L&T Receives LoA Worth ₹4467 Cr for Track Contract T1 of Bullet Train Project 

L&T Receives LoA Worth ₹4467 Cr for Track Contract T1 of Bullet Train Project 
NHSRCL Completes 100 Km of Viaduct and 250 Kms of Pier Erection on the Mumbai-Ahmedabad Bullet Train Project

Larsen & Toubro (L&T) has received a Letter of Acceptance (LoA) worth Rs. ₹ 4467.7 Cr for the track work package T-1 of the Mumbai-Ahmedabad Bullet Train project. Package T-1 is the third and final track installation package for the Mumbai-Ahmedabad High-Speed Rail (MAHSR Bullet Train) project. 

OHQ20768@4x1

National High-Speed Rail Corporation Ltd. (NHSRCL) invited bids for this contract in October 2024 with a 2157-day (5.9-year) deadline. Technical bids were opened on 30 April 2025, revealing that 3 firms have submitted bids for the contract. Technical evaluation of the submitted bids took place on 3 July 2025. During the technical evaluation round, one firm’s bid was rejected. 

Financial bids for the technically qualified bids opened on 4 July 2025. Financial evaluation of the bids took place on 13 August 2025. During the financial evaluation round, one firm’s bid was rejected, announcing L&T as the lowest bidder for the contract. On the same day, L&T received LoA for the contract from NHSRCL. 

Financial Bid Values 

The weekly brief metro & rail professionals read.

One email a week. We never share your address. Unsubscribe anytime.

FirmBids
Larsen & Toubro₹ 4467.7 Cr 
DRA Infracon – DMRC JV₹ 4698 Cr 

IFB Number: Package No. MAHSR – T-1

The scope of Package T-1 concerns track work for the following packages:

Package C-1, which spans 1.028 km and includes the construction of the underground BKC Station by MEIL–HCC JV. 

Package C-2 spans 20.377 km and includes the construction of an underground tunnel executed by Afcons Infrastructure. 

Package C-3 spans 135.45 km and includes the construction of an elevated viaduct along with three stations being constructed by Larsen & Toubro.

Brief Scope: Design, Supply and Construction of Track Works including Testing and Commissioning on Design-Build Lump Sum Price basis for Double Line High Speed Railway between Mumbai Stn. at Bandra-Kurla complex (MAHSR Km. -0.255) and Zaroli Village (Km . 156.600)

To get real-time updates on metro and railway tenders, join our WhatsApp Community: https://chat.whatsapp.com/EzkphM7r0eaGtWJXi59CLb

Guide

High-Speed Rail in India: the complete guide

All corridors, status, routes and the latest news in one place →

Join the Discussion

Have a correction, an on-the-ground update, or a question about this project? Engineers, operators and consultants across the metro, rail and RRTS sector read these threads.

Every comment is read by our editorial team before it appears.

Please enter your comment!
Please enter your name here