Home Blog Page 780

Nagpur Metro | Maha Metro submits DPR for Phase II project to state govt

Nagpur: Nagpur metro phase II project’s Detailed Project Report (DPR) is submitted by the Maharashtra Metro Rail Corporation Limited (Maha Metro) to state government’s Urban Development Department (UDD). The department will study the report in details and if they have any quarries they can question the DPR. After everything found Okay, then UDD will forward the DPR to state cabinet for approval.

After the delay of 2 months. DPR is prepared by Rail India Technical and Economic Service (RITES). RITES had already completed its study which included traffic, topographic and geotechnical data and gave the green light to Phase ll earlier in February. Phase II will have five stretches having a total length of 48.3 km and 35 stations. The cost of the phase is about Rs10,500 crore at 2018 prices.

Five proposed stretches of Nagpur Metro are:

S.noCorridorsLengthStations
1.Automotive SquareKanhan River13 Kms12
2.Lokmanya NagarHingna6.7kms7
3.Wasudeo NagarDattawadi4.5kms3
4.Prajapati NagarTransport Nagar5.6kms3
5.MihanButibori MIDC ESR18.5kms10

The longest stretch is from Mihan to Butiori which is 18.5kms with 10 stations.

The stretches are decided according to the traffic congestion of these routes. The estimated daily ridership from Kanhan River to Butibori MIDC is 2.61 lakh in 2024, 3 lakh in 2031 and 3.73 lakh in 2041. The ridership of Transport Nagar to Hingna line is 2.58 lakh in 2024, 2.98 lakh in 2031 and 3.62 lakh in 2041. The figure for Wasudeo Nagar to Dattawadi spur is 30,000 in 2024, 35,000 in 2031 and 39,000 in 2041.

This metro project will generate a large number of employment opportunities and will help to grow. It will be beneficial for the citizens as they will get relief from traffic and will get a faster way to reach their destination.

Mumbai Metro | MMRC completes 5 km tunneling of Colaba-Seepz corridor

Mumbai: The Mumbai Metro Rail Corporation (MMRC) is executing the 33.5 km corridor of which the 5 km of tunneling across its alignment in the city has been completed. Underground corridor for the Colaba-Seepz metro line has completed 10% of tunneling work.

The four location where the underway tunneling is constructed Marol, Naya Nagar(Mahim), Vidyanagari (Kalina), Azad Maidan and all this is being done with eight tunnel – boring machines (TBM’S) in operation.

The TBM’s need to bore 52 km (without stations) for both the up and down lines for the construction of the underground corridor.

Ashwini Bhide, Managing director, MMRC said that The tunneling commenced in November 2017 from the Naya Nagar-launching shaft in Mahim, and the TBMs are currently moving at a speed of 350m per week. “We are pleased to announce the completion of 5km of tunneling within one year of the project’s initiation. We are positive about completing the project by December 2021”.

Ashwini Bhide, Managing director, MMRC said that The tunneling commenced in November 2017 from the Naya Nagar-launching shaft in Mahim, and the TBMs are currently moving at a speed of 350m per week. “We are pleased to announce the completion of 5km of tunneling within one year of the project’s initiation. We are positive about completing the project by December 2021”.

They expect that the first TBM breakthrough will be achieved in the 4.15km Marol-MIDC-Seepz (package 7) section of the construction by September 2018 says the corporation official.

The progress depends on the geological conditions of the location. They target to bore an average of 700-800m per week, according to the Mumbai Metro Rail Corporation (MMRC). At a depth of 25m to 30m by lowering a TBM, lowering in shaft depth and because of this the tunneling work is carried out.

The Mumbai Metro Rail Corporation is in the process of lowering three additional TBMs and will lower two more by July-end to increase the pace of tunneling for the mega project says, officials.

