DELHI (Metro Rail News): The long-awaited Delhi-Panipat-Karnal RRTS Corridor has started picking up the pace. The National Capital Region Transport Corporation has invited bids for executing electrical utility shifting works on the Kashmiri Gate – Bhalswa Section of the Namo Bharat corridor. In November 2025, the Delhi-Panipat-Karnal RRTS Line received approval from PIB.
Tender Information
| Tender Id | 2025_NCRTC_245257_1 |
| Tender No | DK/UD/COR-OF/009 |
| Pre-bid Meeting | 29-12-2025 |
| Bid submission start date | 12-Jan-2026 |
| Bid submission deadline | 19-Jan-2026 |
| EMD | ₹ 29,28,000 |
| Completion period of work | 12 months |
NCRTC’s Brief Scope of Work: Supply, Installation, Testing & Commissioning/Shifting / Modification for 33KV,11kV, LT Electrical Utilities of TPDDL and Dismantling / Relocation of Street lights infringing Delhi – Panipat – Karnal Namo Bharat corridor from Kashmiri Gate to Bhalswa (Ch. 9550 to 20770).
The Delhi-Panipat-Karnal RRTS Corridor has been identified as a priority link under the NCR Regional Plan to address rising travel demand along the Delhi-Sonipat-Panipat-Karnal belt. The 136km Delhi-Panipat-Karnal RRTS Corridor is planned along a northbound alignment starting from Sarai Kale Khan in Delhi and extending through major urban and industrial centres in Haryana before reaching Karnal. The estimated cost of the project is Rs 33,000 crore.
Join the 6th edition of InnoMetro to explore how the progressions in AI are improving the railway systems, including ticketing, rolling stock, and signalling. Witness the innovation from 200+ exhibitors at India’s leading show for metro & railways.
Date: 21-22 May 2026
Venue: Bharat Mandapam, New Delhi
Register now: https://innometro.com/visitor-registration/