AN OVERVIEW
Navi Mumbai Metro project is a Mass Rapid Transit System (MRTS) with single line developed to ease the transportation in the area of Navi Mumbai in Maharashtra through City and Industrial Development Corporation (CIDCO).
Construction for Navi Mumbai Metro began in November 2011 and is supposed to be completed by 2021
Under Construction line of Navi Mumbai Metro
Line 1 – From CBD Belapur to Pendhar
Total Distance – 11.10 km
Expected Cost – Rs. 3063.63 crores
Station Type – Elevated
Stations Name – CBD Belapur – Sector 7 – CIDCO Science Park – Utsav Chowk – Sector 11 – Sector 14 – Central Park – Pethpada – Sector 34 – Panchanand – Pendhar
Navi Mumbai Metro Planned Network
Line 2 – From Taloje MIDC – Khandeshwar (extension of Line-1)
- Expected Cost – Rs 2820.20 crore
- Total Distance – 10.30 km
- Station Type –Â Elevated
Line 3 – From Taloje MIDC to Pendhar
- Expected Cost – Rs 1750.14 crore
- Total Distance –Â 2 km
- Station Type –Â Elevated
Line 4 – From Khandeshwar to Navi Mumbai International Airport
- Expected Cost – Rs 1270.17 crore
- Total Distance – 4.17 km
- Station Type – Elevated along with Underground
Contractors of Navi Mumbai Metro
- Joint Venture of Louis Berger and Balaji Railroad System – General Consultant
- CRRC Zhuzhou Locomotive Corporation Limited – 24 Coaches
- Ansaldo STS – Signalling, Telecommunications, Automatic Fare Collection (AFC)
- J Kumar – CRTG – Construction of Taloja Depot
- NCC Limited – Construction of 4.91 km viaduct
- J Kumar Infraprojects – Construction of 4.34 km viaduct
- Joint Venture of San José Constructora & Mahavir Roads & Supreme Infra – Construction of 11 stations
Funding Agencies:
- City and Industrial Development Corporation(CIDCO).
- Navi Mumbai Municipal Corporation.
- Mumbai Metropolitan Region Development Authority.