Namma metro’s NICE project makes progress

BANGALORE (Metro Rail News): Construction work which has not taken off for the last three years due to compensation issues on the four-acre Nandi Infrastructure Corridor Enterprise (NICE) land, will finally be seeing the light at the end of the tunnel.

On Monday, Chief Minister BS Yediyurappa instructed the Bangalore Metro Rail Corporation Ltd (BMRCL) officials to deposit the amount in court and go ahead with the civil work.

The delay over acquiring four acres of NICE land is hampering the Metro work on the Mysore road (Challaghatta stretch) Tumkur road (Bangalore International Exhibition Centre (BIEC) stretch, Kanakapura Main road stretch, and the Hosur road stretch.

While the BMRCL requires NICE land to build a station at BIEC, the NICE land is required to build the viaduct.
buy amitriptyline generic buynoprescriptionrxonline.net/amitriptyline.html over the counter
Currently, the BMRCL is unable to start the work on four stretches of Phase II project as the NICE company has brought court stay on the land acquisition process undertaken by the KIADB.

Officials said their first priority is to get the stay order vacated. The instructions were given after the BMRCL reached out to the CM for advice on fixing the compensation amount for the NICE Land. Top officials who attended the closed-door meeting on Monday said that the CM had asked the Advocate General of Karnataka to give an opinion on fixing the compensation package. NICE was not willing to comment on the subject.

A spokesperson from the NICE company told “The matter is subjudice. We have contested the land acquisition process in the High Court”.

It’s learned that the NICE firm challenged the way compensation of its land was evaluated by the KIADB. The sources in the company said “When the IT companies, who got the land for cheaper prices from the KIADB, can claim as much compensation as other land losers, why is the land acquisition agency discriminating against NICE? Let the KIADB offer the same amount of compensation as it is offering to the adjacent properties. We are not asking for more,”.

Kothanur Metro depot work to commence soon

BANGALORE (Metro Rail News): At an estimated cost of Rs 163.44 crore BMRCL has recently invited a tender for the construction of Metro rail depot structures, site development works, internal roads and drainage works in depot area at Kothanur in Reach-6 of Phase-2.

BMRCL had acquired 30 acres in Kothanur for the proposed Metro depot to facilitate stabling and maintenance work of trains on the Gottigere-Nagawara corridor.

The depot work at Kothanur was earlier delayed due to land acquisition issues. Bt 2024 the Gottigere-Nagawara corridor is likely to be operational.

Meanwhile, BMRCL had also called for tenders for the construction of road structures, drain and footpath development works between Yelachenahalli and Anjanapura and also between Nayandahalli Station (pier 437) and Nice Road Junction (pier 734).

YFC Projects bags Rs 726 cr civil contract from Delhi Metro for Phase IV project

DELHI (Metro Rail News): The Delhi Metro Rail Corporation has opened the bids of the civil construction package DC-04 of Phase IV Project Today.

YFC PROJECTS PRIVATE LIMITED, the flagship company of YFC GROUP emerged as the lowest bidder (L1) for the civil construction package DC-04 of the DMRC Phase IV project.

In fourth civil construction contract (package DC-04) of Delhi Metro Rail Phase IV, Total of six contractors participated i.e YFC Projects Pvt. Ltd., L&T Construction, KEC International Limited, NCC Limited, Tata Projects Limited and PNC-SIL JV whereas L&T Construction, KEC International Limited, NCC Limited, Tata Projects Limited and PNC-SIL JV emerged as L2, L3, L4 and L5 respectively. PNC-SIL JV got rejected.

YFC Projects Pvt. Ltd. quoted Rs 726.08 Cr against the estimated value of contract Rs. 726 crores.

Scope of Work

Part Design and Construction of Integrated structure consisting of Elevated Viaduct and 6 lane flyover (Double Deck System), Viaduct and Elevated Ramps for viaduct and flyover, Siding lines, Under Pass at Saket G, Elevated Ramp from BRT corridor to flyover and down ramp from flyover to BRT corridor (partially underground) and Four Elevated Stations viz. Sangam Vihar, Khanpur, Ambedkar Nagar and Saket G (Excluding Architectural Finishing works of stations, Steel FOB & PEB works of stations) from Chainage 14519.149 m to 18750.724 m of Aerocity to
Tuglakabad Corridor of Phase-IV of Delhi MRTS.

