Home Blog Page 448

Mumbai Metro achieves 37th Breakthrough at CSMT Metro Station

MUMBAI: Mumbai Metro Rail Corporation (MMRC) on 22nd April achieved 37th breakthrough at Chhatrapati Shivaji Maharaj Terminus (CSMT) Metro Station out of the total 41 breakthroughs planned for the 33.5 km long Colaba-Bandra-Seepz underground line (Line-3) of Mumbai Metro.

The contract for this work under Package UGC-01 was awarded to the JV of Larsen & Toubro and Shanghai Tunnel Engineering Company which operates Tunnel Boring Machine (TBM) Surya-2 for the construction of tunnels and four stations at Cuffe Parade, Vidhan Bhavan, Churchgate & Hutatama Chowk.

According to MMRC, TBM Surya-2 completed its final drive of 569 meters from Hutatma Chowk to CSMT Metro Station in 106 days using 418 concrete rings. With this 2.9 km long downline tunnel from Cuffe Parade to CSMT Metro Station is completed.

“Tunnelling in the heritage precinct, which is also in the close proximity to the sea, is a daunting task. MMRCL team of contractors, consultants, engineers and workers scientifically dealt the challenge successfully. I am happy that 96% of tunnelling has been completed in package-1 by ensuring the safety of the historical buildings”, said Mr. Ranjit Singh Deol, Managing Director, MMRC.

With this breakthrough, 52 km of tunneling is completed out of the total length of 54.5 km which is approximately 95% of the total project.

The issue regarding construction of car shed for Mumbai Metro Line-3 is still not resolved as the Bombay High Court is yet to decide whether the salt plan land in Kanjurmarg, where the metro depot is proposed to be constructed, belongs to the Centre or State.

UPMRC Place Second Steel Girder at Rawatpur of Kanpur Metro

The 9 KMs long elevated Priority Corridor between IIT Kanpur and Motijheel is being constructed under the Kanpur Metro Rail Project. Last night another ‘Steel Girder’ was erected at Rawatpur Tiraha. In this span the first ‘Steel Box Girder’ was placed on March 27, 2021. These girders are of 45m length, assembled near the location and erected by cranes in the night on the busy crossing.


On this occasion, Managing Director, UPMRC, Shri Kumar Keshav said, “In view of heavy traffic at Rawatpur, it was planned that no Piers should come in the middle of Rawatpur Tiraha and due to this the distance between the two Pillars was increased up to 45 meters in this section. This is the reason that in this span two specially designed light weighted ‘Steel Box Girders’ have been placed instead of U or I-girder. UPMRC always strives to ensure that the Metro Corridor is planned and is executed in such a way that traffic movement doesn’t get affected.”

Three locations have been identified between IIT and Naubasta (Corridor-1), where Steel Girders are to be laid. The first Steel Span has been placed near Rawatpur, the second will be erected at Sisamau Nala and the third one near Vasant Vihar.

Why ‘Steel Box Girder’?

• It was not possible to place a U or an I-girder of this length at the said span hence ‘Steel Box Girder’ has been introduced.

• The length of the steel girder is longer than the U-girders that are being used in the Corridor but relatively lighter in weight. It is also to be mentioned that the length of the referred steel span is 45 meters while U-girder has an average length of 27 meters. A 27-meter U-girder weighs about 147 tons, while 45-meter Steel Span weighs about 120 tons.

• Three locations have been identified between the 23KMs long IIT & Naubasta stretch in where Steel Girders are to be laid. The first Steel Span has been placed near Rawatpur, the second will be erected at Sisamau Nala and the third one will be placed near Vasant Vihar. Separate steel girders are to be laid for up-line and down-line.

Each 45-meter long steel girder is being prepared by connecting 5 segments.

MMRDA invites tender for balance works for Line-2B of Mumbai Metro

MUMBAI: Mumbai Metropolitan Region Development Authority (MMRDA) has invited open e-tenders for the construction of balance works of Package CA06 which is related to Line 2B (D.N Nagar-Mandale) of Mumbai Metro Rail Project. The balance work includes construction of elevated viaduct and 5 elevated stations from MTNL Metro to Chembur.

