MUMBAI (Metro Rail News): Paras Railtech Private Limited has received a Letter of Acceptance (LoA) for the second ballastless track contract CA-273 of the Mumbai Metro Line 2B (Yellow Line). This line spans 23.6 km between Andheri West and Mandale.

In March 2025, the Mumbai Metropolitan Region Development Authority (MMRDA) floated a tender for Package CA-273 with a value of Rs. 121.83 crore. Technical bids were opened on 22 April, revealing that 3 firms have submitted bids for the contract. On 14 May technical evaluation of the submitted bids took place.
Financial bids for the contract were opened on 14 May 2025. Financial evaluation of the technically qualified bids took place on 6 August. During the financial evaluation, round 2 firms’ bids were rejected, and Paras Railtech was declared the lowest bidder for the contract. On 11 August 2025, Paras Railtech received LoA for the contract.
Financial Bid Values
Company | Amount |
Paras Railtech Private Limited | ₹ 99.9 Cr |
Purvakriti Infrastructure Pvt Ltd | ₹ 18.9 Cr |
Rahee Infratech Limited | ₹ 12 Cr |
Contract Duration: 600 Days
The awarded contractor will be responsible for the installation of standard gauge ballastless track between Andheri West Station and ITO Station in Bandra-Kurla Complex.
MMRDA’s Brief Scope: Design, Supply, Installation, Testing And Commissioning Of Standard Gauge Ballastless Track In Main Line From Andheri West (Excluding Station Ch: 34+035.873) To ITO Station (Including Station Ch:44+857.698) Of Line-2B of Mumbai Metro Rail Project.
Also Read: 3 Firms Bid for Track Contract CA-273 of Mumbai Metro Line-2B
To get real-time updates on metro and railway tenders, join our WhatsApp Community: https://chat.whatsapp.com/EzkphM7r0eaGtWJXi59CLb