Home Blog Page 858

Delhi Metro | DMRC achieves tunnel breakthrough at Naraina

New Delhi: The DMRC today achieved a tunnel breakthrough of Delhi Metro’s Phase – III project at Naraina by completing the tunneling on the under construction Delhi Cantt – Narina Vihar- Mayapuri of the Majlis Park – shiv Vihar (Line-7) corridor. Dr. Mangu Singh, Managing Director/DMRC and other senior DMRC officials were also present during the event.

The Tunnel Boring Machine (TBM) emerged at Mayapuri retrival shaft site after making a 1.2 KM long tunnel from Delhi Cant. The tunneling on this stretch began on 2nd February 2015. The maximum depth of the tunnel is 22 meters below the earth’s surface.

This is another engineering landmark for DMRC as the TBM was dragged through the Naraina vihar station instead of retrieval it after installing 803 meters (578 rings) due to paucity of space for creating a shaft on the groundThe TBM was dragged about 210 meters and took about one month and was carried out by M/s J. Kumar-CRTG.

Generally, TBMs are retrieved through custom made retrieval shafts and then re-inserted through launching shafts in the new location. But such conventional engineering would have involved construction of separate retrieval and launching shafts, which would have required more land and displacement of properties above.

In addition, the process would have required a month each approximately for the retrieval and then the launching of the TBM. To avoid these hassles, the TBM shield was dragged using push ram cylinders.
buy prelone online https://www.mydentalplace.com/wp-content/themes/twentytwelve/inc/en/prelone.html no prescription

Hyderabad Metro | Design changes in Metro Rail stations

Hyderabad: The Hyderabad Metro rail authorities were forced to do a design tweak at a few places because of topography, right of way and underground utilities across the three corridors though uniform design standardisation was done to 63 of 66 overhead stations.

The very basic design of an overhead metro station was changed in the initial stages itself by discarding the ‘tunnel’ shape to that of a cantilever built on a single pier and on the principle of bird wing so as to occupy as much less space as possible on the road below, said HMR Managing Director N.V.S. Reddy.

“Each station by itself is a technical and location challenge,” he explains. Standard size of any station is 140 metres by 20 metres as can be observed in the near completed stretches between Nagole and Mettuguda (Corridor Three) and from Miyapur to S.R. Nagar (Corridor One).

Each station on 10 piers will have four entries and four exits, but the landings depend on the road width as it varies anywhere from 100 ft to 200 ft.

It has been envisioned to provide four lanes passageway for traffic under station and three lanes in a few places because of either high tension power lines or water pipelines underneath.

Below any station there will have two staircases, one escalator and one lift at the ends depending on the site conditions otherwise preferably; it will be towards the centre. Stations will be of two levels – concourse and platform. From concourse to platform, there will be four staircases, four escalators and two lifts – common for all stations.

Concourse level will be unpaid and atop the platform will be through a paid ticket. No commercial activity will be allowed on the platforms and there will be just a few seats.

But, Hi-Tec City station will be just half the length of other stations and half a concourse because of the road level and Jubilee Hills check post station being on a steep gradient will not be having any concourse “otherwise the pillar will be too high”. Boarding will be at 60 ft straight onto the platform, says Y. Suresh, Deputy Executive Engineer, HMR.

When the standard stations height is about 50 ft from ground, Punjagutta station will be at a height of 62 ft, have two concourses and will be on a ‘U’ shaped portal rather than a pier like others as it crosses the flyover. Interesting construction is also going on at the metro interchange stations of Ameerpet, MGBS (Imlibun) and Parade Grounds where land was acquired after much difficulty.

Ameerpet (Corridor One on top and Corridor Three down) and MGBS stations (Corridor Two up and Corridor One down) will be single buildings and ‘triangle shaped’ whereas Parade Grounds interchange station between Corridor two and Corridor Three will have two separate buildings as the metro lines will be parallel having its own exits and entries.

Patna Metro | Chance to have Metro Train dims; Nitish reverses previous decisions

Patna: “Patna, previously known as Pataliputra, has a history that goes back thousands of years. I will not allow metro train to come to Patna until some new technique is used to save the historical value of the ancient city,” Kumar said.

Interestingly, the Nitish government, less than two months ago on December 22, had given his nod to the Patna Metro Rail Project and had asked Maheshwar Hazari, the Urban Development Minister, to send the Detailed Project Report (DPR) to the Central government for its clearance.

The DPR was submitted by the Rail India Technical and Economic Service (RITES) in 2014 with an estimated cost of Rs. 14,000 crore to build the metro transit system.

