Kalpataru becomes L1 for Nagpur Metro Phase 2’s Package -C11

0
Nagpur Metro

Nagpur ( Metro Rail News): Maharashtra Metro Rail Corporation Ltd. ( MMRCL or MahaMetro) declared Kalpataru Projects International Ltd.( KPIL) as the lowest bidder for the 17.647 km Package-C11 which comes under Nagpur metro phase 2  (43.8 km ).

Nagpur Metro Phase II map

Package-C11 (Nagpur Metro Phase 2)

Package -C11 includes the construction of three different viaducts for Reach 2B, 3A and 4A on the Nagpur phase 2.

Lines Reach Distance Location
Orange line 2A 5.9 km Cantonment – Kanhan 
Aqua line 3A 6.4 km Lokmanya Nagar – Hingra 
Aqua line 4A 5.3 km Prajapati Square – Transport Nagar 

Earlier, the construction of the viaducts for sections 2B, 3A and 4A was planned to be executed through 3 different packages- C-07, C-03 and C-04 consecutively. The tender procedure for these packages was scrapped. Subsequently, all three packages were merged into one Package- C-11.

In March 2024, the MahaMetro authority invited bids for Package-C-11 with an estimated cost of Rs.1010 crore. The deadline for the project is 1080 days. Later on in May, technical bids were announced with 5 bidders on the list.

Bidders

Bidders Bidders price 
Kalpatura Projects International Ltd.(KPIL)999 crore 
GR Infraprojects Ltd.(GRIL)1031.67 crore
ITD Cementation India Ltd.1075.65 crore
Tata Projects Ltd. (TPL)1183.93 crore

Kalpataru Projects International Ltd. bagged package C11 with Rs.999.0 crore, which is 1.09% less than the authority estimation.

Construction of stations on these viaducts comes under separate packages. Rail Vikas Nigam Ltd.( RNVL) was awarded Package- C-08 for constructing Reach- 2B’s six metro stations.

Advertisement1
InnoMetro_2026

BEML Initiates Production of Train Sets for Bangalore Metro’s Pink & Blue Lines

0
Bangalore metro trainset for blue and pink line.

Bangalore (Metro Rail News):On 31 August 2024, BEML, India’s leading rolling stock manufacturer, finally started the production of train sets for the Pink Line & Blue Line of the 73.92 km Bangalore Metro Phase 2 project.

In August 2023, BEML grabbed rolling stock contract 5RS-DM’s worth Rs. 3177 crore from BMRCL. Under this agreement, BEML is responsible for manufacturing 53 trains (each having 6 coaches). These trains will facilitate operations for:

  • Phase 2A (18.23 km) 
  • Phase 2B (37 km)
  • Pink Line (21 km)

A ceremony took place at BEML’s Bengaluru facility in CV Raman Nagar for the manufacturing of a new rolling stock prototype train. 

img76

Financial Aspects:

In March 2021, A Rs. 3,717 crore loan agreement was signed between the Japan International Cooperation Agency (JICA) and the government of India regarding the manufacturing of rolling stocks, CBTC signalling and platform screen doors.

Allotment of Trains Planned By BMRCL

  Phase   Line        Stations   Length No. of trains
Phase 2Pink lineKalena Agrahara station-  Nagawara station 21.386 km        16
Phase 2ABlue line Silk Board stations  – KR Puram stations 18.2 km      16
Phase 2B Blue line KR Puram station – Airport station37 km       21 

Key Features of New train-sets

img86
  • Bengaluru’s brand new train sets will feature six coaches, comprising two Driving Motor Car (DMC) and four Trailer Car (TC).
  • These trains will operate at a maximum design speed of 95 kmph and operational speed of 85 kmph.
  • These trains will be equipped with Alstom’s CBTC signalling and train-control solution. This advanced feature will empower trains to run “driverless” on GoA4 (grade of automation 4) for Unattended Train Operations (UTO) 

As per the press release BEML’s in-house engineering teams in Bangalore will be responsible for the “design and development” of these brand-new trains.  . high-tensile Austenitic stainless steel will be used in the manufacture of these trainsets. 