Mumbai Metro | Commuters happy with Paytm facility at metro station

Mumbai: Commuters travelling in Mumbai Metro are really happy with the officials introducing Paytm facility at metro stations. All one has to do is scan the code and enter the metro station. No need to stand in queue at the ticket window or vending station. Using mobile phone, commuters have to use the Paytm App to make payments and hop on to the ride.

This simple interface has made life easier for Mumbai Metro travelers who otherwise have to stand in queues to get ticket either at metro or local stations.

Those traveling in metro are flooding the Mumbai Metro Twitter feed with positive feedback. Commuters who were otherwise facing issues while traveling in metro are now finding it easier to commute in mass transit system.

 

 

And this is not all. A rider had lost his metro card while traveling. The rider got his card back within no time and is all praise for the officials.

Here is the Tweet thread of the commuter who got back his lost smart card:

For all those who are still using old public transport, it is time to switch to metro. You travel with easy and comfort. In fact now you don’t even have to stand in long queues to buy ticket, use mobile to make payments and get your ticket within seconds.

Visakhapatnam Light Metro | Panel formed for long pending project

Visakhapatnam: Finally the long pending light metro project is gaining grounds. A panel has been formed for the Visakhapatnam Light Metro Rail Project’. In latest development, orders have been given by principal secretary of Municipal Administration & Urban Development, R Karikala Valavan to formulate a committee for the project.

As per the directives from Valavan, a Visakha Metro Rail Project monitoring and advisory committee’ is being established. The panel will be entrusted with the task of checking the quality of work and monitoring the progress. The long pending project will be taken under the private-public partnership model.

To accelerate the progress all necessary permissions will also be taken at the earliest. The officials now want to speed up the process and shift gears. The estimated cost of the project is around Rs 8,300 crore.

The advisory committee formed consists of a 10-member team. These include the town planner, municipal commissioner, RTC regional manager, city planner, district collector, director of country as well as one person who is nominated by the government at centre.

As per details, in the light metro project, the Amaravati Metro Rail Corporation Ltd (AMRCL) will also have 50 per cent stake. Bulk of remaining stake will also rest with the project contractor with VUDA getting a nominal capital share.

AMRCL’s managing director will be appointed as nodal officer and UMTC company consultant member convenor of the new committee. In this consideration, the principal secretary has ordered AMRCL MD to take up further course of action.

The state government has also agreed to allocate 250 acres of land for the Visakhapatnam Light Metro. It has communicated the same in a review meeting at Amaravati. On the other hand VUDA has lately submitted the design proposals that include three corridors in a stretch of 42.5 km.

It is estimated that the corridors will be constructed in about five year’s time with approximate investment of about Rs 4,100 crores. In case of setting up elevated corridors, the project will be developed at an additional cost of Rs 4,200 crore.

State Govt, Maha Metro and Indian Rly to execute MoU to run HSR trains

Nagpur: It is good news for Indian Railway commuters to get High Speed Local Trains in four towns namely Bhandara, Wardha, Katol, and Ramtek. The government is planning to run the high-speed local trains between Nagpur and four nearby towns- Bhandara, Wardha, Katol, and Ramtek.

A Memorandum Of Understanding will be executed between Maharashtra government, Indian Railways and Maha Metro on July 16 for planning and execution of the project.

Union Minister of Housing & Urban Affairs Hardeep Singh Puri, Cabinet Minister Nitin Gadkari, Railway minister Piyush Goyal, chief minister Devendra Fadnavis and other dignitaries will be present in MoU signing ceremony which will be organized at Nagpur Municipal Corporation (NMC) Suresh Bhat Hall.

“The project would be first of its kind in the nation High speed fully air-conditioned coaches will run under the project. All formalities like timings, number of trips, revenue sharing pattern, special stations etc will be  decided after MoU”, said Dr. Brijesh Dixit, MD of Maha Metro.

