TBM Tatya of the Kanpur Metro Records Final Breakthrough on Package KNPCC-05

Tatya TBM was assigned to build a 420 m tunnel from the MacRobertganj to the Chunniganj portion.

0
527
TBM Tatya of the Kanpur Metro Records Final Breakthrough on Package KNPCC-05
TBM Tatya of the Kanpur Metro Records Final Breakthrough on Package KNPCC-05

KANPUR (Metro Rail News): TBM  Tatya or TBM S92 of the Kanpur Metro recorded a breakthrough at the Chunniganj station of the 32.4 km of the Kanpur Metro Phase 1. 

Assignment 

Tatya TBM was assigned to build a 420 m tunnel from MacRobertganj to Chunniganj portion on the down-line tunnel of Kanpur’s 23.785 km Line-1 (IIT Kanpur – Naubasta).

Final Breakthrough 

TBM Tatya Final Breakthrough 01

It marks TBM S92’s fourth and final tunnel breakthrough and the completion of the tunnelling activities (8 breakthroughs) planned on the project’s 3.619 km Package KNPCC-05, which connects MacRobertganj Ramp to Nayaganj Station.

The Contract 

UPMRC awarded this contract to Gulermak—Sam India in March 2021, with a 36-month deadline. The company will also build 4 stations, each 215 m long, at Chunniganj, Naveen Market, Bada Chauraha, and Nayaganj.

Kanpur Metro 

Kanpur metro is being built for Rs. 11,076.48 Crores, with its First Phase, the Orange Line running between IIT Kanpur & Motijheel, being inaugurated in December 2021 by PM Narendra Modi. The remaining 14.9 km stretch of Orange Line between Motijheel & Naubasta is under construction. 


Discover the endless possibilities of our city’s Metro at InnoMetro, our flagship Expo and Conference. Be an active participant in shaping its future towards a more sustainable tomorrow. Stay informed and join us to take a step towards a brighter future

LEAVE A REPLY

Please enter your comment!
Please enter your name here

This site uses Akismet to reduce spam. Learn how your comment data is processed.