  • Project Cost – 726 Cr
  • Bid Submission Date – 21.11.2019
  • Opening – 17.12.2019

Participants and Bidding Amount

Bidder NameQuoted AmountRank
YFC Projects Pvt. Ltd.726.08 CroreL1
Larsen and Toubro Limited (L&T)766.00 CroreL2
KEC International Limited – Longian784.85 CroreL3
NCC Limited823.57 CroreL4
Tata Projects Limited – CHEC JV823.90 CroreL5
PNC-SILDisqualified

YFC PROJECTS PRIVATE LIMITED, the flagship company of YFC GROUP is into construction and infrastructure industry since the last three decades. YFC has potential interests in Multi-storeyed Building Construction projects, Infrastructure projects involving Roads, Highways, Bridges & Runways and Metro Rail Projects.

DPR prepared to connect Old and New Gurgaon by 2020

GURUGRAM (Metro Rail News): By the first half of 2020 work on the extension of the metro line, connecting old and new Gurgaon, could begin. A revised plan, which now awaits approval from the Centre proposes a composite network without any interchange for Rapid Metro and the Gurgaon section of Delhi Metro.

Earlier this year, the Haryana government had the School of Planning and Architecture had submitted its report, on the basis of which a fresh detailed project report (DPR) was prepared, for metro extension in September. But the exit of Rapid Metro Rail Gurgaon Limited (RMGL) meant the plan had to be revised.

Earlier this month the new plan was prepared, approved by the board of directors of the Haryana Mass Rapid Transport Corporation and the state government, and now awaits approval from the Centre.

The 31-km metro line will be extended up to Rapid Metro station opposite Ambience Mall. Here, instead of making interchange point the metro will run on the same line as the Rapid Metro. The previous DPR had proposed six interchange points in the 25 new metro stations. That has been done away with. Except for these, there are no major changes in the revised plan.

“Parts of the plan had to be modified after RMGL’s exit. The new DPR has not introduced any big changes, only minor tweaks. The plan has been sent to the government for approval,” a senior Gurgaon Municipal Development Authority (GMDA) official said, adding, “It is too early to commit to a deadline, but work on the project is expected to begin soon.”

Tenders for the project could be floated by January or February after approval from the government. The metro station after Huda City Centre, the last station on the Yellow Line now, will be Sector 45. It will go on to Cyber Park, connect Udyog Vihar Phase 6, Palam Vihar and continue onwards till Cyber City Station — 25 stations in all — as proposed in the previous plan. Upon completion, new and old Gurugram will be connected by metro — a relief for commuters from Udyog Vihar, Hero Honda Chowk, and even new Gurugram.

The final plan, prepared by the Haryana Mass Rapid Transit Corporation, is to connect old Gurugram and new Gurugram with a metro loop. With the Regional Rapid Transit System being developed simultaneously, most metro stations will be developed into multi-modal transit points.

Maha-Metro claims to have planted 1,681 trees, transplanted 14,645 in two years

PUNE (Metro Rail News): Maharashtra Metro Rail Corporation Limited (Maha-Metro) claims that since the construction of the Pune metro commenced it has planted 1,681 new trees and transplanted 14,645 trees in two years.

Maha-Metro is currently constructing two routes – Pimpri-Chinchwad Municipal Corporation (PCMC) to Swargate and Vanaj to Ramwadi, work for which is underway.

“The Maha-Metro has so far planted 1,681 new trees and has transplanted 14,645 trees which come along the way of the metro project. The trees have been planted across the city at Akurdi Eco Park, Cooperation Centre, Akurdi Metro Eco Park, Kharadi FS, and Army Campus, Pimple Nilakh, Deccan College Campus. Trees have also been transplanted at Kasarwadi STP, Forest ARAI, Ahmednagar roadside, Deccan Embroidery, Range Hill, KS Gurukul, PWD office, Yerawada Open Jail, Bund Garden, Nagar road, near Aare Dairy bus stand, Alandi, MSRTS bus depot, Agriculture College, Range Hill, and Vanaj garbage depot”, a press statement said.