Keeping in mind the passenger’s comfort Each Metro car will incorporate two roof-mounted Saloon Air Conditioners to provide them with an air conditioning facility.

The trains will also feature an IP-based Passenger Announcement (PA) and Passenger Information System (PIS), along with a Passenger Saloon Surveillance System (PSSS) to provide real-time station information. 

Additionally, the trains will have electrically driven automatic doors synchronised with Platform Screen Doors to ensure passenger safety.

Advertisement1
InnoMetro_2026

PM Modi Shows Green Light to 3 Vande Bharat Express: UP, Tamil Nadu & Karnataka 

0
PM Modi flags off to three new Vande Bharat express train

Metro Rail News: On 31st August 2024, PM Narendra Modi flagged off three new Vande Bharat Express via video conferencing to enhance connectivity in Uttar Pradesh, Tamil Nadu, and Karnataka. 

Recently, inaugurated three Vande Bharat Express trains are:

  • Chennai Central to Nagercoil
  •  Madurai to Bengaluru Cantonment
  •  Meerut City-Lucknow
Vande Bharat
Trial Runs Underway for Puri-Rourkela Vande Bharat Express (Representational Image)

While adding three more Vande Bharat trains, the Prime Minister welcomes more connectivity to the route. More than 100 Vande Bharat Trains are operational, connecting 280 districts. 

BRIEF DESCRIPTION OF NEWLY INAUGURATED TRAINS:

  1. Chennai Central to Nagercoil Vande Bharat Train 
ROUTE TIMINGS STOPS 
From Chennai Egmore to Nagercoil It will leave Chennai Egmore at 5 am and reach Nagercoil at 1:50 Pm 
Will remain off on Wednesdays.
Tambaram, Villupuram, Tiruchirappalli, Dindugal, Madurai, Kovilpatti, and Tirunelveli 
 Will facilitate pilgrimage travelling to the divine Arulmigu Meenakshi Amman Temple, Madurai & Kumari Amman Temple, Kanniyakumari.

  1. Madurai to Bengaluru Cantonment Vande Bharat Train 
ROUTE TIMINGS STOPS 
From Madurai to Bengaluru Cantonment It will leave Madurai at 5:15 AM  and reach Bengaluru Cantonment at 1 PM.Will remain off on Tuesdays.Dindugal, Tiruchirappalli, Karur, Namakkal, Salem, and Krishnarajapuram Connect inter-state with providing connectivity to the temple in Madurai.
  1.  Meerut City to Lucknow Vande Bharat trains
ROUTE TIMINGS STOPS
From Meerut city to Lucknow It will leave Meerut City at 6:35 am and reach Lucknow Charbagh at 1:45 pm. It will remain off on Tuesdays.Moradabad and Bareilly.This will connect pilgrimage sites like Digambar Jain Temple, Mansa Devi Mandir, Surajkund Temple, and Augharnath Temple.

While inaugurating, PM Modi said, “Today, from North to South, a new chapter is being added to the Vikas Yatra of the country. From today, Vande Bharat Train service will start between Meerut – Lucknow, Madurai – Bengaluru Cantonment and Chennai – Nagercoil. 

Advertisement1
InnoMetro_2026

Surat Metro- TBM Narmada Completes Its Third Drive 

0
TBM Narmada final breakthrough Surat metro

Surat (Metro Rail News):Surat Metro project advances as TBM Narmada accomplishes Its last Breakthrough.

On 30 August 2024, Surat Metro witnessed another milestone on Line 1 when Gulermak – Sam India Builtwell JV’s TBM Narmada achieved its third and final breakthrough at Surat Railway Station for the Surat Metro Phase 1 Project.

TBM Narmada established the overall fifth and second-last breakthrough for Package CS2 / UG1. 