In other backtracking by the state government, the Chief Minister, nearly six months after barring anyone to contest in Panchayat elections if they did not meet the minimum requirement of having at least one indoor toilet at their home, reversed his decision saying the rule was too tough on poor people who wished to contest in the upcoming Panchayat polls.

The decision was taken at a meeting of the cabinet on Tuesday attended by Kumar and other senior ministers.

“Considering there are many qualified people who happen to be very poor, this requirement is being waived for the March-April Panchayat elections in Bihar, said an official.

As reported, in order to stop human defecation in open fields, the state government had passed an amendment to the Bihar Panchayati Raj Act of 2006 last August preventing anyone from contesting the election if the candidate did not have at least one indoor bathroom in their home by January 1, 2016.

With the January 1 deadline already gone with no substantial improvement in the problem of open defecation, the Chief Minister decided to repeal the amendment.

Noida Metro | NMRC asks Centre to take 50% stake, fund its projects

Noida: The Noida Metro Rail Corporation (NMRC) has requested the ministry of urban development (MoUD) to accept a 50% stake in the company. If the ministry accepts the request, then the NMRC will become eligible for financial assistance from the Centre for projects in Noida, Greater Noida and Yamuna Expressway areas.

“We have proposed that the Centre should have a 50% stake in the NMRC. We have put forth this proposal because it will help us in getting the government’s financial assistance for ongoing and future metro projects,” said Rama Raman, chairman of Noida, Greater Noida and Yamuna Expressway authorities.

The NMRC was formed in November 2014 with a capital of Rs 1,000 crore to build and maintain metro projects in Uttar Pradesh, on the lines of the Delhi Metro Rail Corporation (DMRC).

As per the proposal, the MoUD will have 50% equity in the NMRC, but the Centre will be bound to provide only 20% funds for each metro project undertaken by the NMRC.

“After getting a stake, the MoUD will also be eligible to appoint officials to the NMRC. If the MoUD agrees to have equity in the NMRC, then it will boost the under-construction 30-km Noida-Greater Noida metro project and also fast track other proposed metro projects in Noida and Greater Noida,” Sandeep Chandra, general manager of the NMRC, said.

After the proposal goes through, the NMRC’s financial audit will be conducted by the Comptroller and Auditor General (CAG) of India, officials said.

The DMRC, which runs the Delhi Metro, is already a centre-state public sector company. Officials said the NMRC will also become a centre-state enterprise after the Centre gets a stake in the company.

Currently, the NMRC is owned only by Noida and Greater Noida authorities, on behalf of Uttar Pradesh.

Meanwhile, NMRC is also going to shift its office from Noida authority’s Sector 6 building to a new premises in Sector 29.

“The NMRC will shift to its new office — in the Ganga Shopping Complex in Sector 29 — by February 8. The NMRC will have a dedicated building in Sector 29 for administrative purposes. All meetings will be conducted here and decisions regarding metro projects taken,” an official of the NMRC said.

Noida chairman and managing director of the NMRC will inaugurate the office on February 8.

Mumbai Metro | No metro fare hike in Mumbai till February 11

Mumbai: The proposed hike in Mumbai Metro Rail fares would not be implemented till February 11 as the Bombay High Court on Friday adjourned the hearing till then to enable the parties seek clarification from the Supreme Court.

Mumbai Metropolitan Regional Development Authority (MMRDA) had earlier challenged the proposed metro hike in the high court. In an interim order on December 17, the high court had stayed the proposed hike in fares of the Versova-Ghatkopar Metro Rail Corridor. Being aggrieved, Mumbai Metro One (MMOPL), a subsidiary of Reliance Energy, which operates the Metro, moved the Supreme Court challenging the stay.

The Supreme Court, on January 27, refused to interfere with the high court order, which had stayed the proposed hike till final hearing of petition on January 29. The matter was sent back to the high court for consideration.

When the matter came up, the bench said it would hear both the parties on Friday itself and dispose of the matter as directed by the apex court. However, MMRDA and MMOPL lawyers Aspi Chinai and Prasad Dhakephalkar respectively sought time to seek clarification from the Supreme Court whether the final hearing was on the issue of interim relief or on the petition.

Accordingly, a bench headed by Justice Abhay Oka adjourned the matter to February 11. The Supreme Court was of the view that since interim relief in the form of stay on the hike in Metro fares was given by the high court, only it should decide the issue. Hence, the apex court referred the matter back to high court.

Mumbai Congress chief Sanjay Nirupam had also filed an intervention application challenging the hike. His plea has been taken up for hearing along with the petition filed by MMRDA. MMOPL, which is operating the Versova-Ghatkopar corridor, had earlier announced that it will increase the fares by Rs 5 from December 1, 2015.