Name of Work

Part Design and Construction of Balance Works of Package CA06, Elevated Viaduct and 5 Elevated Stations viz. MTNL Metro, S. G. Barve Marg, Kurla East, EEH and Chembur (excluding Architectural Finishing and Pre-Engineered Steel Roof Structure of Stations) from Chainage 46860.384m to Chainage 52729.312 of Line 2B [D.N Nagar-Mandale] of Mumbai Metro Rail Project of MMRDA.

Important Details

Contract NoMMRDA/MMRP/L2B-C102

Estimated Cost of Work: INR 631.82 Crore

Completion Period: 30 Months

Bids Document Download Date: 22/04/2021 from 18.01 Hrs to 07/06/2021 till 15.00 Hrs

Bid Submission Date: 22/04/2021 from 18:31 to 09/06/2021 till 18.00 Hrs

Pre Bid Meeting: 06/05/2021 at 11.00 Hrs

Bid Opening Date: 11/06/2021 at 11:00 Hrs

MMRDA has invited bids for this work multiple times while originally in 2017 contract for this work was awarded to RCC Infra Ventures Limited but the contract was terminated in January 2020 due to poor progress of work.

Last time when MMRDA invited bids for this work, NCC Limited emerged as the lowest bidder (November 2020) quoting bid value of INR 719.27 Crores which was way above the MMRDA estimated cost of INR 568.55 Crores and further negotiations between the two did not result in any positive outcome leading to re-inviting of tenders.

Now it remains to be seen how the work progress on this section of Mumbai Metro Line-2B as work is already got delayed. Hopefully, this time tenders invitation will culminate to starting of construction on the given section which will take another few years before operations of metro trains start on this section.

There is also a proposal to build three iconic bridges on this 23.64 km long Metro Line 2B from DN Nagar to Mandale. The designs for the bridges are already ready and tenders were floated for the second time in June 2020 for their construction. The bridges to be constructed are Arch shape bridge over Mithi River, Zero shape bridge at Vakola Nala and the Sword shape bridge at BKC Entry. The purpose is to give aesthetic look to the surrounding areas through these all three cable-stayed bridges. Mumbai will look more beautiful through these bridges and the bridges will be visible from far distances creating new skyline for the city. Hopefully, construction of bridges will start at the earliest to add another jewel to the city that never sleeps.

Bharat Builders and Starworth Infrastructure wins work contracts for Bangalore Metro

BENGALURU: Bharat Builders has bag contract for construction of seven Foot-Over-Bridges (FOB) at six locations of Phase-1 and Phase-2 stations of Bangalore Metro Rail Project.

Important Details

Tender Notification Number: BMRCL/Phase-1&2/FOB-Steel Structures/2021/74

Name of Work: Fabrication & Erection of Steel Structures – 7 Nos. of FOB at 6 locations in Yeshwanthpur, Dasarahalli, Nagasandra Stations of Phase-1 and Mailasandra, Jnanabharathi, Chikkabidarkallu (Jindal) Stations of Phase-2 for Bangalore Metro rail Project.

Contract Value: INR 10.84 Crores

On the other hand, Starworth Infrastructure & Construction Limited has bag contract for construction of Operation Control Centre (OCC) near Baiyappanahalli Metro Depot for Bangalore Metro Rail Project.

Important Details

Tender Notification Number: BMRCL/Phase-2/OCC-2/2020/71

Name of Work: Construction of Operation control center near Baiyappanahalli Metro Depot for Bangalore Metro Rail Project.

Contract Value: INR 23.12 Crores

In an another good news for the Bangalore city, the Union Cabinet on Tuesday approves Bangalore Metro Rail Project Phase-2A and Phase-2B with total length of 58.19 km. The total cost of the project is expected to be INR 14,788.101 crore.

Phase-2A comprises construction of 19.75 km long elevated corridor connecting KR Puram to Central Silkboard with 13 stations while Phase-2 comprises construction of 38.44 long corridor connecting K R Puram to the Kempegowda International Airport via Hebbal Junction with 17 stations on the route.