“For every metro project, we undertake we make sure the project is sustainable right at the design state. So we follow this rule in all metro projects undertaken by Maha-Metro be it Nagpur, Pune or the future Warangal metro project”, said by Hemant Sonawane, general manager, Maha-Metro, public relations department

Press Release says that “With the arrival of the metro, the number of vehicles will be reduced from various roads in the city. Therefore, pollution control is going to have a big impact. To maximize the use of public transport, Maha-Metro has taken various measures to connect Pune Mahanagar Parivahan Mahamandal Limited (PMPML), Maharashtra State Road Transport Corporation (MSRTS) and railway stations keeping in mind the multimodal integrated hub.

1,681 trees planted

14,645 trees transplanted

Officials are doubtful of making 45 Vande Bharat rakes in 2 years

NEW DELHI (Metro Rail News): The Railway Ministry clearing the decks for the Integral Coach Factory (ICF) here to continue making Vande Bharat Express trains is seen as a welcome move though senior officials are doubtful of rolling out 45 rakes, 720 coaches, by 2021-22.

Even if tenders are floated immediately as per the revised specifications approved by the Research Designs and Standards Organisation (RDSO), it would take at least two years to roll out the first prototype for operation after the mandatory oscillation tests and safety approvals.

A senior railway official told on Sunday that, while it would take three months to open tenders for scrutiny, another two months would be needed to finalize and award work.
buy premarin online https://www.parkviewortho.com/wp-content/languages/new/prescription/premarin.html no prescription

Three national awards bagged by L&T metro rail

HYDERABAD (Metro Rail News): The L&T Metro Rail (Hyderabad) Limited received three national awards for best social media for PR and Branding, Best Communications campaign- External Publics and Best corporate film-English during the 41st PRSI National Conference held in Hyderabad recently.

The awards were received by Anindita Sinha, Head, Corporate Communications, L&TMRHL from Home Minister, Md Mahmood Ali in the presence of KV Ramana Chary, State government, media advisor, and Dr. Ajit Pathak, National President, PRSI.

The awards were in the category of Best Social Media for PR & Branding, Best Communications Campaign – External Publics and Best Corporate Film – English.
The conference theme was ‘CSR: A Brand Building Gateway for Corporates’.

KVB Reddy, MD & CEO, L&TMRHL said the awards reinstate their commitment towards the Hyderabad Metro Rail Project. “We have been positively reaching out to our commuters with innovative campaigns to create awareness for their safe and secure commute. Our endeavor is to better our services and operations enhancing the commuter experience”.

After violent protests for CAB on street, several metro stations were shut at Delhi

NEW DELHI (Metro Rail News): On Sunday evening, the aftermath of violence during protests against the amended Citizenship Act in south Delhi, DMRC closed gates of several metro stations, including GTB Nagar, Shivaji Stadium, Patel Chowk and Vishwavidyalaya

The Delhi Metro Rail Corporation (DMRC) in a series of tweets said that entry and exit gates of GTB Nagar, Shivaji Stadium, Patel Chowk, Vishwavidyalaya, Vasant Vihar, Munirka, R K Puram Metro stations were closed on the advice of the police.

According to DMRC, trains will not halt at these stations.

Earlier entry and exit gates of the Sukhdev Vihar metro station on the Magenta line were closed by the DMRC in view of the violent protest in southeast Delhi against the Amended Citizenship Act.

DMRC tweeted on Sunday, “As advised by Delhi Police, entry & exit gates of Sukhdev Vihar and gate no. 3 of Ashram have been closed. Trains will not be halting at Sukhdev Vihar”.

With no trains halting at these stations Entry and exit gates of Jamia Millia Islamia, Okhla Vihar, and Jasola Vihar Shaheen Bagh were also been closed.

As per the new security updates, on Monday morning entry and exit gates were opened and normal services have resumed at all stations.

