Chennai Metro Line 5 (Red Line)

Under Construction Operator: Chennai Metro Rail Limited (CMRL); operations and maintenance contracted to Delhi Metro Rail Corporation (DMRC) Length: 47 km Updated: Official site ↗

As of 19 Oct 2026, Chennai Metro Line 5 (Red Line) is under construction. Latest news: 15 Oct 2026.

Chennai Metro Line 5, the Red Line, is Corridor 5 of CMRL's Phase II: a 47 km line from Madhavaram Milk Colony to Sholinganallur via Villivakkam, Koyambedu, Valasaravakkam, Alandur and Medavakkam. It has 45 stations, with 41.2 km elevated and 5.8 km underground. As of October 2026 no section is open; trial runs on the Koyambedu to Chennai Trade Centre stretch are targeted for November 2026.

Why it matters

Line 5 is the longest of the three Phase II corridors and the only one that runs as an outer north to south arc, linking north Chennai and the Koyambedu bus hub with Alandur, St. Thomas Mount and the Medavakkam to Sholinganallur belt without passing through the city centre. It connects with both Phase I lines, the suburban rail network and the MRTS, and shares a double-decker viaduct with Line 4 between Alwarthirunagar and Alapakkam.

Key facts

  • Operator: Chennai Metro Rail Limited (CMRL); operations and maintenance contracted to Delhi Metro Rail Corporation (DMRC)
  • Length: 47 km, 45 stations
  • Status (October 2026): Under construction (October 2026). No section is open to passengers. Track work on the Koyambedu to Chennai Trade Centre stretch is largely done and CMRL is targeting trial runs from November 2026, followed by about four months of trials. The 3.6 km link from Chennai Trade Centre to Alandur is still being built, so services to Alandur are expected in early 2027. Phase II as a whole is targeted for completion by end-2028.
  • Cost: No separate figure published for Line 5; Chennai Metro Phase II (three corridors, 118.9 km) is sanctioned at ₹63,246 crore (Union Cabinet, 3 October 2024)
  • Trains: BEML, three-car trains designed for driverless (GoA4) operation, from the 70-train ARE02 order shared with Line 3; depot at Madhavaram

Chennai Metro Line 5 (Red Line) stations

The 45 stations below run from Madhavaram Milk Colony to Sholinganallur. Interchanges are listed where a station connects with another line or a railway station.

#StationConnects to
1Madhavaram Milk ColonyLine 3 (Purple), shared station
2Madhavaram Depot
3Assisi Nagar
4Manjambakkam
5Velmurugan Nagar
6Madhavaram Bus TerminusMadhavaram mofussil bus terminus
7Shastri Nagar
8Retteri Junction
9Kolathur Junction
10Srinivasa Nagar
11VillivakkamVillivakkam railway station (suburban)
12Villivakkam Bus Terminus
13Villivakkam MTH Road
14Anna Nagar West
15Thirumangalam JunctionLine 2 (Green)
16Anna Nagar KV
17KoyambeduLine 2 (Green)
18Koyambedu Market
19Natesan Nagar
20Virugambakkam
21AlwarthirunagarLine 4 (Yellow), shared double-decker station
22ValasaravakkamLine 4 (Yellow), shared double-decker station
23KarambakkamLine 4 (Yellow), shared double-decker station
24AlapakkamLine 4 (Yellow), shared double-decker station
25Mugalivakkam
26Ramapuram
27Manapakkam
28Chennai Trade Centre
29Butt Road
30Alandur (Arignar Anna Alandur)Line 1 (Blue) / Line 2 (Green)
31St. Thomas MountLine 2 (Green) / suburban railway / MRTS
32AdambakkamMRTS
33Vanuvampet
34Ullagaram
35Madipakkam
36Kilkattalai
37Echangadu
38Kovilambakkam
39Vellakkal
40Medavakkam I
41Medavakkam II
42Perumbakkam
43Classical Tamil Institute
44ELCOT Park
45SholinganallurLine 3 (Purple), shared station

Sections and opening dates

SectionStationskmStatusOpened or expected
Koyambedu to Chennai Trade Centre (Nandambakkam)1212Civil and track work largely complete (about 90% of track laid, Sept 2026); traction and signalling tests pending; trial runs targeted for November 2026expected early 2027 (after about four months of trials)
Chennai Trade Centre (Nandambakkam) to Alandur23.6Under construction along Butt Road; CMRL plans to run the first Line 5 services up to Alandurexpected Q1 2027
Alandur to Sholinganallur15Under construction; piers and all precast elements of the Ullagaram to Sholinganallur package complete (Aug to Oct 2026), girder erection and station works continuingexpected 2027 to 2028
Madhavaram Milk Colony to Koyambedu16Under construction, includes the 5.8 km underground stretch from Kolathur to Villivakkam MTH Road (tunnelling by TBM since February 2025)expected by end-2028

