HCC Records Delhi Metro Phase 4’s 1st TBM Breakthrough

2 min read
0
1,148
HCC Records Delhi Metro Phase 4’s 1st TBM Breakthrough
Delhi Metro Phase 4’s 1st TBM Breakthrough
Listen to this story
0:00

DELHI (Metro Rail News): At Krishna Park Extension Station, the HCC – VCCL JV’s tunnel boring machine S86 accomplished the first breakthrough of the 65.10 km Delhi Metro Phase 4 project for a 2.03 km underground extension of the 38.235 km Magenta Line (Line-8).

TBM Triveni, a 73-meter-long, 6.52-meter-diameter Terratec Earth Pressure Balance (EPB) machine, began tunnelling in January 2021 from Vikaspuri Park Shaft, a distance of 1.4 kilometres, to construct the down-line tunnel.

The Delhi Metro Rail Corporation (DMRC) awarded HCC – VCCL the contract for building package DC-06 of the 65.10 km Delhi Metro Phase 4 project in January 2020, with a contract value of Rs. 489 crore and a 36-month deadline.

Their job entails constructing twin tunnels from the Vikaspuri Park Shaft north of Janakpuri West Station to the Vikaspuri Ramp near Keshopur Station, with one underground station at Krishna Park Extension (co-incidentally built by HCC in a joint venture with Samsung for Phase 3’s Package CC-34 north of Janakpuri West Station).

Get the Daily Metro & Rail Brief

Join 125,000+ metro and rail professionals. Project updates, new tenders and contract awards from across India, in your inbox every day.

Free · One email a day · Unsubscribe anytime · We never share your address

The equipment will now be dismantled, transported, and reassembled at Vikaspuri Shaft to construct the parallel 1.4 km up-line tunnel.

Triveni will be the only TBM operating in Delhi until mid-2022. STEC’s TBMs will begin tunnelling between New Ashok Nagar Down Ramp – Anand Vihar – Sahibabad UP Ramp for the Delhi – Meerut RRTS’ Package 4 later in 2022. If awarded, Afcons and Tata’s TBMs should be in service for Magenta Line’s DC-05 and Silver Line’s DC-07, DC-08, and DC-09 in 2023.

delhi metro rajiv chowk platform information displayRead nextDelhi Metro: DMRC Awards ₹7.81 Cr Contract to Praruh Technologies to Upgrade PRC System at Control Centres13 Nov 2026

Add to Preferred Sources

Join the Discussion

Have a correction, an on-the-ground update, or a question about this project? Engineers, operators and consultants across the metro, rail and RRTS sector read these threads.

Every comment is read by our editorial team before it appears.

Please enter your comment!
Please enter your name here