Maha metro managing director Brijesh Dixit talked about the project in an interview and said “The project would be first of its kind in the nation High speed fully air-conditioned coaches will run under the project. All formalities like timings, number of trips, revenue sharing pattern, special stations etc will be  decided after MoU”

At present the average speed from Nagpur city to Gondia passengers train is 50 km per hour while the Ramtek passenger train is 27 km per hour. To overcome the speed issue they are planning to run three-coach Electric Multiple Units (EMU) to these towns with four trains on each route.

They have planned to run EMU’s at 120 km per hour. However, the Maha metro will use existing tracks, platforms, signaling and etc of railways for the services.

Refuting allegation by former BJP MP and current MPCC vice-president Nana Patole and activist Prashant Pawar, “Maha metro will also have to start Pune Metro Rail’s priority section with rental coaches” said Dixit

Patole stated that Maha metro’s joyrides are only benefiting L&T Metro Rail Hyderabad Limited(LTMRHL). He added that Maha metro is paying Rs.45 crore as hiring charge for six coaches to LTMRHL for three years.

“Coaches, signaling system etc are not made in the country, hence we are so dependent on foreign countries. We have to place orders only after getting loans. we are likely to get three coaches in September. It will take 6-7 months more for certification and etc. Till then we cannot wait and render the entire infrastructure unutilized” Patole said

“Coaches, signaling system etc are not made in the country, hence we are so dependent on foreign countries. We have to place orders only after getting loans. we are likely to get three coaches in September. It will take 6-7 months more for certification and etc. Till then we cannot wait and render the entire infrastructure unutilized” Patole said

Dixit added that payment of 15 crores has been made tp LTMRHL “we could not take coaches from Chennai as our platform’s design is for three coaches, while Chennai has a set of four coaches”

Dixit said one of two sets of three coaches each will be moved to Hingna-Subhash Nagar T point corridor once the work is completed.

He said Metro Rail will begin operation Manje Square in Sitabuldi and Kapri in March 2019.

On Wednesday, the elevated stretch between airport south station the Maha metro operated electrical shunting vehicle ‘Buland’. This is first of the elevated stretches where all the work have been completed and is ready for the trial run.

At a grade stretch, the Maha metro started metro rail joyrides between airport south and Khapri station in April.

After the conclusion of the MoU programme, the dignitaries will dedicate NMC’s newly commissioned sewage treatment plant (STP) having a capacity of 200 million liters per day (MLD) to the public.

Also, the civic body’s project to supply 150MLD treated sewage from the STP to Mahagenco’s Koradi and Khaparkheda thermal power stations will be announced. At the same time, bhoomipuja of waste-to-energy project will be performed.

At the cost of around Rs. 236 crores at Bhandewadi dumping yard the NMC had constructed the STP on PPP model through a consortium of three private companies, including city-based Vishvaraj Infrastructure Limited (VIL).

This is the MNC’s second STP after an earlier one with a capacity of 130 MLD, which was commissioned under the central government’s JNNURM scheme.

The civic body is already supplying 130MLD treated sewage to Koradi thermal power station. Now, the quantum will increase to 330MLD.

Under the waste-to-energy project, the private operator will produce 11.50MW power by treating 800 of the total 1,100 to tonnes of garbage generated from the city daily. The power will be supplied to MSEDCL.

Mumbai Monorail | Staircase brought monorail again in controversy

Mumbai: Once again the Mumbai Monorail is in the argument. Bhavya Heights Society, a housing society in Wadala has complained that the point of entry and exit staircase at the Wadala monorail station is blocking the access of fire brigade in the society.

This housing society has now moved to high court which has castigated Mumbai Metropolitan Region Development Authority (MMRDA) and Brihanmumbai Municipal Corporation (BMC) for not working in an organized way which has resulted in such situations.

Now the court has said and directed the authorities further to assure that the other monorail project from Jacob Circle to Chembur will not have such problems. The residents of Bhavya Heights Society, Wadala depot has said MMRDA to move the existing staircase towards the south side of as it is an obstruction for the entry of fire tenders, all these petitions were heard by the bench of Justices Naresh Patil and Girish Kulkarni.

