18.1 C
Delhi
Wednesday, February 18, 2026
spot_img
spot_imgspot_img
Home Miscellaneous Indian Railways Ministry of Railways shares Dimapur-Kohima Project Progress Report

Ministry of Railways shares Dimapur-Kohima Project Progress Report

3 Tunnels completed, 3 are under advanced & 14 are at mobilization stage.

0
583
Dimapur-Kohima Railway Progress Report
Dimapur-Kohima Railway Progress Report

NAGALAND (Metro Rail News): Ministry of Railways shared the Dimapur-Kohima Project Progress Report on its Twitter handle.

Advertisement1
InnoMetro_2026

The state of Nagaland’s capital, Kohima, will be connected to the rail network via the 82-kilometer-long Dimapur-Kohima railway project. This rail project is scheduled to be completed in March 2023.

3 Tunnels completed, 3 are under advanced & 14 are at mobilization stage, 4 major bridges Superstructures are complete, 8 are in progress, Substructure of 11 bridges are complete, 8 are in progress, and 134 minor bridges out of 198 are completed.

LEAVE A REPLY

Please enter your comment!
Please enter your name here

This site uses Akismet to reduce spam. Learn how your comment data is processed.