Binod Kumar
Image Credit: Binod Kumar

TBM Narmada’s Journey In Surat Metro Phase 1

First assignment Kapodra – Labheshwar Chowk.1.5km January 2024
Second assignment Labheshwar Chowk Station – Central Warehouse Station600m March 2024 
Current assignment Central Warehouse- Surat Railway Station.338m August 2024 

Note: The first breakthrough was still hidden as soil excavation is still in progress.

Antima
Image Credit: Antima

Package CS2 / UG1

In March 2021, Gulermak – Sam India JV grabbed underground Package CS2 / UG1’s construction contract, which spans 3.46 km connecting Kapodra station and Surat Railway Station. 

The scope of work under this package incorporates the construction of three twin tunnels and the 3 stations at ;

  • Kapodra
  •  Labheshwar Chowk
  •  Central Warehouse 

Surat Metro Phase 1 Project

Surat metro is an under construction Mass Rapid Transit System (MRTS) which spans 41.93 km, consisting of  2 corridors and 37 stations. 

Line 1 Sarthana station – Dream City station 22.77 km Total no. of stations: 20 

Line 2 
Bhesan station – Saroli station 19.26 km.Total  no. of stations:  18 

Advertisement1
InnoMetro_2026

11 Firms Bid for Geotechnical Work on Mumbai Metro’s Line 11

0
Mumbai Metro

Mumbai (Metro Rail News):  Mumbai Metro Rail Corporation Ltd. (MMRCL) has revealed that 11 bidders have signed up to conduct a geotechnical soil investigation for 18 km Mumbai Metro Line 11( Green Line ), which will connect Anik Bus Depot- SPM Chowk featuring 15 underground stations.

WhatsApp Image 2024 09 02 at 18.05.43
Map of the green line

Beforehand, MMRCL had invited bids for geotechnical work on the new alignment of Line 11. The deadline for the project is 90 days. This line will be the third underground line after Line 3 (Aqua Line) and Line 7 (Red Line).

Contractors Have Bids For The Project :

  1. CEG Test House & Research Centre Pvt. Ltd.
  2. C E Testing Company Pvt. Ltd.
  3. Genstru Consultants Pvt. Ltd. 
  4. Geomarine Dynamics India Pvt. Ltd.
  5. Idhitri Geoservices Pvt. Ltd.
  6. Independent Consultants and Technocrats
  7. Monarch Surveyors and Engineering Consultants Ltd.
  8. Myrtle Project and Consultancy Pvt. Ltd.
  9. Pureways Infra Pvt. Ltd. 
  10. SKW Soil and Survey Co
  11. S & R Geotechniques Pvt. Ltd.

 The lowest bidder has yet to be announced, and bids have been sent for technical evaluation.

Objective For Geotechnical Contract 

This geotechnical investigation aims to collect sufficient data on the sub-soil that will help to prepare detailed structure designs and the use of appropriate machinery, methods & technology during construction. This will also help ensure the least possible damage to existing structures during construction.

Work Description: The contract involves a geotechnical investigation of the new alignment of Mumbai Metro line 11. 

The report of the geotechnical survey should contain the following details:

  • Borehole details and locations with georeferenced coordinates
  • Geological characteristics of the area
  • Water table levels
  • Results of conducted tests
  • Foundation recommendations based on borehole data
  • Cut off values
  • Bearing capacities of Soil
  • Seismicity of the soil

According to the contract details, boreholes with 150 mm diameter should be drilled periodically after every 500 meters along the twin tunnel alignment. A total of 3 boreholes will be drilled at each station site. The depth of these boreholes will vary from 10 meters to 20 meters.

On corridor 11, 15 underground stations are planned to be constructed on Anik Bus Depot, Wadala Depot, CGS Colony, Ganesh Nagar, BPT Hospital, Sewri, Hay Bunder, Coal Bunder (Darukhana), Reay Road, Byculla, Nagpada Junction, Bhendi Bazaar, Crawford Market, CSMT Metro, Horniman Circle, and SPM Circle.