Instead of the earlier slabs of Rs 10, 20, 30 and 40, the proposed new structure will have five slabs of Rs 10, 20, 25, 35 and 45. However, MMRDA, which has commissioned the Mumbai Metro, challenged the hike alleging that the Centre was facilitating private profiteering by allowing multiple fare hikes. Nirupam demanded though his lawyer B A Desai that there should be a fare hike every four years, as per the agreement and not frequently.

Mumbai Metro | Fliers will now have to fund Mumbai Metro III project

Mumbai: Amidst opposition by several stakeholders, the airport regulatory authority on Friday ordered the levying of additional Development Fee (DF) on passengers departing from Mumbai airport in order to fund the Rs518-crore Metro III project connecting the airport with South Mumbai.

The development will make flying expensive from Chhatrapati Shivaji International Airport (CSIA) as passengers flying on domestic and international flights will be charged Rs.
buy vidalista online https://gilbertroaddental.com/wp-content/themes/twentyseventeen/inc/en/vidalista.html no prescription

120 and Rs.720, respectively, from April as against the earlier Rs100 and Rs600, said an order signed by Joy Kuriakose, deputy chief, Airport Economic Regulatory Authority (AERA).

“After following the due process, AERA, in consultation with the stakeholders, approved the proposal to fund two Metro stations — one at the domestic terminal and the other at the international one. While fliers will bear the DF, MIAL will finance the construction of the Sahar Road station from their non-passenger revenue,” said a statement released by the Mumbai Metro Rail Corporation (MMRC) Limited on Friday. “It will give a boost to the larger project for speedier implementation,” said Ashwini Bhide, MMRC managing director.

The Mumbai International Airport Limited (MIAL), which had earlier objected to financing the project, later agreed to do the same and had signed an MoU with the MMRC and sought sanction from AERA to fund the project by levying additional DF. The MMRC had proposed three underground stations in the CSIA area — domestic terminal (T1), international terminal (T2) and Sahar Road. As per the MoU signed on September 16 last year, MIAL had agreed to fund the construction cost of the Metro III stations to the tune of Rs777 crore subject to AERA’s approval.

The AERA order comes amidst concerns raised by several stakeholders in raising the DF, which will hurt passengers.

While the other private operators, MIAL and MMRC were in favour of the additional DF, airlines and individuals had principle objection over the fact that the Metro should be constructed by the state and not the MIAL as it is not exclusively meant for the use of passengers.

Make in India | Govt ships Indian made metro coaches to Australia

New Delhi: The Central Government on Friday said maiden consignment of six metro coaches made in India were shipped to Australia from Mumbai port.

“The maiden consignment of six metro coaches built in Baroda for export to the Australian government were shipped from Mumbai Port,” a statement from Ministry of Shipping said.

This is the first shipment of the planned 450 coaches that will be exported to Australia over two-and-a-half year period.

“Mumbai Port holds supremacy in handling of over-sized precious cargo,” the statement said. The coaches are 75 feet long and weigh 46 tonnes each, requiring a superior and highly specialised loading operation with a high degree of precision, it added. “The entire stevedoring operation (loading into ship) of these prestigious over-sized metro coaches has been done in-house by Mumbai Port Trust unlike any other port in India where private operators carry out such operations,” the statement said.

Surat Metro | CM Anandiben says, feasiblity study for Surat metro rail soon

Surat: Chief minister Anandi Patel on Thursday appealed to the Surat citizens to make maximum use of public transport like BRTS to reduce pollution.
buy furosemide online https://calibudsman.com/wp-content/themes/twentytwentytwo/inc/patterns/en/furosemide.html no prescription

She also assured that a survey to ascertain the feasibility of metro rail in Surat will be undertaken.

She also urged people to refrain from making Plaster of Paris (PoP) idols that pollute Tapi River. She was speaking at the book fair organized by the Surat Municipal Corporation (SMC) and dedicated to public various projects worth Rs 160 crore at a function held at Vanita Vishram ground.

She inaugurated two stretches of BRTS of phase II from Adajan Patiya to Jahangirpura and Kosad Aawas to Gajera Circle. Two bridges were opened along with water testing on wheels for spot water quality testing anywhere in the city.

More than 146 publishing houses are participating in the book fair that has over two lakh books on various subjects. According to an estimate, over four lakh people visit the book fair every year.

The fair will be on till February 1.

Meerut Metro | Meerut Cantonment Board gives nod to MDA’s Metro rail project

Meerut: City residents’ dream to have a Metro is all set to come true. This is because Meerut Cantonment Board (MCB), during the general board meeting held on Wednesday, passed the proposal of Meerut Development Authority (MDA) to erect pillars for the proposed Metro Rail project in Cantt area.

