India’s First Undersea Tunnel Work For Bullet Train Begins Soon In Mumbai

0
Mumbai-Ahmedabad Undersea Tunnel route map
Mumbai-Ahmedabad Undersea Tunnel route map

MUMBAI (Metro Rail News): The work for India’s first undersea tunnel work handed over to Afcons Infrastructure Limited, which is 21 km long for the underground package C-2 of the Mumbai- Ahmedabad bullet train project located between the underground station in Bandra Kurla Complex (BKC) and Shilphata near Kalyan.

On 9 April 2023, the financial bidding for the work was opened by the National High-Speed Rail Corporation (NHSRC) in which  Afcons Infrastructure Limited quoted by the lowest bid

The single-tube undersea tunnel that is 7 kilometres long will accommodate the twin tracks at Thane Creek (inter-tidal zone). It will also hold 39 equipment rooms at 37 locations which connect the tunnel location.

The Tunnel Boring Machines (TBMs) with a cutter head of diameter 13.1-m will be used to build this tunnel, which doubles the size of those used for the Metro. About 16 km of the tunnel portion will make by three TBMs, and the remaining 5-m stretch will be done by the New Austrian tunnelling method (NATM).

Representational Image
Representational Image

The tunnel will be about 25 to 65 metres deep from ground level, and its deepest construction point will be 114 metres below the Parsik Hill near Shilphata. Three shafts will enable the construction at BKC, Vikhroli and Sawli near Ghansoli with estimated depths of 36, 56 and 39 metres, respectively.

A 42-metre inclined shaft will facilitate the tunnelling through NATM at Ghansoli and the tunnel portal at Shilphata.

The corridor has BKC High-Speed Rail (HSR) station as the only underground station. At a depth of 24 metres from ground level, the platform is planned. Three floors have been set up on the platform: concourse and service floors along with two entry/exit points, one to facilitate access to the nearby Metro station on the 2B line and the other towards the MTNL.

Advertisement1
InnoMetro_2026

Tunnel Boring Machine -II Lowered at Moin-Ul-Haq

0
TBM lowered at Moin-Ul-Haq stadium in Patna.
TBM lowered at Moin-Ul-Haq stadium in Patna.

Patna (Metro Rail News): The very first Tunnel Boring Machines (TBM) of Patna Metro Rail Project for Corridor II was commissioned on 7th of this month in a ceremonial inauguration by CM, Nitish Kumar at Moin-Ul-Haq stadium in Patna.

Patna Metro TBM launched

In a series of the same, the second TBM was also successfully lowered in the shaft here on Sunday at Moin-Ul-Haq stadium station to construct the underground metro network. Both TBMs will complete its journey of 1494m towards university in a period of five months. There will be a gap of 4 to 5 weeks between both TBMs. After which, Both will be retrieved and re-launched for its further journey. It is to be noted that there are four no.s of TBMs in that shall be deployed for this corridor, out of which the remaining two will be launched at Gandhi Maidan station in the month of September.

Advertisement1
InnoMetro_2026

Chennai-Coimbatore Vande Bharat Express Receives Green Signal by PM Modi

0
Hon'ble Prime Minister Shri Narendra Modi flags off New Vande Bharat Express in chennai
Hon'ble Prime Minister Shri Narendra Modi flags off New Vande Bharat Express in chennai

CHENNAI (Metro Rail news): Prime Minister Narendra Modi flagged off the Chennai-Coimbatore Vande Bharat Express in a function at Dr MGR Chennai Central Railway Station on 8 April 2023 in the presence of Railway Minister Shri Ashwini Vaishnaw, Tamil Nadu Governor R N Ravi along with Chief Minister M K Stalin and Union Minister of State L Murugan.

Chennai-Coimbatore (semi-high-speed) Vande Bharat express trains will cover the distance of 495 kilometres between two cities in 6 hours and 10 minutes for all days except Wednesday. The train journey begins from Chennai connecting Tirupur, Erode, Salem, and Coimbatore.

The Chennai-Coimbatore Vande Bharat Express has eight coaches with one executive coach, accommodating 530 passengers, whereas all other Vande Bharat trains have 16 coaches.

The fare of Chennai-Coimbatore Vande Bharat Express( Train No- 20643) will be Rs.1365, including Rs.308 as a catering charge which is optional, as well as Rs.2485, which will be charged in the Executive Class, including Rs.369 as catering charges. However, the fare of Vande Bharat Express(Train No- 20644 ) will be Rs.1215 for Chair Car, which includes catering charges of Rs. 157 and Rs.2310 for Executive Cass, which will also include Rs. 190 catering charges.

Advertisement1
InnoMetro_2026

CMRL Conducts Inspection In Madurai Metro Rail Project

0
Chennai Metro
Representational image only

MADURAI (Metro Rail News): On 7 April 2023, the officials of Chennai Metro Rail Ltd.(CMRL) inspected the metro field to find a suitable place for 18 stations and a train depot planned near the Thirumangalam bus stand.