The Mumbai Metropolitan Region Development Authority (MMRDA) is responsible for the development of Green Line. The Green Line includes four lines( Line 4, Line 4A, Line 10, and Line 11).In 2023, the first section of the Green Line will be opened and connected with other metro lines through multiple interchanges along its route.

Advertisement1
InnoMetro_2026

Agra Metro Advances with 2 TBM Breakthroughs on Line 1 

0

Agra (Metro Rail News): Recently, the Agra Metro Phase 1 project witnessed 2 milestones on Line 1 when  Afcons-Sam India Consortium’s TBM Ganga and TBM Shivaji achieved breakthroughs at SN Medical College Station and Raja Ki Mandi, respectively.

TBM 324 and TBM S718C established the 13th and 14th breakthroughs for the 7.93 km underground Package AGCC-02 of Agra Metro Phase 1.

TBM Ganga’s Journey in Agra Metro Phase 1 

TBM Ganga, also known as TBM 324, is the 2nd TBM deployed for the Agra Metro Project.

1724851601622 1
Image Credit: Gaurav Chauhan

TBM Ganga’s journey so far records the construction of;

First Assignment Ramleela Maidan – Agra Fort Station 334m June 2023 
Second Assignment Agra Fort Station – Shahjahan Gardens Midshaft175m September 2023 
Third Assignment Shahjahan Gardens Midshaft – Taj Mahal Station 1175mDecember 2023 
Current Assignment Agra College Station – SN Medical College Station.525m August 2024 
1724851618676
Image Credit: Gaurav Chauhan

TBM Shivaji’s Journey in Agra Metro Phase 1 

TBM Shivaji, nicknamed TBM S-718C, is the 3rd TBM machine deployed for the Agra Metro Project.

1725039999713
Image Credit: Gaurav Chauhan

TBM Shivaji’s journey so far records the construction of; 

First assignment Taj Mahal Station -Taj Mahal Ramp 228m October 2023 
Second Assignment RBS Ramp -RBS College Station.734m December 2023 
Current Assignment RBC College- Raja Ki Mandi Station.685m August 2024 

Package AGCC-02 

In March 2022, Afcons – Sam India Consortium bagged Rs. 1819.79 crore underground Package AGCC-02 with a 48-month deadline.

The scope of work under this package includes the construction of twin tunnels connecting 7 stations at;

  • Taj Mahal
  • Agra Fort
  • Jama Masjid 
  • SN Medical College
  • Agra College
  • Raja Ki Mandi
  • RBS College 

Upcoming Developments 

Till date,14 breakthroughs have been achieved out of 18 breakthroughs planned for the Agra Metro Phase 1 project.

In future, The remaining breakthroughs will be recorded at: 

  • 2 breakthroughs at Agra College 
  • 2 breakthrough at Mankameshwar (Jama Masjid) 
Advertisement1
InnoMetro_2026

Chennai Metro’s TBM S81B Achieves Breakthrough at Otteri Station

0
TBM S81 B's breakthrough on line 3 in Chennai metro phase 2

Chennai ( Metro Rail News): Another day, another achievement. TBM S81 B with the nickname Kolli, commissioned by Tata Projects Ltd. recorded a breakthrough at Otteri station of Line 3 in 116.1km Chennai Metro Phase 2.

1724946015667 1
PICTURE BY BHAWAR SINGH YADAV

In July 2023, Tata Projects deployed TBM (Kolli ) on the south shaft of Ayanavaram Station of the 45.8km Line 3 ( Mandharam station – Siruseri SIPCOT ). After covering a distance of about 903 m TBM Kolli reached Otteri station in just 13 months.

TBM S18 B ( Kolli) 

Kolli is a Terratec Earth Pressure Balance (EPB) machine with 06.61 km. During the excavation, the machine encountered more than 100 bore wells and to avoid any inconvenience it took two sharp curves of radius 220 m and 280 m respectively.