The society filled the petition after they got a letter from the Mumbai fire brigade informing about the inability to douse any fire in the society premises as the staircase was proving an obstructing.

When the matter came up for hearing, the MMRDA and BMC pointed fingers to each other direction but the court blamed the civic body for not taking attention when the staircase was being constructed and looked into that only after its completion. The bench also scolded MMRDA for not keeping the civil corporation in the coil when the staircase was being constructed.

After all the hearings, the MMRDA assured the court that it will find some alternative for the existing staircase and ensured that the society will not be blocked.

The society suggested shifting the staircase to the south end of the stations whereas the bench suggested a skywalk to which the MMRDA said that it will take decisions only after consulting its officials.

The court accepted their submissions and has placed the matter for hearing after 4 weeks.

Problems faced by Monorail

Fire safety issues

A fire department is yet to give the NOC to the Dadar station of the Mumbai monorail. The issue about the fire tenders which will go through the narrow lanes which the monorail passes is yet to be resolved.

Scomi claims compensation over cost escalation

Compensation of nearly Rs 1200 crore is demanded by Scomi Engineering which was contracted by MMRDA to provide rakes and run the services of Mumbai Monorail. They have asked for this contract because they have invested over and above the contracted amount.

Read Also: After LTSE left the monorail work the MMRDA is planning to start it again

Permissions

Since its inception in 2005, Mumbai Monorail project has faced many problems like land acquisition issues and permissions from various authorities and agencies. In 2014 phase 1 was finally completed the services between Chembur and Wadala started.

Read Also: Mumbai Mono Rail | L&T-Scomi workers not paid for months, MMRDA denies to Interfere

Shortage of rakes

For the trial runs of Mumbai Monorail between Wadala and Jacob Circle and between Chembur and Wadala the monorail has 10 rakes which were utilized for these trials. Scomi said that there are four more rakes are there which are needed to be modified to be in service.

From Transit oriented Development to Development Oriented Transit in Indian cities

Land-use development and Transportation both are inter linked with each other and make different types of urban forms. Globally, there are many cities whose forms were shaped by transportation and land use. However, there is neither a systematic approach nor empirical method to understand which kinds of transportation factor should connect land use and which kinds of land-use factor should connect transportation. There is a school of thought either development should be oriented to transit or transit should orient to development. Therefore, this paper aims at reviewing whether development should come first or Transit. Finally, this paper will focus on Development Oriented Transit.

Introduction

Land use and Transportation both are connected with each other. Transport is the most essential component for shaping development of a city.

Land use is one of the prime determinants of movement and activity which means land use determines the demand for transport. Land use may change because of increase or decrease in accessibility. Integration of land-use and transit is very essential. National Urban Transport Policy (NUTP) also emphasizes on integrated land use and transport planning.

Research Paper: From Transit Oriented Development to Development Oriented Transit in Indian cities.
Research Paper: From Transit Oriented Development to Development Oriented Transit in Indian cities. (By: Architect and Town Planner Priyanka Kumar)

Types of development with relation to transit

The Integration of land-use and transit may carry out in many ways such as Transit Adjacent Development (TAD), Transit Joint Development (TJD), Transit Supportive Development (TSD) or Transit Oriented Development (TOD) and Development Oriented Transit (DOT).

In 19th Century there were concepts like Transit Adjacent Development (TAD), a development which is physically near transit but fails to capitalize upon this proximity to promote transit riding and other economic benefits, which lacks in functional connectivity to transit/ with transit, in Integration of Land use with Transit, in means of station access, and in economic and fiscal benefits. Fremont is a city in California used to be a good example of Transit Adjacent development.