GPS based CORS technique to ensure accurate alignment of Rapid Rail

New Delhi, April 23, 2021– The Linear Railway infra projects require high accuracy surveys to achieve designed track alignment. Given the design speed of 180 kmph on the structure either elevated viaducts or underground tunnels, there is no scope for fault in the construction of RRTS structures and tracks. The NCRTC is using “Continuously Operating Reference Station (CORS)” technology to ensure accurate civil structure alignment in the construction of Delhi-Ghaziabad-Meerut RRTS Corridor.

CORS image 2

 
CORS- Continuously Operating Reference Station – is a global positioning system (GPS) based technology mainly used in surveys, mapping, and allied services. This technique ensures complete accuracy in the construction of a predetermined corridor in civil construction so that the planned alignment can be achieved.


Delhi-Ghaziabad-Meerut is an 82 km long corridor going over rivers, railway lines, roads, expressways, and flyovers. Hence it is very important to maintain accuracy in civil structure alignment. Keeping this in mind, the NCRTC went beyond the traditional technologies and adopted an ultra-modern survey technique, CORS, which is being used for the first time in the country in any mega infrastructure project.  

CORS image 3

CORS is a network of ‘reference stations’ that are established at every 10-15 kilometers along with the Delhi-Ghaziabad-Meerut RRTS corridor, these CORS ‘reference stations’ are connected to the “Control Center”, which provides the real-time data to the rovers collected from 3-5 reference stations. The entire process of data collection enables the rovers to achieve accuracy of up to 10 mm.


Also, given the limited timeframe for the implementation of the country’s first RRTS project, the construction work is in progress at multiple sites simultaneously. To ensure that construction at multiple locations does not impact the accuracy of the project, CORS is being used as it mitigates the risks of any kind of error during the construction. The CORS network is set up for the first time in the country for a rail-based project, the system is set to be a path-breaking system for such projects to conduct surveys.

Agra Metro completes half pilling work in record time

AGRA: Half of the pilling work has been completed in record time for the Agra Metro Rail Project. A total of 344 piles have been completed in less than four and half months out of the 688 piles to be made for the elevated portion running from Taj East Gate to Fatehabad Road with three elevated stations.

At present, work of 344 piles, 33 pile capes and 11 pillars have been completed for the 3 km long elevated portion of Priority Corridor. For the elevated section, 688 piles, 171 pile caps and 171 pillars and 104 pier caps are to be constructed.

Regarding update on the construction of first depot for Agra Metro on Line-1 at PAC ground, boundary wall of 680 meters has been completed so far out of the total 2400 meters. Casting of 50% blocks for the boundary wall is also completed along with work on other structures is also going with full speed for the metro depot. Work for metro depot construction was awarded to Lisha Engineers Pvt. Ltd in October 2020 for a contract value of INR 112.63 crores and is expected to be completed by June, 2022.

The Priority Corridor of Agra Metro comprises construction of 6 km long section from Taj East Gate to Jama Masjid with six stations. Contract is awarded to Sam India Built Well Pvt. Ltd. for the elevated portion of length 3 km with 3 stations namely – Fatehabad Road, Basai & Taj East Gate. However, tender is still pending for the underground section of length of 3 km that will run from Jama Masjid to Taj Mahal with three underground stations.

Uttar Pradesh Metro Rail Corporation (UPMRC) has set a deadline of March 2024 to start operation of metro trains on the Priority Corridor.

Line-1 (14.24 km) of Agra Metro is partly elevated (6.56 km) and partly underground (7.68 km) with 14 stations. These stations are Sikandra, Guru Ka Taal, ISBT, Shastri Nagar, RBS College, Raja Ki Mandi, Agra University, Medical College, Jama Masjid, Agra Fort, Taj Mahal, Fatehabad Road, Basai & Taj East Gate.

