Mumbai Metro Line 2A (Yellow Line)

Operational Operator: Maha Mumbai Metro Operation Corporation Ltd (MMMOCL) operates the line; MMRDA owns it Length: 18.6 km Since: 02/04/2022 Updated: Official site ↗

As of 19 Oct 2026, Mumbai Metro Line 2A (Yellow Line) is operational (since 2 Apr 2022). Latest news: 28 Oct 2026.

Mumbai Metro Line 2A, the Yellow Line, is an 18.6 km elevated corridor with 17 stations from Dahisar (East) to Andheri (West) at D.N. Nagar, running along Link Road through Borivali, Kandivali, Malad and Goregaon. MMMOCL operates it for owner MMRDA. It opened in two stages and has been fully operational since January 2023. Fares start at ₹10.

Why it matters

Line 2A gives the western suburbs a north to south rail option that runs parallel to the crowded Western Railway suburban line and the Link Road and S.V. Road corridors. At Dahisar (East) it meets Line 7 and, since April 2026, Line 9 towards Mira-Bhayandar, and at D.N. Nagar it links with Line 1 to Ghatkopar. It will also form the western end of the planned Line 2B to Mandale, making the Yellow Line a cross-suburb route.

Key facts

  • Operator: Maha Mumbai Metro Operation Corporation Ltd (MMMOCL) operates the line; MMRDA owns it
  • Length: 18.6 km, 17 stations
  • Status (October 2026): Fully operational (October 2026). Dahisar (East) to Dahanukarwadi opened on 2 April 2022 and Dahanukarwadi to Andheri (West) on 20 January 2023, after inauguration by the Prime Minister on 19 January 2023. All 17 stations are in service.
  • Cost: About ₹6,410 crore (Wikipedia, citing MMRDA); ADB loan for about 52%, state for 48%
  • Trains: BEML 6-car trainsets, 25 kV AC, built for future driverless running; Alstom Urbalis 400 CBTC signalling; Charkop depot shared with Line 7
  • Ridership: Not published for Line 2A alone. MMRDA's lines (2A, 7, 2B Phase 1 and 9 Phase 1) together averaged about 2.79 lakh journeys a day between February and August 2026.

Mumbai Metro Line 2A (Yellow Line) stations

The 17 stations below run from Dahisar (East) to Andheri (West). Interchanges are listed where a station connects with another line or a railway station.

#StationTypeConnects to
1Dahisar (East)ElevatedLine 7 (Red) / Line 9 (Red)
2Anand NagarElevated
3KandarpadaElevated
4MandapeshwarElevated
5EksarElevated
6Borivali (West)Elevated
7ShimpoliElevated
8Kandivali (West)Elevated
9DahanukarwadiElevated
10Valnai-Meeth ChowkyElevated
11Malad (West)Elevated
12Lower MaladElevated
13Bangur NagarElevated
14Goregaon (West)Elevated
15OshiwaraElevated
16Lower OshiwaraElevated
17Andheri (West)ElevatedLine 1 (Blue), D.N. Nagar

Sections and opening dates

SectionStationskmStatusOpened or expected
Dahisar (East) to Dahanukarwadi99.8Operational2022-04-02
Dahanukarwadi to Andheri (West)88.8Operational2023-01-20

Explore more

Official source: www.mmmocl.co.in

Latest updates

56 tenders tracked →

See all news & updates →

Phases

PhaseLinesStationsLength (km)Status
Dahisar (East) to DahanukarwadiDahisar (East) to Dahanukarwadi99.8Operational
Dahanukarwadi to Andheri (West)Dahanukarwadi to Andheri (West)88.8Operational

Latest ridership: Not published for Line 2A alone. MMRDA's lines (2A, 7, 2B Phase 1 and 9 Phase 1) together averaged about 2.79 lakh journeys a day between February and August 2026.

Milestones

  • Maharashtra government approves the Dahisar to D.N. Nagar corridor
  • Prime Minister Narendra Modi lays the foundation stone
  • DMRC appointed as implementing agency
  • Civil contract awarded to J Kumar Infraprojects
  • Construction begins
  • Trial runs flagged off on Lines 2A and 7
  • Dahisar (East) to Dahanukarwadi opens to passengers with Line 7 (Dahisar East to Aarey), flagged off by Chief Minister Uddhav Thackeray
  • Prime Minister Narendra Modi inaugurates Dahanukarwadi to Andheri (West)
  • Passenger service begins on the full 18.6 km line
  • MMRDA renames stations: Pahadi Eksar becomes Shimpoli, Valnai becomes Valnai-Meeth Chowky
  • Line 9 Phase 1 opens, extending through-service north from Dahisar (East) to Kashigaon
  • MMRDA network (Lines 2A, 7, 2B and 9) crosses 30 crore passenger journeys

Fares

Mumbai Metro Line 2A (Yellow Line) fares range from ₹10 to ₹10, set by Maha Mumbai Metro Operation Corporation Ltd (MMMOCL) operates the line; MMRDA owns it.

Distance / zoneFare
Minimum fare₹10

Frequently asked questions

Is Mumbai Metro Line 2A fully open?

Yes. All 17 stations from Dahisar (East) to Andheri (West) have been in service since 20 January 2023.

How long is Line 2A and how many stations does it have?

It is about 18.6 km long (18.589 km in project documents), fully elevated, with 17 stations.

Where can I change to other metro lines?

At Dahisar (East) for Line 7 and Line 9, and at Andheri (West), next to D.N. Nagar, for Line 1 (Versova to Ghatkopar).

Who operates Line 2A?

Maha Mumbai Metro Operation Corporation Ltd (MMMOCL) runs the trains. MMRDA owns the line.

What is the fare on Line 2A?

Fares are distance based and start at ₹10.

What trains run on Line 2A?

Six-car trains built by BEML, with Alstom CBTC signalling. They are maintained at Charkop depot, shared with Line 7.

Why were some station names changed?

In April 2023 MMRDA renamed Pahadi Eksar as Shimpoli and Valnai as Valnai-Meeth Chowky after demands from commuters. Pahadi Goregaon is now Bangur Nagar.

Journey Planner & Route Map

Awarded tenders & contracts

No awarded tenders or contracts recorded yet.

Ongoing tenders

TenderAgencyValueBid dueStatus
MahaMetro invites maintenance tender for Navi Mumbai Metro Line-1 Maha MetroOpen
MRVC invites bids for electrification work in Borivali-Virar Section of Western RailwaysMRVCSubscribersUnder evaluation
Maha Metro floats Rs 3.54 cr tender for Navi Mumbai Metro Line 1 maintenanceMaha MetroSubscribersSubscribersUnder evaluation

Upcoming tenders

No upcoming tenders announced yet.