TBM 3 Achieves Breakthrough at Delhi Metro’s IGNOU Station

TBM 3 Achieves Breakthrough at Delhi Metro’s IGNOU Station

Delhi (Metro Rail News): Following the successful breakthrough of TBM-4 (DZ1124) in the Down-Line tunnel at IGNOU Station, TBM-3 has now completed its drive on the UP-Line and achieved a breakthrough at IGNOU Station which is a part of the Delhi Metro’s Golden Line. The Golden Line covers a distance of 23.622 km and connects Aerocity and Tughalakabad via 15 stations.

1742294500404 1
Image Credit: Sandip Mandal

TBM 3’s Drive in Delhi Metro Phase 4

 In November 2023, TBM 3 was deployed from Chhattarpur Mandir Station by L&T for its first assignment. On 18 March 2025, the TBM reached IGNOU station after constructing a 1470m up-line tunnel.

1742298037968
Image Credit: Sandip Mandal

6th Tunnel Breakthrough in Package DC-09 

This was the 1st tunnel breakthrough of TBM-3 (DZ1125). However, it was the 6th overall breakthrough within Package DC-09, which was awarded to Larsen & Toubro. This package covers a 6.51 km stretch from Kishangarh to Saket G Block and includes four stations: Chhattarpur (interchanging with the Yellow Line), Chhattarpur Mandir, IGNOU, and Neb Sarai.

The Progress Ahead

TBM-3 and TBM-4 will now be moved through the IGNOU Station box and deployed to construct approximately 1.2 km of twin tunnels toward Neb Sarai.

Guide

Delhi Metro: the complete guide

All corridors, status, routes and the latest news in one place →

Join the Discussion

Have a correction, an on-the-ground update, or a question about this project? Engineers, operators and consultants across the metro, rail and RRTS sector read these threads.

Every comment is read by our editorial team before it appears.

Please enter your comment!
Please enter your name here