RVNL invites tender for S&T works for Majorda – Vasco-Da-Gama Railway section in South Goa

NEW DELHI: RailVikas Nigam Limited (RVNL) invites bids under single stage two packet system for the supply and commissioning of signalling and telecommunications works related to doubling of Majorda – Vasco-Da-Gama section in South Goa.

Name of Work

‘Design, Supply, Installation, Testing and Commissioning of Indoor & Outdoor Signalling and Telecommunications works in connection with doubling of Majorda (Excl.) – Vasco-Da-Gama (Incl.) section of Hubbali Division of South Western Railway in South Goa District of Goa State, India’.

Important Details

Tender Reference Number RVNL/SBC/SnT/MJO-VSG/2021/OT03

Estimated Cost of Project – INR 31.58 crores

Period of Completion 18 Months

Pre Bid Meeting Date 05-May-2021 at 11:30 AM

Document Download Start Date 20-Apr-2021 from 04:00 PM

Document Download End Date 25-May-2021 till 11:00 AM

Bid Submission Start Date 10-May-2021 from 09:00 AM

Bid Submission End Date 25-May-2021 at 11:00 AM

Bid Opening Date 25-May-2021 at 11:30 AM

Further Details

For more information and further details  on detail scope of works, applicants can download tender documents free of cost from RVNL website www.rvnl.org and RVNL e- Tendering portal i.e. https://rvnl.euniwizarde.com/

This tender work is a part of project related to doubling of 342 km long railway track from Hospet in Karnataka to Vasco-da-gama in Goa. According to Ministry of Railways, the project has nearly completed in the state of Karnataka except 10 Km between Unkal and Hubballi stretch which was expected to be completed in March this year.

About 7 km track between Madgoan- Majorda in the state of Goa has also been doubled. Remaining stretch of about 90 Km is in the State of Goa, where works are awarded for doubling and are being taken up after ensuring necessary clearances.

Doubling of the said section will be a game changer for the state of Goa, taking the development to new heights, by giving impetus to trade and enabling easier and faster passenger movement. Existing rail network is constrained due to single line long ghat sections severely limiting train running capacity.

RITES led consortium emerges lowest bidder for Bangladesh Railway Project

MUMBAI: RITES led consortium emerged as the lowest bidder for the construction of dual gauge railway line from Bogura to Shahid M. Mansur Ali station of the Bangladesh Railway.

In February 2019, Export and Import Bank of India (EXIM) invited Project Management Consultants (PMC) for Construction of Dual Gauge Railway Line from Bogra to Shahid M. Mansur Ali Station of Bangladesh Railway (79.30 km Dual Gauge main and 11.35 km Dual gauge loop line) in Bangladesh.

This is an 80 km long green field project with two phases—

  • Preparation of a detailed project report (DPR)
  • Construction supervision.

Duration for the project is 13 months for Phase-1 and 30 months for Phase-2. This project is funded by EXIM Bank of India under Line of Credit (LOC).

Total Fee Income would be about Rs. 63 crores and signing of Contract is expected to take place soon.

Scope of work –

  • Consultancy Services for Updating Feasibility Study, Detail Engineering Design, Mathematical Modeling, Tendering Services and Construction Supervision, Services during Defect Liability Period.
  • Conduct detail topographic and hydrographic survey.
  • Identify the possible alternative alignments and recommend the best suitable alignment for the project.
  • Find out whether the project will be technically, economically, financially, environmentally and socially viable. 
  • Prepare Initial Environment Examination report, Environmental Impact Assessment, Environmental Management Plan & Environmental Monitoring Plan etc.
  • Prepare Land Acquisition Plan and Resettlement Plan.
  • Conduct detailed engineering survey including sub-soil investigation along the alignment, at bridge locations.
  • Conduct hydrological & morphological survey. 
  • Prepare detailed engineering design and drawings of all infrastructures including bridges, embankment, railway track, stations, signaling and all other facilities. 
  • Prepare detailed cost estimate on the basis of the detail design and drawing and verify the same with the DPP. Also prepare the revised DPP [RDPP] if required. 
  • Prepare tender documents in conformity to the procurement rules of Bangladesh.
  • Provide tendering services of all sorts including preparation of RFP, selecting contractor, bid evaluation, provide assistance to the project authority for award of contract, including contract negotiation and finalizing the contract documents.

