Final Pile Bored On the ECV-02 Package of Chennai Metro Phase 2

2 min read
0
783
Final Pile Bored On the ECV-02 Package of Chennai Metro Phase 2
Final Pile Bored On the ECV-02 Package of Chennai Metro Phase 2
Listen to this story
0:00

CHENNAI (Metro Rail News): The HCC-KEC JV bored the 2039th pillar for the 7.94 Km-long  ECV-02 Package on the Chennai metros’s line 4 connecting Light-House to Poonamallee Bypass. 

The Contract 

The HCC-KEC JV was awarded the contract for the package by CMRL in May 2021 with a 36-month deadline at an estimated cost of Rs. 1007.95 Crores. Besides the 7.9 Km of viaducts and U-Girders, the package also includes a viaduct to the Poonamallee Depot. 

Package ECV-02

Get the Daily Metro & Rail Brief

Join 125,000+ metro and rail professionals. Project updates, new tenders and contract awards from across India, in your inbox every day.

Free · One email a day · Unsubscribe anytime · We never share your address

Package ECV-02 is a 7.9 Km long package of the Chennai metro Phase 2’s line 4 that connects Ponnamallee Bypass to Porur Bypass station with 9 stations in between. 

The 9 stations

SponsoredInnoBus Conference & Expo 2026, 23 December 2026, Bharat Mandapam, New Delhi

Chennai Bypass Crossing, Ramachandra Hospital, Iyyapanthangal Bus Depot, Katupakkam, Kumanan Chavadi, Karayan Chavadi, Mullai Thottam, Poonamallee Bus Terminus and Poonamallee Bypass.

Status

With the award of the Rs 1817.54 Cr Contract with TATA Projects to construct five underground stations in Corridor-05 of Chennai metro Phase:02., CMRL achieves 100% completion of the award of civil and track contracts for the Phase 02 project comprising a 116.1 Km metro network in 3 corridors. 

2039th pillar CM Ph 2 02

Chennai Metro Phase 02 

Phase 2 of the Chennai Metro Project pitches for a 118.9 km Network consisting of 3 corridors, namely: 

  1. Corridor 3: Madhavaram to SIPCOT (45.8 Km)
  2. Corridor 4: Lighthouse to Poonamalle Bypass (26.1 Km)
  3. Corridor 5: Madhavaram to Sholinganallur (47 Km)

The project is scheduled for completion by the conclusion of 2026.


Intrigued by the future of Metro and its impact on our city? Join us at our upcoming InnoMetro event to delve deeper into this vital issue. Stay informed, get involved, and let’s ride the Metro towards a brighter, more sustainable future together. 

chennai metro jpgRead nextCMRL Floats ₹45.79 Cr Tender for Architectural Works at Chennai Metro Phase II Corridor 4 Elevated Stations17 Nov 2026

Add to Preferred Sources

Join the Discussion

Have a correction, an on-the-ground update, or a question about this project? Engineers, operators and consultants across the metro, rail and RRTS sector read these threads.

Every comment is read by our editorial team before it appears.

Please enter your comment!
Please enter your name here