After the study, T Archunan, the director of the Madurai Metro project, studied the possibilities of constructing the elevated stations in Thoppur, Thirunagar, Thiruparankundram, and Pasumalai. He further added during the discussion of underground slope construction that it is challenging to construct an underground slope near Palanganatham Bridge.

A total of 18 stations have been provisionally identified. Out of these stations, there would be 14 elevated stations along with four underground stations to provide service from Thirumangalam to Othakadai. The construction will be on a single route at a distance of 31 kilometers, with 25 km as an elevated Flyover route and 5 kilometers on the underground route connecting nearby temples.

According to the managing director of Chennai Metro Rail Limited, M A Siddique informed that the Detailed Project Report (DPR) of Rs 8,500 crore project with 20% contribution of central and state governments and 60% external financial contribution, is expected to complete in June. He also mentioned that construction work of the metro starts in 2024 and is expected to be completed by the end of 2027.

Advertisement1
InnoMetro_2026

First Tunnel Breakthrough achieved for Delhi section of Delhi-Ghaziabad-Meerut RRTS Corridor

0
Tunnel Boring Machine (TBM) breakthrough for Delhi - Ghaziabad - Meerut RRTS corridor
Tunnel Boring Machine (TBM) breakthrough for Delhi - Ghaziabad - Meerut RRTS corridor

NEW DELHI (Metro Rail News): NCRTC has today achieved its first Tunnel breakthrough for the Delhi section of the Delhi – Ghaziabad – Meerut RRTS corridor. The tunnel Boring Machine (TBM), Sudarshan 4.1 made the breakthrough from the tunnel retrieval shaft constructed at Khichdipur, Delhi.

Shri Manoj Joshi, Secretary, Ministry of Housing and Urban Affairs, Govt. of India initiated the breakthrough by pushing the lever in the presence of Mr. Vinay Kumar Singh, MD, NCRTC. The Directors and other senior officials of NCRTC and contractors were also present on the occasion.
The first TBM of the Delhi section, ‘Sudarshan 4.1’, was lowered at the Anand Vihar launching shaft in January 2022 for the construction of RRTS tunnels between Anand Vihar and Khichdipur. This RRTS tunnel is the longest tunnel in Delhi made by any Tunnel Boring Machine and is about 3 kilometers long. RRTS tunnels have a diameter of 6.5 metres which is highly optimised as compared to global benchmarks of tunnels for similar design speed of 180 Kmph with wider and higher rolling stock.

Untitled design 10

A total of 4 tunnels are being constructed in Delhi for the 82-kilometre Delhi – Ghaziabad – Meerut RRTS corridor for to and from movement in both directions. Two parallel tunnels of about 3 kilometers long between Anand Vihar to Khichdipur towards New Ashok Nagar RRTS station and about 2 kilometer long parallel tunnels from Anand Vihar to Vaishali towards Sahibabad RRTS Station.

This is the first tunnel which has been completed in the Delhi section from Anand Vihar to Khichdipur. The other TBM ‘Sudarshan 4.2 has completed tunnelling of about 2.5 kilometer in the same direction. On the other hand, Sudarshan 4.3 and 4.4 are boring tunnels in the direction of Sahibabad from Anand Vihar and have completed the construction of more than 1.5 kilometres and 1 kilometre respectively.

Speaking on the occasion, Secretary, MoHUA while congratulating NCRTC said, “RRTS is aimed to ease regional mobility in NCR thereby reducing vehicular congestion on roads and lowering air pollution. Multi-modal integration has been one important consideration while planning and implementing RRTS. I am confident that it will enhance the quality of life in NCR.”

Untitled design 11

Mr Vinay Kumar Singh, MD, NCRTC said, “I compliment the engineers of NCRTC as well as our construction partner for completing this section of tunnelling which was a complex and challenging task.

Going towards New Ashok Nagar, it has negotiated very close to existing metro station piling structues in addition to foundations of expressways and non-engineered buildings in Patparganj and Khichdipur.

NCRTC has prioritised commuters’ convenience over ease of construction. Sarai Kale Khan and Anand Vihar RRTS station are examples of extensive multi-modal integration which will enable seamless transfers to stations of Indian Railways, ISBTs, City Bus as well as Metro.”

More than 14000 high-preciion pre-casted tunnel segments were used to construct this 3 kilometer long RRTS tunnel, ensuring a long tunnel life .The Tunnel Segments of Delhi section are being casted at NCRTC’s Casting Yard established at Karkardooma, Delhi.

NCRTC is targeting to commission the entire 82 km long Delhi-Ghaziabad-Meerut for the public by 2025. Before that, it will operationalise a 17-km long Priority Section between Sahibabad and Duhai shortly, before the scheduled time.