Metro rail construction in Indian cities is advancing at a rapid pace despite Covid-19

NEW DELHI (Metro Rail News): Despite the menace of Covid-19, metro rail construction activities across many Indian cities are moving at rapid pace as tenders are continue to invite for various metro projects along with awarding of contracts which further aided by soft loans from multilateral agencies and contribution from central and state governments.

Work is already underway for Delhi Metro Phase-4 and recently JICA (Japan International Cooperation Agency) gave approval for soft loan amounting to INR 8,390 crores for Phase-4 of Delhi Metro and INR 3,717 crores for Phase-2 of Bangalore Metro.

Mumbai Metro’s Line-2A and Line-7 will start operation this year. Work is progressing at a rapid pace for the other under-construction lines with MMRDA continue to invite tenders and award contracts for multiple works on various lines. Recently, Maha Metro also invited bids to complete the remaining works related to Navi Mumbai Metro Line-1 (11.1 Km) from Belapur to Pendhar.

Work on next phase of metro construction is already underway in the cities of Chennai and Bangalore. Giving boost to metro connectivity in cities of Madhya Pradesh, MPMRCL in March invited tenders for construction of elevated viaducts and stations for Indore and Bhopal Metros respectively.

In Uttar Pradesh, construction activities for metro systems in Agra and Kanpur are progressing at rapid pace. Track laying work is already started on Delhi-Meerut RRTS.

In Bihar, tender inviting activities for Patna Metro have started gradually. In Kerala, Kochi water metro will began operation on the Vyttila-Kakkanad route by the end of this month.

As per reports, the quantum of civil construction bids currently underway in this sector is higher than the sum of projects awarded in FY 20 & FY21.

400 U-girders placed so far on 9 km long Priority Corridor of Kanpur Metro

KANPUR (Metro Rail News): The pace of construction of Kanpur Metro Rail Project is unprecedented as 400 U-girders have been placed so far on viaduct out of the total 622 to be placed on the 9 km long Priority Corridor running from IIT to Motijheel with 9 elevated stations.

As a result, base of metro track for around 5 km has been completed so far out of the total length of 9 km of Priority Corridor.

Uttar Pradesh Metro Rail Corporation (UPMRC) aims to start operation of metro trains on 9 km long Priority Corridor from December this year. On completion as per deadline, Kanpur Metro will become the fastest built and commissioned metro project in the world.

AFCONS has won the contract for this work in September 2019 with Bombardier Transportation (now acquired by Alstom) won contract to provide rolling stock and signaling systems for the project in July 2020.

Kanpur Metro also become the first metro in India to use double T-girders for a metro rail corridor which saves cost and time to a great extent. The casting of all 439 double T-girders has been already completed and the erection of these double T-girders is completed on 8 metro stations out of the total 9 metro stations on Priority Corridor.

UPMRC has also come up with an  another innovation in the form of ‘Twin pier Cap’ which is constructed for the Kanpur Metro depot line which will run from Gurudev to Geeta Nagar connecting the mainline and the Polytechnic Metro Depot.

According to the Managing Director of UPMRC, Kumar Keshav, “Twin Pier Cap is the second such successful innovation after the double T-girder, which has been implemented in the Kanpur Metro Project for the first time in the Metro Rail sector of India and it is a matter of pride for all of us. The credit for this goes to the research and innovation based working style of our metro engineers. The entire team of UPMRC, civil contractor AFCONS and the General Consultants deserve applause on this achievement. I am quite confident that the Kanpur Metro Rail Project will emerge as a paradigm for all other Metro Rail Projects in the country.”

In Phase-1 of Kanpur Metro Rail project, two corridors will be built. The first corridor (Red Line), with length 23.7 km, will have 22 metro stations and the second corridor (Blue Line), with length 8.6 km, will have 8 metro stations. Trail run is expected to start on Priority Corridor by November this year.