L&T emerged as lowest bidder for Mumbai – Ahmedabad Bullet Train’s T3 Track Work

Package T-3 in Gujarat is the second of three track related packages (T-1, T-2, T3) of this HSR line and will connect Mumbai and Ahmedabad through 12 stations at an estimated cost of Rs. 1.1 lakh crore.

0
1193
Mumbai-Ahmedabad Bullet train
Image credits: NHSRCL

MUMBAI (Metro Rail News): Larsen & Toubro on 25th March emerged as the lowest bidder to design, manufacture and install tracks (Package T-3) of the 508.17 km Mumbai – Ahmedabad High Speed Rail (MAHSR Bullet Train) project.

Package T-3 in Gujarat is the second of three track related packages (T-1, T-2, T3) of this HSR line and will connect Mumbai and Ahmedabad through 12 stations at an estimated cost of Rs. 1.1 lakh crore.

It is a stretch of 116.175 km from south of Vadodara city to Sabarmati Depot through civil packages C5 (awarded to L&T), C6 (under construction by L&T), C7 (awarded to IRCON_DRA) and C8 (awarded to SCC-VRS JV)

India’s National High Speed Rail Corporation (NHSRCL) invited bids for this package in August 2021 with an undisclosed estimate and 5.36 years completion period. The technical bids for this were opened in December 2021 to reveal 4 bidders.

Financial Bid Values (Note: final approximate value is a combination of all currencies)

FirmPrice Bid
Larsen & Toubro (L&T)INR 930,15,73,983 + JPY 34180846879 (Approx. Rs. 3069 cr)
NCC – Rahee Infratech JVINR 1641,74,70,220 + JPY 27826910566 + USD 23300341 (Approx. Rs. 3560 cr)
IRCON InternationalINR 1496,86,81,729 + JPY 31499429969 + USD 24299243 (Approx. Rs. 3652 cr)
Tata Projects Ltd. (TPL)Disqualified in Technical Bid Evaluation

Tender: MAHSR-T-3

The brief scope of this package includes Design, Supply and Construction of Track and Track related Works including Testing and Commissioning on Design-Build Lump Sum Price basis for Double Line High Speed Railway between Vadodara (MAHSR Km. 393.700) and Sabarmati Depot and Workshop (MAHSR Km. 509.875) in the State of Gujarat for the Project for Construction of Mumbai-Ahmedabad High Speed Rail.

A special slab track system will be utilized for the Bullet Train project instead of a conventional ballasted track system found in main-line railway lines.

Here’s the scope and status of the Mumbai – Ahmedabad Bullet Train’s 3 track-work packages:

PackageStatus
T-1 (Maharashtra): Design, Supply & Construction of Track & Track related works between HSR station at BKC/ Mumbai and Zaroli Village on MH/GJ border (156.855 km)Tender Notice Pending
T-2 (Gujarat): Design, Supply & Construction of Track and Track related works between Zaroli Village and Vadodara (237.10 km)Awarded to IRCON
T-3 (Gujarat): Design, Supply & Construction of Track and Track related works between Vadodara and Sabarmati Depot and workshops (114.60 km)L&T is lowest bidder