DMRC tweeted, “Security Update. Entry and exit gates at all stations have been opened. Normal services have resumed in all stations”.

UPMRC invites consultancy bids for Kanpur and Agra Metro Project

Lucknow, India (Metro Rail News): The Uttar Pradesh Metro Rail Corporation Limited (UPMRC) invited request for proposal (RFP) from the eligible and experienced bidders for providing general consultancy services (GCS) for Kanpur and Agra Metro Rail projects in Uttar Pradesh State

Important information

  • Tender Notice No.: UPMRC/KNPAGGC-01
  • Date of Issue: December 12, 2019,
  • Scope of work: General Consultancy services for Kanpur and Agra Metro Rail projects.
  • Contract Period: 5 years
  • Estimated Cost of Work: Refer tender document
  • Security Money Deposit: INR 2,00,00,000.00
  • Tender Document Cost: INR 100,000 or USD 1450
  • Sale of Tender Documents: 13.12.2019 to 23.01.2020
  • Pre-bid Meeting: 03.02.2020 at 11.00 hrs
  • Last date for submission of Bids: 02.03.2020 till 15.00 hrs
  • Opening date of Technical Bids: 02.03.2020 at 15.30 hrs

Eligibility Criteria

Work Experience:

The Applicants must be having prior experience of working as General Consultant/Project Management Consultant/Detailed Design and Construction Supervision Consultant for an MRTS/High-Speed Rail Projects involving the work of framing specifications, drawing up contract documents, checking designs, Project management and Supervision including inspection, safety, quality, testing & commissioning.

The Bidder should have completed during the last 07 (seven) years:-

  • Single similar work costing not less than INR 3000 million (USD 42 million) or
  • Two similar works costing not less than INR 1850 million (USD 26 million) each.
  • Three similar works costing not less than INR 1500 (USD 21 million) each.

Financial Eligibility Criteria

  • Average Annual Turnover: Minimum average annual turnover of INR 1600 million (USD 2.23 million)
  • Net Worth: Net Worth of minimum INR 160 million (USD 0.23 million) in the last audited Financial year.

Pre-Bid Meeting Venue/Contact Point

The Chief Engineer/Contract
Uttar Pradesh Metro Rail Corporation Limited,
Administrative Building, Vipin Khand,
Gomtinagar, Lucknow,
Uttar Pradesh 226010, India
E-mail: cecontractlmrc@gmail.com
Office No.: 0522-2304014

Read more: Agra Metro Rail Project | Kanpur Metro Rail Project

MMRC Recruitment 2019: Apply online for Architect and Various Engineering post in Mumbai Metro

MUMBAI (Metro Rail News): Mumbai Metro Rail Corporation (MMRC) Limited intends to appoint qualified and experienced professionals for the following posts on Contract / Deputation basis:

MMRC Recruitment 2019 Vacancies

  1. Dy. Town Planner: 02 vacancies, Pay Scale: ₹60000 – 180000/- (E3)
  2. Dy. Engineer-I (MEP) – Elect. & Mech. : 01 vacancy, Pay Scale: ₹60000 – 180000/- (E3) 
  3. Architect: 01 vacancy, Pay Scale: ₹60000 – 180000/- (E3) 
  4. Dy. Engineer (Civil): 01 vacancy, Pay Scale: ₹50000 – 160000/- (E2)
  5. Accounts Officer: 02 vacancies, Pay Scale: ₹50000 – 160000/- (E2) 
  6. Jr. Engineer-I (MEP) – Elect. & Mech. : 03 vacancies, Pay Scale: ₹35280 – 67920/- (W6) 
  7. Deputy Accountant: 04 vacancies, Pay Scale: ₹34020 – 64310/- (W5) 

How to Apply for MMRC Recruitment 2019

Eligible candidates may apply online on prescribed format at MMRC website from 10/12/2019 to 24/01/2020 only for Government Job Vacancy Recruitment in MMRCL 2019.

Detailed information and online application format

Please visit the Career section of MMRCL website at  https://www.mmrcl.com/en/careers for details of Government Job Vacancy Recruitment in MMRCL 2019 and online application format.

Selection Process

How to Apply