1724946009814 1
IMAGE CREDIT TO BHAWAR SINGH YADAV

After its first breakthrough in the Pune metro, In December 2022, TBM S18 passed the FAT   (Factory Acceptance Test ) before being deployed in the Chennai Metro Phase 2.

Scope Of Work  

This assignment of Tbm Kolli falls under Package TU-01.  In May 2021, Chennai Metro Rail Ltd. (CMRL) awarded Tata Projects with Package TU-01  with a 42-month deadline. The total cost of the project is Rs 1999 crore. Package TU-01 is a 9 km long section on Line 3 of Chennai metro Phase 2.

The work scope of TBM Kolli and 6 other TBMs under Package TU-01 includes the construction of a 9 km twin tunnel (totalling 18 km) from the TBM retrieval shaft near Venugopal (line 5) to Kelly station (Line 3) and the construction of diaphragm walls and entry and exit structures of Madhavaram Milk Colony Station, Murari Hospital Station, Ayanavaram Station and Purasaiwakkam High Road Station. 

1724946016981
PHOTO: BHAWAR SINGH YADAV

As of now, Tata Projects Ltd. has recorded 6 tunnel breakthroughs under the Package -TU-01.

TBM STATIONDISTANCEYear (breakthrough)
TBM S98 (Anaimalai)Venugopal Nagar 415 mJune 2023 
TBM S96 (Nilgiri)Madhavan High Road 1.4 kmAugust 2023
TBM S99 (Servarayan)Venugopal Nagar 415 mSeptember 2023
TBM S97 (Podhigai )Madhavaran High speed1.4 kmNovember 2023
TBM S98 (Anaimalai)Otteri Station925 mJune 2024
TBM S81B (Kolli) -current assignmentOtteri Station 903 mAugust 2024
Advertisement1
InnoMetro_2026

5 Firms Bid For Thane Metro’s DDC-01 Package 

0
Vizag Metro
Metro Representational image.

Thane (Metro Rail News): On 29 August, after the opening of technical bids, MMRCL revealed the names of 5 Firms that have submitted bids for Thane Metro’s first Detailed Design Consultant (DDC-01) contract. 

In early August, Maha-Metro floated tenders for this contract with an estimated budget of Rs 3.82 crore and a 36-month deadline.

Scope of Thane Metro’s Package DDC-01 

The appointed contractor under this package will be responsible for providing Detailed Design Consultancy Services for Thane Metro’s 6 elevated stations:

  • Dr. Kashinath Ghanekar Natyagraha
  • Manpada 
  • Dongripada
  • Vijay Nagari 
  • Waghbil 
  • Waterfront 

Bidders

The bidders for the Package DCC-01 are: 

  • Enia Design Pvt. Ltd.
  • LKT Engineering Consultants Ltd.
  • RITES Ltd.
  • STUP Consultants Pvt. Ltd.
  • SYSTRA MVA Consulting (India) Pvt. Ltd.

Thane Metro Project

cabinet approves thane integral ring metro rail project the v0 lsisxkzkk2jd1
Image Credit: Reddit

Thane Metro, also referred as the Thane Integral Metro Project, has recently received approval from the Central Government’s Cabinet with an estimated total budget of Rs. 12,200 crore and a 2029 deadline. 

Thane Metro will consist of a single corridor. The elevated route will span 26 km with 22 stations and a 3km underground twin tunnel section with 2 underground stations. 

The Process Ahead

The Bids would go through a technical evaluation. Subsequently, MMRCL will reveal the financial bids of technically qualified bidders to identify the L1 (Lowest Bidder) for this Package.

Advertisement1
InnoMetro_2026

MPMRCL MD Inspects Indore Metro from SC-03 to Gandhi Nagar Depot 

0
INSPECTION ON INDORE METRO

Indore (METRO RAIL NEWS): Shri S. Krishna Chaitanya, IAS, Managing Director of Madhya Pradesh Metro Rail Corporation, conducted a comprehensive inspection of the Indore Metro Super Priority Corridor from the SC-03 station to the Gandhi Nagar Depot by metro train. The Managing Director also inspected the underground route.

