NAGALAND (Metro Rail News): Ministry of Railways shared the Dimapur-Kohima Project Progress Report on its Twitter handle.
The state of Nagaland’s capital, Kohima, will be connected to the rail network via the 82-kilometer-long Dimapur-Kohima railway project. This rail project is scheduled to be completed in March 2023.
3 Tunnels completed, 3 are under advanced & 14 are at mobilization stage, 4 major bridges Superstructures are complete, 8 are in progress, Substructure of 11 bridges are complete, 8 are in progress, and 134 minor bridges out of 198 are completed.