As time passes Transit Adjacent Development gradually changed into Transit Joint Development (TJD) is that development which is Joint with transit neither before nor after transit. Tokyo is one of the best examples for Transit Joint Development which did not restrict itself to Transit Joint Development but expanded as a Transit Oriented Development (TOD) as well. Transit Joint Development (TJD) also states that a type of development which occurs because of any formal agreement or arrangement between a public transit agency and a private individual or organization. Hong-Kong is one of the good examples of this type of development.

In Early 20th Century, A San Francisco-based Architect, Urban designer and urban planner “Peter Calthorpe”, coined a term Transit Oriented Development (TOD) which defines “A mixed use community within an average 2000-foot walking distance of a transit stop and core commercial area. TODs mix residential, retail, office, open space, and public uses in a walk able environment, making it convenient for residents and employees to travel by transit, bicycle, foot or car”. Transit Oriented Development (TOD) also known as Transit Supportive Development (TSD).One of the earliest and most successful examples of Transit Oriented Development TOD is Curitiba, Brazil.

Now Development Oriented Transit (DOT) is defined as a process in which transit is incorporated after development. DOT defines as put development first whereas TOD defines as put transit first. For example Electric streetcar systems evolved after the development of the electric traction motor in the 1890’s in network. But this term little bit explained by Dittmar H. and Ohland G in 2004 as Development Oriented Transit (DOT) is built to serve the development. Here transit follows the development rather than vice-versa.

To read complete research paper, please read Metro Rail News (Monthly) Magazine, June 2018 Issue (Pages 26 – 33)

Bullet Train expected to start by 2022 in August, on schedule

New Delhi: India’s ambitious project of setting up Bullet Train network in the country is expected to meet deadline. As per recent information, Bullet train might start from 2022. The earlier deadline was 2023 and National High Speed Rail Corporation Limited (NHSRCL) feels it is on schedule.

The entire project is estimated at Rs 1.08-lakh-crore project with 80 per cent of the loan financed by Japan.  The work on bullet train is racing against time as the work on the project started in December 2017. The Mumbai-Ahmedabad bullet train project has been mired with protests and controversy from land owners in Gujarat and Maharashtra over land acquisition. These protests are getting support from local groups and political parties.

NHSRCL assures that it has not missed milestones set in its timeline.  To built the entire network, NHSRCL will need 1,400 hectares, with 353 hectares in Maharashtra and the remaining in Gujarat.

The requirement is further divided into 7,000 plots, in 195 villages in Gujarat and in 104 villages in Maharashtra. The project will pass through eight districts in Guajarat and three districts in Maharashtra besides a small area in Dadra & Nagar Haveli.

What is the progress like so far?

As per usual procedure, LIDAR is started along with land acquisition along with a laser-based aerial survey. This is followed by a physical survey to authenticate and update LIDAR results. After this a joint measurement survey by a team representing all stakeholders is done. Subsequently information of the land owners is processed for the compensation means.

For the bullet train LIDAR was wrapped up in 2017 and the actual study began in December last year covering 50 villages in Maharashtra and 184 villages in Gujarat.

Engineers had visited sites and given notices to land-owners. The notice however did not state that the project requires only a linear tract 17.5m wide (not the whole land) and that this was a survey, not a notice for acquisition. Several senior NHSRCL officials now presume that because of this exclusion, local politicians convinced farmers that they would lose their complete land ownership.

Mapping the progress the joint measurement is completed in 30 in Gujarat and 50 villages in Maharashtra covering 102 km of the 508 km line.

This analysis is followed by installing a small pillar for physical detection for land acquisition. NHSRCL officials said that disbursing compensation takes around three months post all processes. The officials are trying to meet the deadline of land acquisition by December 2018. Till now only 0.9 hectares in Bandra-Kurla Complex has been physically handed over.