During the site inspection, the Managing Director reviewed the progress and intricate aspects of various components constructed for train operations at SC-03, SC-04, SC-05, SC-06 stations, and Gandhi Nagar station, including the station control room, ticket office machine room, signalling equipment room, and telecom equipment room.

1724853399572

Following the inspection, the Managing Director conducted a review meeting with all stakeholders at the metro office to assess the current progress and achievements against the set targets.

Guidelines For Contractors of Indore Metro Project

  • The Managing Director instructed the project contractors to ensure a proper drainage system at the depot.
  • To complete the entry and exit points of the stations as soon as possible.
  • He urged all metro project officials, general consultant representatives, and contractors to contribute their best efforts to bring the metro project to fruition, enabling the metro service to be made available to the public at the earliest.
  • He also emphasised removing the unnecessary barricades and reconstructing the roads to smoothen the traffic near the metro construction site
  • He instructed that the system work at these stations be completed promptly.
  • He explained the dependency of the depot station in the operation of the metro train.
Routmap Indore page 0001
Route Map

Meeting Attendants 

At the Gandhi Nagar Depot, the Managing Director discussed the significance of the depot in metro train operations with senior officials, the general consultant, and contractors. 

The site inspection meeting was attended by senior officials, including Shri Shobhit Tandon, Director (Systems), Shri Ajay Gupta, Director (Projects), Shri Ajay Kumar, General Manager (Civil – Underground), Shri Ranveer Singh Rajput, General Manager (Civil – Elevated), Shri Arun Kumar Srivastava, General Manager (S&T and Rolling Stock), Shri Rajeev Kumar Goyal, General Manager (Admin), along with representatives of the general consultant and metro construction contractors

Inspection’s Reviews 

During his first inspection of the Indore Project, the Managing Director expressed satisfaction with the work done so far and reiterated the commitment to a safe, seamless, and environmentally friendly metro that aligns with public aspirations.

Advertisement1
InnoMetro_2026

Kanpur Metro: TBM Vidyarthi Starts its 2nd Drive Towards Transport Nagar Station

0
TBM S639B

Kanpur (Metro Rail News): On 28 August 2024, Afcons-Sam India Consortium deployed TBM S- 639B (Vidyarthi) for its second assignment from Transport Nagar Ramp to Transport Nagar Metro Station on Line 1 under Package KNPCC-06 of the Kanpur Metro Phase 1 Project.

For its current assignment, TBM S-639B will construct an approximate 350 m-long tunnel for the downline towards Transport Nagar Metro Station.

TBM Vidyarthi of Kanpur Metro
Representational image

TBM Vidyarthi’s Journey in Kanpur Metro

In December 2023, TBM S-639B, nicknamed Vidyarthi, started its journey as the fourth TBM deployed to facilitate the construction of twin tunnels on Line-1, which spans 23.78km between IIT Kanpur and Naubasta.

TBM S-639B began its first drive from Kanpur Central Station, covering a 1250m long distance in 6 months; TBM achieved a breakthrough at Nayaganj Station in June 2024.

Till date, Afcons – Sam India has achieved 2 out of 8 breakthroughs – both were recorded at Nayaganj Station in March and June 2024.

KNPCC-06 Package 

In March 2022, Afcon Sam India Consortium bagged package KNPCC-06 at Rs. 1087.67 crore with a 36-month deadline.  

KNPCC-06 is a 2nd underground package for the Kanpur Metro Line-1. This Package will connect Nayaganj Station and Transport Nagar Ramp through 3 underground stations at 

  • Kanpur Central
  • Jhakarkatti
  • Transport Nagar

Future Prospects

Once TBM S-639B achieves a breakthrough at Transport Nagar Station, it will be moved from its station box to construct tunnels at Jhakarkatti Station.