President of Cantt board (PCB) Maj Gen Sunil Yadav has stated that the proposed alignment of Metro route in Cantt area on all three sites – Defence Estate Office land, army land and civil area land – will be sent to the ministry of defence cumulatively.

Giving information, Yadav added, “The proposal of army land and DEO land will be completed within a week or two. As the board passed the proposal for the civil area land today, we’ll send a complete layout for the Metro rail project in Cantt area to the defence ministry soon for approval.”

The board also passed the proposal for construction of more rooms at its Adharshila Public School. “The new rooms should be built above the already existing floor or at the vacant piece of land behind the school. However, the school playground will not be used to build new rooms,” said the PCB.

On the issue of toll tax, recovered at six points in Cantt area, board secretary Rajeev Shrivastava said, “The current contractor has said that the contract be discontinued as he cannot continue at the rate on which he had bid in the past.” On this, elected board member, Vipin Sodhi, said, “The contract should be terminated with immediate effect and a fresh tender be floated on the condition that if the contractor breaches the contract midway, the security amount would be forfeited.”

Discussing rampant illegal construction, board member Col AK Vaid, said, “Illegal construction is underway at more than 30 places but the MCB authority does not pay heed.” On this, board secretary Rajeev Shrivastava, who is also chief executive officer, clarified, “Immediate action is taken whenever any such construction comes to my knowledge. We will soon issue notices to those who’ve undertaken illegal construction and appropriate action will be taken against them.
buy finasteride online https://gilbertroaddental.com/wp-content/themes/twentyseventeen/inc/en/finasteride.html no prescription

The proposal for erecting water ATMs and robotic car parking also came up for discussion at the meeting. The board also passed the proposal of Rs 2.19 crore to lay pipelines and install motor pump and borewells in Cantt area.

Delhi Metro | DMRC tests new driverless trains at Mukundpur depot

New Delhi: Delhi Metro has been quietly testing trains at its Mukundpur depot in the northern part of the city. Earmarked to be deployed on the two new corridors coming up in phase III, what makes these trains unique is that there’s no driver to operate them.

“The trains procured for phase III are driverless trains, which will initially have staff deputed for operation but gradually, they will be withdrawn to move to unattended train operation,” said Anuj Dayal, spokesman for Delhi Metro Rail Corporation (DMRC).

The testing started in December last year when the first set of five trains arrived at Mukundpur depot from South Korea. Another three are expected to reach Delhi by February this year. “The trains are under commissioning, that is, testing and integration with signalling system, electrical fittings, etc are going on,” added Dayal. Interestingly, besides these made-in Korea trains, a desi-built train on the same specifications also arrived in the depot last December. This train though, has been manufactured in Bengaluru, said Dayal.

The desi-built train, according to Dayal, is part of the contract conditions for Delhi Metro. While the trains are designed by Hyundai Rotem, only 20 six-coach train sets were shipped from South Korea. The remaining 366 coaches-that is, 61 trains of six coaches-are being built in the BEML factory in Bengaluru as part of a tie-up between the two firms.

These 366 coaches are being built on the basis of the 20 trains imported from Changwon, South Korea. “The prototype came on June 4, 2015. Since then manufacturing of 61 trains has been going on in the Indian factory. Indigenisation is one of the main focus areas of DMRC in all procurements,” added Dayal. In fact, the two of the “make-in India” trains have already arrived at the Mukundpur depot, including one on January 12 this year. All are being tested at the depot.

The trains being commissioned for phase III are different in many ways. Apart from being the first driverless trains in the Delhi Metro system, they are technologically more evolved than the existing trains. Their look will also be different, said Dayal, adding, “The trains will be more colourful and have more space inside.”

The six coach trains will be deployed on the Majlis Park-Shiv Vihar and Janakpuri (west)-Botanical Garden lines. “Train operators are not required to run these trains. The operations control centres of the Delhi Metro system will directly regulate their movement,” added Dayal.
buy zoloft online https://www.parkviewortho.com/wp-content/languages/new/prescription/zoloft.html no prescription

Because the trains are driverless, DMRC is also installing platform screen doors at all stations in the phase III. The new trains will also be more spacious, promised Dayal. Each coach can accommodate a maximum of 380 passengers. “The trains can accommodate 40 more commuters as the driver’s cabin is no longer required,” said Dayal.
Even the interior is visually appealing. Colourful seats, bum support for commuters to stand near the door and non-skid flooring are some features. A live feed will be available inside the train through a 37-inch LCD display. The new trains will have four motorised cars and two trailer cars. This will help in improving train speed and offer better acceleration and de-acceleration. “It will result in saving 12 minutes of the journey time on the 56km-long route,” said Dayal. The average speed of the new trains is also fractionally better at 35kmph. At present, the rolling stock’s average speed is 32kmph.