Hyderabad Metro | Trial runs from Amarpreet to LB Nagar line begins

Hyderabad : The much awaited Hyderabad metro rail corridor-1 is likely to be ready by the last week of July. This corridor stretch is linked from Ameerpet to LB Nagar via Khairatabad, Namapally, Malakpet, and Dilsukhnagar. The stretch would be thrown open to public by Chief Minister K Chandrasekhar Khar Rao. Municipal administration and urban development (MA&UD) minister KT Rama Rao on Wednesday announced that after traveling in the metro rail from Ameerpet to LB Nagar in the new route, during the trial run. Along with Metro Rail managing director NVS Reddy, Transport Minister P Mahender Reddy and others, KTR inspected the ongoing works at Nampally and MGBS, en route.

Rama Rao said that Trial runs and necessary safety tests are already in progress, with the certificate from the Commissioner of Metro Rail Safety approving commercial operations also expected by the end of July.

Rama Rao said that Trial runs and necessary safety tests are already in progress, with the certificate from the Commissioner of Metro Rail Safety approving commercial operations also expected by the end of July.

This 16 km busy stretch which is between Ampreet and LB Nagar is expected to bring relaxation from the heavy vehicle’s movements. Miyapur- Ameerpet stretch which is 13- km will be linked with the red line of metro rail corridor-1.

Rama Rao also added that Compared to Chennai and Bengaluru Metros, the Hyderabad Metro was registering good patronage, he said. “More than 80,000 passengers were traveling every day in Metro trains of which 40 pc use smart cards. It is very much unlike Bengaluru and Chennai where I visited, wherein the footfall used to be a meager 25,000 initially”.

Rama Rao also added that Compared to Chennai and Bengaluru Metros, the Hyderabad Metro was registering good patronage, he said. “More than 80,000 passengers were traveling every day in Metro trains of which 40 pc use smart cards. It is very much unlike Bengaluru and Chennai where I visited, wherein the footfall used to be a meager 25,000 initially”.

Multi-level parking lots

Rao said that MAUD Minister KT Rama Rao has said tenders for construction of 42 multi-level car parking lots would be invited in 15 days. “There are complaints about lack of parking lots. We are calling tenders for 42 multi-level car parking lots. Those stretches would also be used to have commercial viability”.

Rao said that MAUD Minister KT Rama Rao has said tenders for construction of 42 multi-level car parking lots would be invited in 15 days. “There are complaints about lack of parking lots. We are calling tenders for 42 multi-level car parking lots. Those stretches would also be used to have commercial viability”.

Madhya Pradesh | Indore Metro work may kick off in August

Madhya Pradesh:- Madhya Pradesh Metro Rail Corporation Limited (MPMRCL) is ready to start out for the Phase 1 Indore Metro Rail Project in two months. The Indore Metro system will be a rapid transit system and the metro will provide free Wi-Fi connectivity for the commuters.

The Project will not only run on road bridges and in some underground location. The project will be the first driver less trains in India.
The MPMRCL had asked to district administration as there is a need of spotting and relocate the utilities that include water and electricity lines on 31.55 km stretch.

The letter was issued by the MPMRCL director, Jitendra Kumar Dubey and in his letter, he informed that company has appointed general consultant who is currently working on tender designing and in revert the district collector Nishant Warwade told Times Of India (TOI) that official of MPMRCL have sought our help in identification and shifting of utilities falling on the way of proposed first phase of Metro Rail Project Company’s official will give a Presentation in a meeting scheduled on Wednesday. The letter also concludes that the plan will soon start by August -September of Metro line Phase 3. The project is set to be completed before 2020.
As the metro run on the road, rail and underground so there is need of reallocation of other transport and there is a need for land too. Planning has been done on elevated viaducts column as there is will be the underground metro. Locations of a metro station have marked to fuse other modes of transports. So, the metro would not lead to any distortion to other transport.
As the company asked for the relocation of utilities which also conclude other electricity lines and poles and sever and telephone line way and the proposed plan of laying tracks and the station. For the shifting of utilities, the project implementation agency has requested for the collection of a nodal officer who works on the daily basis.