PUNE (Metro Rail News): Maharashtra Metro Rail Corporation Ltd (Maha Metro) invites bids from eligible applicants for the supply and commissioning of Solar PV projects including its operation and maintenance for Pune Metro Rail Project.
Name of Work
Design, Engineering, Manufacture, Supply, Storage, Civil work, Erection, Testing & Commissioning of the Rooftop and Boundary Walls mounted Solar PV projects under RESCO model including Operation and Comprehensive Maintenance (O&M) of 5.0 MWp Solar PV project for a period of 25 years after commissioning of 10 Nos. of Elevated Stations and 2 Nos. of Depots for Pune Metro Rail Project.
Important Details
Tender Notice Number – P1EG-02R/2021
Completion Period –
- Execution/ Erection Period: 1.5 Years (including Monsoon Period) from the date of issue of LOA
- PPA Period: 25 years from the date of commissioning & commercial operation (COD).
Document Download Date – From 23.03.2021 at 16:00 Hrs to 22.04.2021 till 16:00 Hrs.
Pre Bid Meeting Date – 06.04.2021 at 11:00 Hrs
Date & Time of submission of Tender – Online submission till 22.04.2021 up to 16:00 Hrs
Date & Time of Opening of Tender – 22.04.2021 at 16:30 Hours
Further Details
Sale of document, e-payment procedure, submission and other details are available on Maha Metro tender portal under section in e- tenders. https://mahametrorail.etenders.in.
Sale of document, e-payment procedure, submission and other details are available on Maha Metro tender portal under section in e- tenders. https://mahametrorail.etenders.in.
Pune Metro Rail Project comprises construction of 3 Corridors with total route length of 54.58 km at present –
Line-1 (Purple Line) -PCMC Bhavan to Swargate (16.59 km) with 14 stations
Line-2 (Aqua Line) – Vanaz to Ramwadi (14.66 km) with 16 stations
Line-3 – Hinjawadi – Civil Court (23.33 km) with 23 stations