Western Railway Plans ₹98 Cr Vande Bharat-Compatible Coaching Depot at Mumbai’s Currey Road

3 min read
0
0
Western Railway Plans ₹98 Cr Vande Bharat-Compatible Coaching Depot at Mumbai’s Currey Road
Western Railway plans a ₹98 crore coaching depot at Currey Road to support Vande Bharat and long-distance trains/Representational image
Listen to this story
0:00

MUMBAI (Metro Rail News): Western Railway (WR) is planning a 55,000-sq-metre coaching depot at Mumbai’s Currey Road to ease capacity constraints at Mumbai Central and support the maintenance of long-distance trains, including Vande Bharat services. The ₹98 crore facility will have 10 dedicated railway lines and is targeted for completion by December 2028.

The proposed depot will come up on railway land between Currey Road and Lower Parel. It will provide additional space for train parking, routine servicing, inspections and coach repairs, addressing the limited capacity available at existing facilities in Mumbai.

Depot to have 10 dedicated railway lines

The facility will be divided into three types of lines to handle different maintenance and operational requirements:

  • Two pit lines: For routine maintenance and servicing of trains.
  • Six stabling lines: For parking trains when they are not in operation.
  • Two sick lines: For detailed inspections, repairs and maintenance of coaches.

The depot will also accommodate the maintenance requirements of Vande Bharat trains. This will add to Western Railway’s capacity to handle modern trainsets alongside conventional long-distance services.

Get the Daily Metro & Rail Brief

Join 125,000+ metro and rail professionals. Project updates, new tenders and contract awards from across India, in your inbox every day.

Free · One email a day · Unsubscribe anytime · We never share your address

Existing railway store depot to be shifted

Work on the project depends on relocating an existing railway store depot currently occupying the proposed site. Central Railway will shift this facility to Thakurli, after which the land will be cleared for construction.

The railway land has already been handed over to Western Railway. However, construction can begin only after the relocation and site clearance are complete.

SponsoredInnoBus Conference & Expo 2026, 23 December 2026, Bharat Mandapam, New Delhi

Tendering targeted for February 2027

Western Railway plans to begin the contractor tendering process by February 2027. The project timeline will then depend on the relocation of the existing store depot and the subsequent start of construction. Key project details include:

InformationDetails 
LocationCurrey Road-Lower Parel, Mumbai
Project cost₹98 crore
Land areaAround 55,000 sq m
Total railway lines10
Pit lines2
Stabling lines6
Sick lines2

Additional capacity for Mumbai’s long-distance trains

Mumbai Central and Dadar currently face limitations in parking and maintaining long-distance trains. Mumbai Central, in particular, has limited scope for expanding its existing facilities. The proposed Currey Road depot is expected to take over part of the maintenance and stabling workload, creating additional capacity for train operations from Mumbai Central and Dadar.

The new depot could ease pressure on Mumbai’s existing coaching infrastructure and provide Western Railway with more flexibility to plan long-distance services. Its December 2028 target will depend on the timely relocation of the railway store depot and completion of construction.

Also Read: South Coast Railway Floats ₹4,299 Cr EPC Tender for 151-km Third and Fourth Lines in Andhra Pradesh

Untitled design 2023 07 18T114646.896Read nextSouth Coast Railway Floats ₹4,299 Cr EPC Tender for 151-km Third and Fourth Lines in Andhra Pradesh22 Nov 2026

Add to Preferred Sources

Join the Discussion

Have a correction, an on-the-ground update, or a question about this project? Engineers, operators and consultants across the metro, rail and RRTS sector read these threads.

Every comment is read by our editorial team before it appears.

Please enter your comment!
Please enter your name here