Explore more

Official source: chennaimetrorail.org/phase-2

Latest updates

58 tenders tracked →

See all news & updates →

Phases

PhaseLinesStationsLength (km)Status
Koyambedu to Chennai Trade Centre (Nandambakkam)Koyambedu to Chennai Trade Centre (Nandambakkam)1212Civil and track work largely complete (about 90% of track laid, Sept 2026); traction and signalling tests pending; trial runs targeted for November 2026
Chennai Trade Centre (Nandambakkam) to AlandurChennai Trade Centre (Nandambakkam) to Alandur23.6Under construction along Butt Road; CMRL plans to run the first Line 5 services up to Alandur
Alandur to SholinganallurAlandur to Sholinganallur15Under construction; piers and all precast elements of the Ullagaram to Sholinganallur package complete (Aug to Oct 2026), girder erection and station works continuing
Madhavaram Milk Colony to KoyambeduMadhavaram Milk Colony to Koyambedu16Under construction, includes the 5.8 km underground stretch from Kolathur to Villivakkam MTH Road (tunnelling by TBM since February 2025)

Milestones

  • Union Home Minister Amit Shah lays the foundation stone for Chennai Metro Phase II
  • CMRL signs the ₹1,817.54 crore C5-UG06 contract with Tata Projects for five underground stations and twin tunnels between Kolathur and Villivakkam MTH Road
  • BEML wins rolling stock contract ARE02 for 70 three-car trains for Lines 3 and 5
  • Union Cabinet approves Chennai Metro Phase II at ₹63,246 crore, including the 47 km Madhavaram to Sholinganallur corridor
  • Tunnel boring machine Kurinji starts the first Line 5 tunnel drive from the Kolathur ramp
  • DMRC awarded the operations and maintenance contract for Corridors 3, 4 and 5
  • TBM Kurinji breaks through at Kolathur station, the first breakthrough on Line 5
  • Last of 824 U-girders cast for the ECV-02 elevated package (13.1 km viaduct)
  • Final pier (P814) completed on the 11.3 km Ullagaram to ELCOT package near Medavakkam
  • All 3,126 precast elements cast for the Ullagaram to Sholinganallur package

Frequently asked questions

Is Chennai Metro Line 5 open?

No. As of October 2026 no part of Line 5 carries passengers. CMRL is targeting trial runs on the Koyambedu to Chennai Trade Centre stretch from November 2026.

What is the route of the Red Line?

Line 5 runs from Madhavaram Milk Colony in north Chennai to Sholinganallur on the OMR, via Kolathur, Villivakkam, Anna Nagar, Koyambedu, Valasaravakkam, Alandur, St. Thomas Mount and Medavakkam.

How long is Line 5 and how many stations does it have?

CMRL gives the length as 47 km, of which 41.2 km is elevated and 5.8 km underground. CMRL's station list has 45 stations, six of them underground.

When will the first section open?

Trials on the Koyambedu to Chennai Trade Centre section are expected to last about four months, and CMRL plans to start services up to Alandur, so the first opening is likely in early 2027. No date has been announced.

Where can passengers change lines?

Planned interchanges include Thirumangalam and Koyambedu (Line 2), Alandur (Lines 1 and 2), St. Thomas Mount (Line 2, suburban rail and MRTS), Madhavaram Milk Colony and Sholinganallur (Line 3), and four double-decker stations shared with Line 4.

Who will run the trains?

CMRL owns the line. Operations and maintenance of all three Phase II corridors have been contracted to Delhi Metro Rail Corporation, and the trains are three-car sets from BEML built for driverless operation.

Journey Planner & Route Map

Awarded tenders & contracts

No awarded tenders or contracts recorded yet.

Ongoing tenders

TenderAgencyValueBid dueStatus
Chennai Water Metro: CMRL floated tender for DPR along Buckingham CanalCMRLOpen
Chennai Metro Line 3: PSD Door System SupplyCMRLSubscribersSubscribersUnder evaluation
Chennai Metro Phase 1 & 2 Expansion: Bids Invited for DPRs’ Preparation CMRLSubscribersUnder evaluation

Upcoming tenders

No upcoming tenders announced yet.

Bid values, closing dates and awardees are for subscribers. See plans.