Advertisement1
InnoMetro_2026

PM Modi Flags Off Secunderabad-Tirupati Vande Bharat Express In Telangana

0
Hon'ble Prime Minister Shri Narendra Modi flags off New Vande Bharat Express in chennai / Representational image
Hon'ble Prime Minister Shri Narendra Modi flags off New Vande Bharat Express in chennai / Representational image

 

TELANGNA (Metro Rail News): On 8 April 2023, Prime Minister Narendra Modi flagged off the semi-high-speed train, Secunderabad-Tirupati Vande Bharat Express (Train No- 20701), from Secunderabad Railway Station.
The Secunderabad-Tirupati Vande Bharat Express Cover 660 kilometres journey in 8 hours and 30 minutes which is 3 hours and 20 minutes fast than the previous train and is scheduled to run six days a week except for Tuesday between the two cities within a short span of 3 months.
The Train fare between these two cities will be ₹ 1680, which includes ₹364 as catering charges which are optional, and for the Executive Class, it will be ₹ 3080 with catering charges of ₹419.
The train starts from Secunderabad of Telangana, connecting Nalgonda, Guntur, Ongole, and Nellore to Tirupati of Andhra Pradesh in the Abode of Lord Venkateswara.

This indigenously designed train set of Vande Bharat Express is equipped with state-of-the-art passenger amenities. The train is set to provide a faster, comfortable, and convenient travel experience to rail users. It is expected to boost tourism and promote economic development in the region.

 

Advertisement1
InnoMetro_2026

Delhi Metro Approves Tender For Geotechnical Investigation Work From New Delhi Metro To Knowledge Park II.

0
Delhi-Metro
Representational image

NEW DELHI (Metro Rail News): Delhi Metro Rail Corporation (DMRC) has approved the tender and issued a Letter of Acceptance (LoA) to M/s Cengrs Geotechnical Pvt. Ltd. for the geotechnical investigation work to prepare Detailed Project Report (DPR) of the Delhi Metro corridor from New Delhi metro to Knowledge Park II ( Greater Noida) metro station which is approximately 37. 43 kilometers long.

In January 2023, Delhi Metro invited a tender for tender number NIT/04/GM/CS/2022-23 with a completion period of 10 weeks with an awarded value of INR 16,47,204/-.

The investigation work consists of major activities such as drilling of 150 mm diameter boreholes up to 30 m depth in all types of soil with a standard penetration test conducted at a regular intervals of time as per I.S. Code practice at 1.5 m.

As well as Recording of water table level, in-situ test, collecting rock core sample and other necessary laboratory tests.

Advertisement1
InnoMetro_2026

India’s First Under Water Metro Trial To Be Conducted Soon In Kolkata

0
kolkata underwater metro/ Representational image
kolkata underwater metro/ Representational image

KOLKATA (Metro Rail News): On 9 April 2023, The Kolkata Metro Rail Corporation (KMRC) is planning to begin the trial of India’s first underwater metro rail in Kolkata, which connects the Esplanade on the east bank of the Hooghly River and Howrah Maidan on the west bank. The Howrah metro station is the deepest metro station in the country at 33 m below ground level.

This train stretch is 4.8 km with a 520-meter twin tunnel under the Hooghly River that got completed a year ago. Still, the KMRC is waiting to complete its second stretch (2.5 km) between Sealdah and Esplanade before starting commercial operations. Moreover, it will connect to the 16.6 kilometers long east-west corridor(Green Line) through sector V.

According to the KMRC officials, two six coaches trains will run on trial from the Metro Rail’s Salt Lake depot to Esplanade through the east bond tunnel between Esplanade and Sealdah, which is still experiencing regular cave-inns but the tunnel has been bridged by temporary track to perform the trial; as well as the metro between Sector V and Sealdah, is already operational.

From Sealdah to Esplanade, the trains will be pushed by battery-powered loco since it doesn’t have electrified tracks. It is further stated by the authority if everything goes well after the trial, the train will be operational in a couple of months.

Advertisement1
InnoMetro_2026

Namma Metro’s Yellow Line To Be Opened In July

2
Bengaluru Metro/Image for representational purpose only
Image for representational purpose only

BENGALURU (Metro Rail News): The Bengaluru Metro Rail Cooperation Limited (BMRCL) is likely to open its Yellow Line for the public by July of this year. The yellow line connects the southeast part of Bengaluru between RV Road to Bommasandra.

According to the BMRCL, this 19-kilometer line having 16 stations, connects many major busy areas of the city. The stations begin from Rashtreeya Vidyalaya Road (RV road) to Bommasandra connecting Ragigudda, Jayadeva Hospital, BTM Layout, Central Silk Board, Bommanahalli, Hongasandra, Kudlu Gate, Singasandra, Hosa Road, Beratena Agrahara, Konappana Agrahara, electronic city, Huskuru Road, Hebbagodi and Bommasandra stations.
The new Yellow Line connects to the Green Line at RV Road.

Similarly, it will intersect with the upcoming Pink Line (Gottigere-Nagawara) at Jayadeva Hospital and with Blue Line at Central Silk Board Station and will proceed to Bommasandra.
It is further stated by the BMRCL authority that major construction work, such as the laying of tracks and the stations, has been completed.

Therefore, if the final steps of the work are done according to the planned time, the Line will be operational by late July or early August this year.