange Line) under Package CA-241.

The tender notice for Line-5’s crucial systems includes the provision of rolling stock (22 trains, each comprising 6 coaches, totaling 132 coaches), CBTC signaling & train control (S&TC), telecommunication, platform screen doors (PSDs), and depot machinery & plant (M&P) at Kasheli Depot.

Asian Infrastructure Investment Bank (AIIB) intends to finance the design and build aspect of this contract, spanning 50 weeks (approximately 1 year), through a proposed USD 186.57 million loan. MMRDA will fund the comprehensive maintenance component for a period of 17 years, inclusive of a 2-year Defects Liability Maintenance Period (DLP).

Key Details:

  • Estimated Cost: Rs. 2640.72 crore
  • Contract Period: 1 + 17 years
  • Pre-Bid Meeting: March 22, 2024, at 11 am
  • Bid Submission Deadline: May 14, 2024, at 3 pm
  • Technical Bid Opening: May 15, 2024, at 3 pm

MMRDA’s Scope: The project entails the design, manufacture, supply, installation, integration, testing, and commissioning of Rolling Stock, Communication Based Signaling & Train Control, Telecommunication, Platform Screen Doors Systems, and Depot Machinery & Plant for Line 5 (Phase 1 – Kapurbawadi – Kasheli – Dhamankar Naka & Phase 2 – Dhamankar Naka – Bhiwandi – Kalyan APMC) of the Mumbai Metro Rail Project, including 15 Years of Comprehensive Maintenance After 2 Years of Defect Liability Maintenance Period.

The weekly brief metro & rail professionals read.

One email a week. We never share your address. Unsubscribe anytime.

According to the tender schedule, the delivery timeline for Line-5’s Phase 1 prototype train requires the first prototype train to be delivered at week 56 (1.1 year) after contract signing, followed by the next 2 trains at week 78, and the subsequent 9 trains at week 96.

For Line-5’s Phase 2, where construction is pending, the first two trains must be delivered at week 180, and the following 8 trains at week 196 (approximately 3.75 years) from contract signing.

While uncertainties regarding the technical bid opening persist, the anticipation is for financial bids to be opened in Q4 (October – December), with subsequent contract signing contingent upon bid placement. This marks a significant milestone as MMRDA advances its rolling stock procurement process for all under-construction lines, including Line-4 (Green Line) and Line-6 (Pink Line).

Project Overview

Mumbai Metro – Information, Route Map, Fares, Tenders & Updates

All corridors, status, routes and the latest news in one place →

Join the Discussion

Have a correction, an on-the-ground update, or a question about this project? Engineers, operators and consultants across the metro, rail and RRTS sector read these threads.

Every comment is read by our editorial team before it appears.

Please enter your comment!
Please enter your name here